Last Update 11 hours ago Total Questions : 180
The TOGAF Enterprise Architecture Combined Part 1 and Part 2 Exam content is now fully updated, with all current exam questions added 11 hours ago. Deciding to include OGEA-103 practice exam questions in your study plan goes far beyond basic test preparation.
You'll find that our OGEA-103 exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these OGEA-103 sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any TOGAF Enterprise Architecture Combined Part 1 and Part 2 Exam practice test comfortably within the allotted time.
Please read this scenario prior to answering the question
You are employed as an Enterprise Architect for a company that supplies products for industrial production automation. You are part of an Enterprise Architecture (EA) team that has responsibilities across the company.
The company has multiple manufacturing plants where it assembles both standard and customized products. Each of these plants operates its own planning and production scheduling systems, as well as applications and control systems that drive the automated production line.
During a recent management meeting, the agenda included discussion of how a competitor company had improved production efficiency by replacing multiple planning and scheduling systems with a single cloud-based system. This had reduced lifecycle costs through reduced duplication, lowered software maintenance costs, and supported incremental replacement. The CIO claimed the company ' s current systems architecture is already optimized. However, as the competitor has reported better financial results, the CEO has requested an investigation of a cloud-based solution.
In response, the Architecture Board approved a Request for Architecture Work to find out if such an architecture transformation would lead to efficiency improvements. You have been asked to help the architecture team with this project.
A concern of the plant managers is the safety and dependability of using a remote centralized system for planning and scheduling production. The system they choose must also be able to work with the local partners in the supply chain at each plant.
The company has an Enterprise Architecture (EA) practice and uses the TOGAF standard as the basis for its work. It has been running for many years and has established governance and development processes for EA. The Chief Information Officer (CIO) sponsors the Enterprise Architecture program.
Refer to the scenario
You have been asked to describe how you will start the architecture project.
Based on the TOGAF standard, which of the following is the best answer?
Please read this scenario prior to answering the question
You have been appointed as senior architect working for an autonomous driving technology development company. The mission of the company is to build an industry leading unified technology and software platform to support connected cars and autonomous driving.
The company uses the TOGAF Standard as the basis for its Enterprise Architecture (EA) framework. Architecture development within the company follows the purpose-based EA Capability model as described in the TOGAF Series Guide: A Practitioners ' Approach to Developing Enterprise Architecture Following the TOGAF® ADM.
An architecture to support strategy has been completed defining a long-range Target Architecture with a roadmap spanning five years. This has identified the need for a portfolio of projects over the next two years. The portfolio includes development of travel assistance systems using swarm data from vehicles on the road.
The current phase of architecture development is focused on the Business Architecture which needs to support the core travel assistance services that the company plans to provide. The core services will manage and process the swarm data generated by vehicles, paving the way for autonomous driving in the future.
The presentation and access to different variations of data that the company plans to offer through its platform poses an architecture challenge. The application portfolio needs to interact securely with various third-party cloud services, and V2X (Vehicle-to-Everything) service providers in many countries to be able to manage the data at scale. The security of V2X is a key concern for the stakeholders. Regulators have stated that the user ' s privacy be always protected, for example, so that the drivers ' journey cannot be tracked or reconstructed by compiling data sent or received by the car.
Refer to the scenario
You have been asked to describe the risk and security considerations you would include in the current phase of the architecture development?
Based on the TOGAF standard which of the following is the best answer?
Full Scenario
You are employed as an Enterprise Architect in an Enterprise Architecture (EA) team at a food production and distribution company. The main goal of the company is to increase profit while meeting the needs of consumers for its products. Its customers want food that is produced sustainably, safely, and transparently, while reducing environmental impact.
The company has an Enterprise Architecture practice based on the TOGAF standard, using it as the method and guiding framework. The Chief Information Officer (CIO) is the sponsor of EA practice.
The business is a highly mechanized agricultural operation where business capabilities, including planting, harvesting, processing, packaging, and distribution, rely heavily on technology and machinery. The use of EA has enabled the decision makers to have valuable insights into the different aspects of the business.
The warmer climate has led to less successful farming, and the company is growing fewer crops than before. Also, prices for energy, feed, fuel, and fertilizer have gone up. This has caused a big drop in earnings. Due to the rising costs and lower profits, the company has been unable to do as much to help the environment. It especially has struggled to reduce its carbon emissions.
In response to the situation, the Chief Executive Officer (CEO) has decided that big changes are needed, that will lead both to improved crop production and profitability. They must look to all aspects of the business. This includes looking at the mix of crops to mitigate for the change in climate. The company will also cease to process its own crops and will sell off its processing facilities. Thus, the target market will change, and the end-products will be different and more varied. A formal request for architecture change has been approved. At this stage there is no fixed scope, shared vision, or objectives.
Question:
What is the best approach for architecture development to realize the CEO’s change in direction for the company?
Based on the TOGAF standard which of the following is the best answer?
Please read this scenario prior to answering the question
You are employed as an Enterprise Architect within a clinical research and health
technologies company. The company is dedicated to transforming healthcare with
new ideas and advancements. The company has multiple divisions that cover different
aspects of the business.
The company ' s Enterprise Architecture (EA) department has mature, well-developed
architecture governance and development processes following the TOGAF standard.
In addition to the EA program, the company has a number of management
frameworks in use. The Architecture Board includes representatives from each
division of the company. The Chief Information Officer (CIO) is the sponsor of the
Enterprise Architecture program. The CIO has actively encouraged architecting with
agility within the EA department as the preferred approach for projects.
Many of the company ' s rivals have begun using Artificial Intelligence (Al) in their
operations, and the indications are that this will be transformative for healthcare
delivery. This is something the EA department has been interested in for a while, and
they had recently submitted an architecture Change Request which was approved. As
a result, the CIO has approved a Request for Architecture Work to investigate the
implementation of Al in the company.
Areas for evaluation include:
How can staff use Al daily in their current roles?
How can Al enhance access to care for patients, and how to make that experience
seamless?
How can Al offer new workplace platforms and tools to increase efficiency?
Some of the top managers are worried about a change in the way of working, and if it
will achieve the goals. Many are not confident that the company ' s risk management
processes are adequate for a company-wide integration of generative Al. There are
also questions from staff about whether enough specific guidelines and polices have
been put in place for responsible use of Al.
Refer to the scenario
You have been assigned to the architecture development and asked how to address
the concerns and manage risk for the project. How do you begin?
Based on the TOGAF standard which of the following is the best answer?
Please read this scenario prior to answering the question
You are employed as an Enterprise Architect at a company. The company manages
large-scale farming operations with food production, processing, and distribution. The
goal of the company is to maximize profit while satisfying the needs of consumers for
its products. Its customers demand food that is produced sustainably, safely, and
transparently, while reducing environmental impact.
The business is highly mechanized, and this mechanization has brought about a
decrease in the number of workers needed, together with a focus on agricultural
engineering to improve the efficiency of its farms, its processing facilities, and the
overall enterprise. As part of this, the company has established an Enterprise
Architecture (EA) practice based on the TOGAF standard, using it as the method and
guiding framework. The Chief Information Officer (CIO) is the sponsor of EA practice.
The practice has adopted an iterative approach for its architecture development. This
has enabled the decision makers to have valuable insights into the different aspects
of the business.
In recent years there have been a series of bad harvests, and a major reduction in
yields of the main crop produced by the company. This combined with an increase in
costs for energy, feed, fuel, and fertilizer, had led to a significant decrease in profits.
The rising costs and lower profits mean that the company is unable to take as much
planned action on climate measures as it would like, such as reducing its carbon
footprint. The Chief Executive Officer (CEO) has stated that big changes are needed
to improve yields and profitability.
The outline strategy for change, includes new products, and new markets. The
company will switch to a mix of crops rather than depend on a main crop and will
allow use of its processing facilities by third parties. This is a major decision, and the
CEO has stated a desire to repurpose and reuse rather than replace so as to manage
the risks and limit the costs.
The CIO has assigned the EA team to manage this project. The CIO has stated that
although the overall objective is known, the EA team are expected to define the
scope, a shared vision, and the requirements.
Refer to the scenario
You have been asked to recommend the best approach for architecture development
to realize the CEO ' s change in direction for the company.
Based on the TOGAF standard which of the following is the best answer?
Please read this scenario prior to answering the question
You are employed as an Enterprise Architect in a team at a large company. The
company sells luxury food and drinks in more than 10,000 stores worldwide. The
company is a leader in using technology to connect with its customers. This includes
online ordering, mobile apps, and rewards programs. The company is also famous for
bringing new ideas to the market, like ordering through apps, using Al to suggest
personalized options, self-service pickup stations, and changing prices based on
demand.
The stores are open every day. They send timely sales data to a central system that
manages inventory. This system can predict what products are needed, adjust how
much stock there is, and order more stock automatically. The stores and the main
inventory system work directly with the mobile apps, allowing orders to be made
online. The central inventory system is located at the company ' s main data center.
The company will merge with a major competitor. This competitor has a synergistic
business. Leaders from both companies have told shareholders that the merger will
happen fast. There will be minimal impact for customers. All stores will keep the
current brand names. They will combine their systems, choosing the best ones to use.
This means their store management and back-office systems will become one. They
will stop using duplicate systems and use one main system to manage the stores.
They will also cut down on the number of back-office applications they use.
The Request for Architecture Work to oversee the merger has been approved.
Stakeholders, concerns, and business requirements have been identified. The
stakeholders have made it clear that they expect to continue to be able to innovate
quickly, and that changes should not restrict that capability. The scope of what is
inside and what is outside the architecture efforts has been confirmed. The next step
is to revisit and review the Architecture Principles, as they form part of the constraints
on architecture work.
Business Continuity is essential given that the business depends on real-time
ordering and automated inventory management. During the systems integration,
maintaining service for customers and inventory operations must be prioritized
Refer to the scenario
You have been asked to identify the most relevant Architecture Principles for the
merger besides Business Continuity.
Based on the TOGAF standard, which of the following is the best answer?
[Note: You should assume that the company follows the example set of Architecture
Principles provided in the TOGAF standard, ADM Techniques, Architecture Principles
chapter.]
Please read this scenario prior to answering the question
You are employed as an Enterprise Architect within a multinational company. The
company has been very successful and has been buying companies around the
world. This has led to a growing number of manufacturing divisions in various
locations with a complex supply chain.
The top management recently expressed concerns about the company ' s effectiveness
because of its multiple data centers and duplicate applications. The EA team has
been working on a project to solve this issue. An analysis shows that supply chain
issues have led to not enough products being produced to meet all the customer
demand.
A strategic architecture has been defined to help meet customer demand and manage
the supply chain more effectively. The strategic architecture involves combining
different Enterprise Resource Planning (ERP) applications that are currently used
separately in the company ' s production sites.
Each division has finished the Architecture Definition documentation to address their
own specific manufacturing needs. The Enterprise Architects have agreed an overall
strategy for the migration. They have defined a set of work packages that address the
gaps found. They have defined the intermediate architectural states between the
Baseline and Target architecture to add a new ERP environment into the company.
Because of the risks posed by this change from the current environment, the
architects have recommended that a phased approach should be taken to implement
the target architecture with several stages of change. They have created a draft
roadmap with the implementation process estimated to take over two years.
The company has an established Enterprise Architecture (EA) practice and follows the
TOGAF Architecture Development Method. The company also uses various
management frameworks such as business planning, project/portfolio management,
and operations management. The EA program is sponsored by the Chief Information
Officer (CIO). In your role as an Enterprise Architect within the EA team, you work
closely with the important stakeholders from the various divisions within the company.
Refer to the scenario
You have been assigned to plan the next steps for the migration. Which approach will
you choose?
Based on the TOGAF standard which of the following is the best answer?
Full Scenario (Complete and Unmodified):
You are employed as an Enterprise Architect at a healthcare company. The company operates over 250 hospitals and is dedicated to transforming healthcare with new ideas and advancements. The company has multiple divisions including surgery centers, freestanding emergency departments, urgent care clinics, and physician practices. They also develop and supply a range of products and services, many with specialized systems and clinical needs.
The company ' s Enterprise Architecture (EA) department has been operating for several years and has mature, well-developed architecture governance and development processes following the TOGAF standard. The Chief Information Officer (CIO) is the sponsor of the Enterprise Architecture program.
Healthcare is a highly controlled sector, and the company must maintain robust security practices to keep patient information private and prevent data breaches. The company shares electronic health records with multiple providers and has standardized its medical coding for billing and reporting.
Many of the company’s rivals have begun using Artificial Intelligence (AI) in their operations, and the indications are that this will be transformative for healthcare delivery. This is something the EA department has been interested in for a while, and they had recently submitted an architecture Change Request which was approved. As a result, the CIO has approved a Request for Architecture Work to implement AI-based solutions in the company.
The project has been established and you have been assigned to work on it. Stakeholders, concerns, and business requirements have been identified. The stakeholders have made it clear that timely implementation of changes can be life-critical, and that changes should be focused on improving patient outcomes. They also have a concern about disruption due to the changes and require the systems to preserve clinical data access and maintain critical life-support systems during any outages.
The scope of what is inside and what is outside the architecture efforts has now been confirmed. Your task is to revisit and review the Architecture Principles, as they form part of the constraints on architecture work.
Question:
The EA team leader has asked you to explain which Architecture Principles are most relevant for this project.
Based on the TOGAF standard, which of the following is the best answer?
(Assume the company follows the example Architecture Principles from the TOGAF ADM Techniques – Architecture Principles chapter.)
Please read this scenario prior to answering the question
You are the Lead Enterprise Architect at a major agribusiness company. The company ' s main harvest is lentils, a highly valued food grown worldwide. The lentil parasite, broomrape, has been an increasing concern for many years and is now becoming resistant to chemical controls. In addition, changes in climate favor the propagation and growth of the parasite. As a result, the parasite cannot realistically be exterminated, and it has become pandemic, with lentil yields falling globally.
In response to the situation, the CEO has decided that the lentil fields will be used for another harvest. The company will also cease to process third-party lentils and will repurpose its processing plants. Thus, the target market will change, and the end-products will be different and more varied.
The company has recently established an Enterprise Architecture practice based on the TOGAF standard as method and guiding framework. The CIO is the sponsor of the activity. A formal request for architecture change has been approved. At this stage there is no fixed scope, shared vision, or objectives.
Refer to the scenario
You have been asked to propose the best approach for architecture development to realize the CEO ' s change in direction for the company.
Based on the TOGAF standard which of the following is the best answer?
Please read this scenario prior to answering the question
Your role is that of a consultant to the Lead Enterprise Architect to an international supplier of
engineering services and automated manufacturing systems. It has three manufacturing plants
where it assembles both standard and customized products for industrial production
automation. Each of these plants has been operating its own planning and production
scheduling systems, as well as applications and control systems that drive the automated
production line.
The Enterprise Architecture department has been operating for several years and has mature,
well-developed architecture governance and development processes that are based on the
TOGAF Standard. The CIO sponsors the Enterprise Architecture.
During a recent management meeting, a senior Vice-President highlighted an interview where
a competitor company ' s CIO is reported as saying that their production efficiency had been
improved by replacing multiple planning and scheduling systems with a common Enterprise
Resource Planning (ERP) system located in a central data center. Some discussion followed,
with the CIO responding that the situations are not comparable, and the current architecture is
already optimized.
In response, the Architecture Board approved a Request for Architecture Work covering the
investigations to determine if such an architecture transformation would lead to improvements
in efficiency. You have been assigned to support the architecture team working on this project.
A well-known concern of the plant managers is about the security and reliability of driving their
planning and production scheduling from a remote centralized system. Any chosen system
would also need to support the current supply chain network consisting of local partners at
each of the plants.
Refer to the scenario
You have been asked to explain how you will initiate the architecture project.
Based on the TOGAF Standard, which of the following is the best answer?