You'll find that our MSP-Practitioner exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these MSP-Practitioner sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any MSP Practitioner, 5th edition Exam practice test comfortably within the allotted time.

Question # 21

Which of the following statements is NOT TRUE?

A.

The SRO is accountable for confirming Programme Mandate.

B.

The SRO is accountable for the Programme Brief.

C.

The Programme Manager is responsible for the Vision Statement.

D.

The Programme Manager is responsible for the Blueprint.

Question # 22

Which document is created from Programme mandate and works as input for Business Case?

A.

Programme preparation plan

B.

Blueprint

C.

Programme Brief

D.

Programme management plan

Question # 23

The programme is in the ' identify the programme ' process. The CEngO is concerned that the engineering department will not be able to deliver the proposed Engineering Department Work at the same time as supporting the research into new smart meters and water leak detection equipment. The programme board believes that the engineering department will be able to manage, if the programme is planned optimally.

Which role is MOST LIKELY to approve the programme board ' s recommendation?

A.

Senior responsible owner

B.

Programme manager

C.

Business change manager

D.

Programme office lead

Question # 24

Which of the following is an influencer type of stakeholder?

A.

Management board

B.

Business partner

C.

Media

D.

Supplier

Question # 25

Who approves Business Case?

A.

Sponsoring Group

B.

SRO

C.

Programme Manager

D.

BCM

Question # 26

The programme is in the ‘close the programme ' process. All the projects have been successfully completed, and the capabilities have been delivered. However, some of the new sales roles are still to be recruited in order to deliver increased sales. The programme manager has passed the management of this remaining work to the HR Director.

Is this an appropriate action for the programme manager to take, and why?

A.

Yes, because the remaining recruitment should be handed to the HR Director to ensure that the benefits are realized

B.

Yes, because the impact of closure on the HR Director needs to be understood and managed well

C.

No, because programme information should be up-to-date and archived before the programme can be formally closed

D.

No, because the SRO should be responsible for disbanding the programme team and closing the programme

Question # 27

The programme is in the ‘plan progressive delivery ' process for the first time and the business case has been confirmed. The programme manager is now attempting to get commitment from the Call Centre Manager that they will provide the staff needed in Tranche 1.

Is this an appropriate application of the ‘plan progressive delivery ' process, and why?

A.

Yes, because the Call Centre Manager should commit the resources before Tranche 1 begins

B.

Yes, because resources from the call centres will be critical to the success of Tranche 1

C.

No, because the sponsoring group should commit the resources before Tranche 1 begins

D.

No, because resources should be appointed by the project management team when Tranche 1 begins

Question # 28

The programme is in the ‘design the outcomes’ process. One risk to the programme is that new and improved meter technology may be developed during implementation. This risk has been assessed as high probability and high impact and is therefore a high priority. The initial delivery approach proposes a phased roll-out of the meters so that the programme can exploit any new technology that emerges. The CTO has been appointed as the owner of this risk.

Is this appointment an appropriate application of the identify and prioritize risks’ activity, and why?

A.

Yes, because the exposure created by this risk warrants the appointment of a senior risk owner

B.

Yes, because this risk would impact on the expected increased number of gas and electricity customers

C.

No, because the phased roll-out should be documented as landing points during the ‘develop the target operating model ' activity

D.

No, because the phased roll-out should be planned for as part of the ‘develop programme plans’ activity

Question # 29

In delivering the capability, which role is responsible for aligning projects with programme objectives?

A.

SRO

B.

BCM

C.

Programme Manager

D.

Programme Office

Question # 30

UU has partnered with a supplier who has expertise in training and change management. The supplier will provide a virtual change office function, helping staff in the business prepare for the significant transformation ahead and ensuring that the benefits will be realized. However, these change management services are very costly.

Is this an appropriate application of the ‘justification’ theme, and why?

A.

Yes, because the costs are justified by the support provided to staff members and the benefits to be delivered

B.

Yes, because the money saved by having a single call centre will provide contingency to pay for the change office

C.

No, because the BCM should use a network of internal change agents to support the changes in order to save money

D.

No, because defining the need for additional supporting offices is part of tailoring the ’organization’ theme