You'll find that our MSP-Practitioner exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these MSP-Practitioner sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any MSP Practitioner, 5th edition Exam practice test comfortably within the allotted time.

Question # 11

The engineering department has been asked to produce a weekly report for the programme board. The report will include data on how many new water meters have been installed in the last seven days. The programme manager is writing the assurance approach. The engineering department report has been included as part of the first line of defence.

Is this an appropriate application of the assurance’ theme, and why?

A.

Yes, because the increased number of gas and electricity customers is dependent on the new water meters being installed

B.

Yes, because the programme board should use the report to monitor the progress of ongoing engineering work

C.

No, because the reporting progress by the engineering department demonstrates application of the ‘decisions ' theme

D.

No, because everyone in the programme should have access to progress information, not just the programme board

Question # 12

Which of following groups can be a stakeholder for building a city programme?

A.

Employees

B.

Political leadership

C.

People interested in being residents

D.

All of above

Question # 13

Which of following best defines Outcomes?

A.

Deliverable of a project

B.

Completed set of project outputs

C.

Measurable improvement resulting from outcomes perceived as advantage

D.

New operational state achieved after transition of capability in live operations

Question # 14

The programme manager has analysed the costs of using an expert external company to work on the Research and Development Project. Although using the external experts is likely to produce a higher quality solution which would lead to increased organizational adoption, the SRO has insisted that the project only uses internal staff to minimize costs.

Is the SRO ' s response an appropriate application of the ‘deploy diverse skills ' principle, and why?

A.

Yes, because the programme should minimize its reliance on external suppliers to minimize costs

B.

Yes, because it is important to build internal skills for the future during the programme

C.

No, because the sponsoring group should approve decisions on how the programme will be resourced

D.

No, because programme delivery should use the right mix of skills to achieve the outcomes of benefit

Question # 15

The programme is in the middle of Tranche 2. A new SRO has been appointed. To understand the current status of the programme, the SRO has asked for a health check to be carried out. The programme office lead has recruited an external consultant to carry out the health check.

Which assurance success factor does this demonstrate?

A.

Independence

B.

Accountability

C.

Coordination

D.

Risk appetite

Question # 16

The programme is starting Tranche 1 and there is a lot of dissatisfaction in the workforce about the planned merging of the engineering roles. The programme board has made some proposals on how to deal with this issue but is unsure whether to involve the sponsoring group.

According to the ‘decisions’ theme, which document should be consulted to clarify whether it is necessary to escalate this issue to the sponsoring group?

A.

Programme strategy: issue resolution approach

B.

Issue register

C.

Programme strategy: decision-making approach

D.

Decision register

Question # 17

Which of following Best defines capital cost?

A.

Costs associated to roles for programme management

B.

Costs of activities associated in realizing the benefits

C.

Cost of BCM and change team

D.

Cost of fixed assets

Question # 18

The project manager for the Customer Processes Project has heard a rumour that Web ‘n’ Go is having financial difficulties. If this company becomes bankrupt, they will not be able to supply the agreed customer web-based portal services which are required to enable the single customer services call centre. The programme manager has added this risk to the programme risk register.

Is this action by the programme manager an appropriate application of the ‘design’ theme, and why?

A.

Yes, because the web-based portal services are needed to reduce staff levels and associated costs

B.

Yes, because projects should escalate risks that could affect the project ' s objectives to the programme manager

C.

No, because the vision and target operating model should be developed as part of the ‘design’ theme

D.

No, because this is just a rumour and no action is needed until Web ‘n’ Go is actually bankrupt

Question # 19

In which MSP theme would you expect to find the POTI model?

A.

Vision

B.

Blueprint Design and Delivery

C.

Leadership and Stakeholder Engagement

D.

Planning and Control

Question # 20

There is a risk that the utilities market is changing, with green energy solutions becoming more attractive to customers. As UU does not currently offer this type of green energy, the benefits gained from cross-selling electricity and gas to current water customers may be overestimated.

Which activity is relevant in the ‘plan’ phase of the Plan-Do-Check-Act (PDCA) cycle?

A.

Scheduling daily monitoring of how many current water customers also buy either electricity or gas services

B.

Analysing the market trends for utility companies offering green energy solutions and how many customers they gain

C.

Surveying customers to assess if they are aware of UU ' s new green tariff introduced in response to this risk

D.

Purchasing and selling a small amount of energy from renewable sources to provide an element of environmental credibility