Summer Sale Special 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: ex2p65

Exact2Pass Menu

Question # 4

Which of the following best describes the difference between the current state and the desired future state in project management?

A.

The current state is a high-level view of the project scope, and the desired state is what is happening right now.

B.

The current state is where the business is now, and the desired state is where the project is going to take the business.

C.

The current state is a high-level view of the project scope, and the desired future state is the specific outcome the business wants.

D.

The current state defines the specific outcome the business wants, and the desired state documents what is happening now that prevents it.

Full Access
Question # 5

Which of the following would be considered operational security?

A.

Mobile device compliance

B.

Background screening

C.

Multifactor authentication

D.

Facility access

Full Access
Question # 6

A project coordinator has started a new project and is reviewing the following characteristics provided by the customer:

• Two developers

• High uncertainty about existing systems

• Risk of frequent requirement changes

• Tight deadlines

Which of the following project methodologies would be best to use in this situation?

A.

PRINCE2

B.

Scrum

C.

SAFe

D.

XP

Full Access
Question # 7

A system was implemented, and testing was successfully completed. Which of the following should the project manager do NEXT?

A.

Validate against the scope statement and ask for sign-off.

B.

Run a control chart to ensure the quality of the deliverables.

C.

Review the risk register and close up residual risks.

D.

Start the training and handoff for the operations team.

Full Access
Question # 8

During the execution phase of a project, the project team faced an unexpected website downtime The project manager how a brainstorming session and the team identified causes and effects tor the problem Now the project team needs to analyze and determine whether the particular cause and effect are related by using one of the following charts. Which of the following should the team use?

A)

B)

C)

D)

A.

Option A

B.

Option B

C.

Option C

D.

Option D

Full Access
Question # 9

Hackers are attempting to extract large amounts of data to sell on the dark web. Which of the following steps should a project manager take next to mitigate this risk?

A.

Update the issue log.

B.

Apply the contingency plan.

C.

Transfer the risk.

D.

Submit a change request.

Full Access
Question # 10

During the execution phase, a new PM was assigned to a project. The PM received a request to add new functionality to the system that is being developed. While the PM was conducting a preliminary review with the team, the technical lead highlighted that this functionality request was rejected during the planning phase. Which of the following documents is the best source for the PM to use to confirm this assertion?

A.

Issue log

B.

Scope statement

C.

Risk report

D.

Change log

Full Access
Question # 11

A project manager is meeting with business stakeholders to define the time frame for a go-live to occur without impacting business operations. Which of the following is the project manager working on?

A.

Validation check

B.

Downtime window schedule

C.

Customer notifications

D.

Risk analysis

Full Access
Question # 12

Which of the following would most likely take place when a team reviews the backlog and presents the status of each task?

A.

Sprint retrospective

B.

Sprint review

C.

Sprint planning

D.

Daily Scrum

Full Access
Question # 13

Which of the following activities are performed during the closing phase? (Select three).

A.

Requesting project charter sign-off

B.

Recognizing project team efforts and rewarding team members

C.

Working with the financial team to obtain return of investment

D.

Revoking resource credentials from the system

E.

Updating the risk register with new findings

F.

Informing the functional manager about the release of resources

G.

Monitoring project team performance

Full Access
Question # 14

A project manager was concerned the results were not fulfilling the expectations at the end of the execution phase. After reviewing the SOW, the project manager realized the vendor delivered everything included in the contract. Which of the following actions should the project manager complete next?

A.

Perform a gap analysis.

B.

Escalate the issue.

C.

Submit a change request.

D.

Approve deliverables.

Full Access
Question # 15

Which of the following should be the PRIMARY basis for establishing metrics that measure the effectiveness of an information security program?

A.

Residual risk

B.

Regulatory requirements

C.

Risk tolerance

D.

Control objectives

Full Access
Question # 16

A critical business initiative introduced new processes and technology to the organization. Which of the following approaches should be used to ensure the deliverables are increasingly adopted and leveraged by the organization over time?

A.

Creation of a social news forum

B.

Management directives to use the new system

C.

New user kickoff meeting

D.

Monthly feedback and training sessions

Full Access
Question # 17

Following the approval of a change by the CCB, which of the following should a project manager consider next when deploying a new networking device into an existing production environment?

A.

Maintenance window

B.

Risk assessment

C.

Operational security

D.

Validation check

Full Access
Question # 18

A hurricane delays the shipment of critical equipment for a project. Which of the following is BEST to use to document the effects of this delay?

A.

Issue log

B.

Gantt chart

C.

Milestone chart

D.

Change control log

Full Access
Question # 19

Which of the following cloud models can be used to speed up the development of a service that integrates with the operating system and accelerates the delivery of a software project?

A.

SaaS

B.

IaaS

C.

DaaS

D.

PaaS

Full Access
Question # 20

A global franchise requests that a company provide a solution to unify its operation worldwide. Additionally, the company would like the solution to provide operation reports in real time without asking the country franchise manager for these reports. Which of the following cloud models would the company suggest to the global franchise?

A.

laaS

B.

XaaS

C.

PaaS

D.

SaaS

Full Access
Question # 21

Which of the following is a capital expense?

A.

Building lease

B.

Building purchase

C.

Building maintenance

D.

Building insurance

Full Access
Question # 22

A customer requests some changes to a product, and those changes are approved by the CCB. Which of the following should be changed first?

A.

ROI

B.

KPI

C.

RACI

D.

SOW

Full Access
Question # 23

After a release, the project sponsor received an escalation from an executive about the extension of the downtime after the scheduled window. Which of the following should be added to the issue log?

A.

Continuous integration

B.

Rollback plan

C.

Customer notification

D.

Automated testing

Full Access
Question # 24

A fix that was not submitted to the CCB for approval was applied to an application. Although the change did not have negative consequences, the sponsors expressed concern to the project manager. Which of the following should the project manager do first to prevent this situation from reoccurring?

A.

Meet with the team and highlight the importance of change management.

B.

Roll back the process and submit a change request.

C.

Document the event as a lesson learned.

D.

Remove the team member who bypassed the CCB process.

Full Access
Question # 25

A project manager identifies stakeholders who will be impacted when a new product is delivered to the company. The project manager notices that more stakeholders will be positively impacted than negatively impacted. Which of the following actions should the project manager take?

A.

List both positively and negatively impacted stakeholders.

B.

Update the communication plan with the new findings.

C.

List the negatively impacted stakeholders only.

D.

List the positively impacted stakeholders only.

Full Access
Question # 26

A project manager has decided to wait until all requirements are developed to initiate testing. Which of the following relationship dependencies is the project manager using?

A.

Start-to-finish

B.

Finish-to-finish

C.

Finish-to-start

D.

Start-to-start

Full Access
Question # 27

The goal of a project is to fulfill specific technical features requested by customers. Which of the following actions should the product owner take?

A.

Define the success criteria.

B.

Create a communication plan.

C.

Use a task board.

D.

Perform a root cause analysis.

Full Access
Question # 28

A project manager was just assigned to a new project. Which of the following activities should the project manager undertake after accepting the project? (Select TWO).

A.

Review the detailed plan.

B.

Develop a preliminary scope.

C.

Develop a transition plan.

D.

Develop a project management plan.

E.

Review the resource pool.

F.

Review the project objectives.

Full Access
Question # 29

A project sponsor is struggling to provide the latest project status information on a weekly executive call. Which of the following should be reviewed?

A.

Meeting cadence

B.

Gap analysis

C.

Dashboard

D.

Adoption training

Full Access
Question # 30

Which of the following software programs would be best to use to store information related to business transactions?

A.

Record management system

B.

Customer relationship management

C.

Enterprise resource planning

D.

Content management system

Full Access
Question # 31

Which of the following provides a layered approach to logging in to systems that contain an organization's most valuable intellectual property?

A.

Remote access

B.

Password protection

C.

Multifactor authentication

D.

Virtual private network

Full Access
Question # 32

Which of the following best describes why a project manager would decide to sign a fixed-price contract with a vendor?

A.

The scope of the project deliverable is clearly defined.

B.

There is a non-disclosure agreement in place.

C.

There are multiple requirements for the product.

D.

The PM wants to simplify the logistics of the required product.

Full Access
Question # 33

Which of the following contract types in project procurement has the highest risk for the buyer?

A.

Time and material

B.

Cost-plus

C.

Fixed-price

D.

Unit price

Full Access
Question # 34

A program manager is reviewing the project portfolio and prioritizing each project based on the company's strategic plan. Which of the following should be considered in this evaluation? (Select TWO).

A.

Company vision

B.

Global environment

C.

Brand value

D.

Mission statement

E.

Portfolio budget

F.

Local legislation

Full Access
Question # 35

During the stabilization phase for recently deployed software, an end user reports a bug that is compromising data integrity. Which of the following tools will the project manager MOST likely use?

A.

Issue log

B.

Defect log

C.

Change log

D.

Task board

Full Access
Question # 36

Several stakeholders have asked about how the requirements are being covered by the deliverables and the progress of each requirement Which of the following would be the best tool the project manager can use to provide this information to the stakeholders?

A.

Risk register

B.

Change log

C.

Traceability matrix

D.

Project status report

Full Access
Question # 37

A project manager submits a change request. The change request is rejected because of code freeze. Which of the following actions should the project manager take next?

A.

Update the risk register.

B.

Escalate the issue for exceptional approval.

C.

Communicate to the stakeholders.

D.

Submit a duplicate change request.

Full Access
Question # 38

Given the following velocity chart:

Which of the following updates on the project status should the Scrum master provide to the senior management team?

A.

The project utilized all of its available reserve.

B.

The project has scope creep.

C.

The project deviated from the critical path.

D.

The project is trending ahead of schedule.

Full Access
Question # 39

During the testing process, testers have found multiple bugs that could jeopardize the project commitment date Which of the following tools should the project manager use first to update the findings?

A.

Defect log

B.

Change log

C.

Issue log

D.

Risk log

Full Access
Question # 40

Which of the following is a consideration when determining a project's ESG factors?

A.

Project management methodology

B.

IT infrastructure security

C.

Proper accounting practices

D.

Corporate values compliance

Full Access
Question # 41

A PM is working on the schedule for a project that has technical tasks and requires a SME's knowledge. The PM decides the best way to track this project is to have the project lead provide high-level updates. Which of the following is the best tool to track this data?

A.

Gantt chart

B.

Project organization chart

C.

Program Evaluation Review Technique chart

D.

Milestone chart

Full Access
Question # 42

A project sponsor requires a system that is capable of providing integrated management of all the business's core functions. Which of the following systems is the project sponsor describing?

A.

CMS

B.

CRM

C.

EDRMS

D.

ERP

Full Access
Question # 43

A new project team started work three months ago. The team members are increasing their work productivity and are comfortable asking for help with tasks. Which of the following describes the current stage of the project team?

A.

Performing

B.

Adjourning

C.

Forming

D.

Norming

Full Access
Question # 44

During an executive call, a project sponsor found out about issues with the project but was not able to provide details about the next steps. Which of the following needs to be revised?

A.

Project dashboard

B.

Gap analysis

C.

Risk register

D.

Communication plan

Full Access
Question # 45

While managing a project, a PM is assigned to work on a second project. The second project becomes more complex and monopolizes the PM's time. The PM learns that a similarly time-consuming project was executed previously in the organization. Which of the following actions should the PM take?

A.

Perform a root cause analysis.

B.

Organize a stakeholder meeting

C.

Escalate the issue to the CCB

D.

Contact the PMO for assistance.

Full Access
Question # 46

Which of the following activities are important parts of the closing phase? (Select two).

A.

Releasing resources

B.

Locking risks

C.

Updating stakeholder register

D.

Closing contracts

E.

Completing the work breakdown structure

F.

Negotiating the next project

Full Access
Question # 47

During the execution of a project, a project manager wanted to discover how the number of worked hours was affecting the quality of given tasks. For a two-month period, the following data was documented:

Average worked hours

Which of the following describes the result?

A.

A negative correlation exists between the number of mistakes and the working hours.

B.

No correlation exists between the number of mistakes and the working hours.

C.

A low correlation exists between the working hours and the number of mistakes.

D.

A positive correlation exists between the number of mistakes and the working hours.

Full Access
Question # 48

A data center is under construction, and the project manager wants to address the risks related to physical injuries. Which of the following is the best risk response method for this scenario?

A.

Avoid injuries by using robots to perform tasks.

B.

Transfer risk to an insurance company.

C.

Mitigate risk by training the construction workers.

D.

Accept the risks inherent to construction.

Full Access
Question # 49

Two stakeholders, who have a history of animosity toward one another, are in disagreement during a project. The project's timeline depends on the stakeholders accomplishing their tasks. Which of the following conflict resolution methods would be best to utilize?

A.

Smoothing

B.

Confronting

C.

Forcing

D.

Compromising

Full Access
Question # 50

Which of the following is a quantitative key performance indicator?

A.

The project sponsor ranked the graphics of an application as four out of five.

B.

The project implements the application in ten different geographical regions.

C.

The workers complete tasks on average 25% faster using a new application.

D.

The use of a multimedia interface appeals more to users under the age of 21.

Full Access
Question # 51

Which of the following is a typical characteristic of Scrum?

A.

Large teams

B.

Low-risk scope

C.

Self-organized team

D.

Well-defined scope

Full Access
Question # 52

A team member needs to make an emergency update. The team member is unable to return to the office. Which of the following is the most secure way to make the update?

A.

At home, using home internet and the company’s computer

B.

At a coffee shop, using free Wi-Fi and the corporate computer

C.

At home, using home internet and the corporate virtual private network

D.

Anywhere the team member would like, using a mobile device and mobile internet

Full Access
Question # 53

Which of the following tasks should the project manager complete first when validating deliverables?

A.

Assess the documentation.

B.

Obtain stakeholder feedback.

C.

Review the project objectives.

D.

Mitigate risks.

Full Access
Question # 54

During the execution phase, user accepted testing failed; nonetheless, the vendor PM is insisting that the program manager approve the invoice for this phase. Which of the following actions should the Program manager take?

A.

Escalate the issue with the project sponsor and ask for assistance in managing the situation.

B.

Work with the vendor to achieve a compromise that benefits everyone.

C.

Approve the invoice to avoid damaging the relationship with the vendor.

D.

Schedule a call with the vendor PM and vendor executive to review the statement of work.

Full Access
Question # 55

A project manager, who finished a project some time ago, keeps receiving questions from another project manager who is currently leading a similar project. Which of the following is the most likely cause of this situation?

A.

The retrospective session feedback was not communicated properly.

B.

The project resources were released ahead of time.

C.

The documentation was not archived as per the PMO standards.

D.

The validation of deliverables is running behind schedule.

Full Access
Question # 56

Which of the following should a product manager choose in order to enable collaboration between team members located in different regions? (Select two).

A.

Real-time surveys/polling

B.

Wiki knowledge base

C.

Spreadsheets

D.

Meetings/face-to-face

E.

Real-time, multi-authoring editing software

F.

Charting/diagramming

Full Access
Question # 57

A project scheduler updates the project status with the following information: SPI = 1.25 and CPI = 0.85. Which of the following can the project manager infer about the current project status?

A.

The project is ahead of schedule and under budget.

B.

The project is behind schedule and over budget

C.

The project is ahead of schedule and over budget.

D.

The project is behind schedule and under budget

Full Access
Question # 58

A company is starting a new implementation project The stakeholders are reviewing RFP responses to help make a decision about which project management consulting firm to hire. Given the following information:

Which of the following is the best consulting firm for the company to hire?

A.

Consulting firm 1

B.

Consulting firm 2

C.

Consulting firm 3

D.

Consulting firm 4

Full Access
Question # 59

Which of the following best describes a manufacturer's obligation to repair or change, without extra costs, any part of a product that is not functioning?

A.

Service-level agreement

B.

Functional testing

C.

Warranty period

D.

Audit

Full Access
Question # 60

Which of the following describes three-tier architecture?

A.

Conceptual, design, and implementation stages

B.

Presentation, application, and data processing

C.

Network, software, and security

D.

Development, testing, and production environment

Full Access
Question # 61

During a code implementation, a senior developer and junior tester are discussing the testing scenarios that were performed. A major malfunction resulted in an inoperative product condition. As a result, the team was forced to work until midnight to restore operations. Which of the following should the PM have generated FIRST to alleviate the impact of this issue prior to deployment?

A.

A risk budget

B.

A risk impact

C.

A change request

D.

A contingency plan

Full Access
Question # 62

Which of the following is an intended outcome of a stand-up meeting?

A.

To identify team members for next tasks

B.

To identify future tasks

C.

To identify stakeholders for next tasks

D.

To identify blocking tasks

Full Access
Question # 63

Which of the following is a reason to use a SOW on a project?

A.

To find out the contact information for the vendors

B.

To review the list of stakeholders

C.

To ensure the team stays within the scope of the contract

D.

To give explicit instruction on how to execute the work

Full Access
Question # 64

Which of the following is the most important activity for the project manager during the closure of a project?

A.

Obtain project sign-off.

B.

Capture lessons learned.

C.

Document historical information.

D.

Release resources.

Full Access
Question # 65

Which of the following is the best example of CapEx?

A.

Taxes

B.

Vehicles

C.

Salaries

D.

Utilities

Full Access
Question # 66

Which of the following criteria would favor using the agile methodology to manage an upcoming project?

A.

Strong projectized organization

B.

Medium risk

C.

Lack of resources

D.

Multiple undefined tasks

Full Access
Question # 67

A project manager prefers to have immediate contact with team members because it allows for faster response times and more interactive discussions. Which of the following communication methods should the project manager use?

A.

Synchronous

B.

Informal

C.

Asynchronous

D.

Formal

Full Access
Question # 68

An IT intern was assigned to set up workstations as part of a project. The IT intern was very careful to do the task well and initially referred to notes while performing the task. By the end of the two-week rotation, the IT intern no longer needed the notes and completed more set-ups in less time. Which of the following MOST likely represents the observed relationship in this scenario?

A)

B)

C)

D)

A.

Option A

B.

Option B

C.

Option C

D.

Option D

Full Access
Question # 69

Which of the following statements best represents a network issue?

A.

The development team on the fourth floor is unable to access servers and email services.

B.

Cell phones served by a specific telecom company are getting a "no service" message.

C.

A user cannot connect to Wi-Fi because of a wrong ID or password.

D.

A user is receiving an automatic reply message saying that an email address does not exist.

Full Access
Question # 70

Project members are based in three countries and each work remotely Which of the following would a project manager use to improve internal project communication?

A.

Progress reporting

B.

Meeting minutes

C.

Team touch points

D.

Change management

Full Access
Question # 71

During a quality analysis review, the causes of several issues have been highlighted. Which of the following should the project manager use to identify the MOST important causes?

A.

Ishikawa diagram

B.

Scatter diagram

C.

Pareto chart

D.

Decision tree

Full Access
Question # 72

A project team member wrote a user guide over the past ten days. Given the following scatter diagram.

Which erf the following can be formally conducted?

A.

The team member prioritized other tasks over the completion of this task

B.

The learn member had performance issues over time.

C.

There is a negative correlation with 6me and output

D.

This is a display of units of outstanding work to predict completion

Full Access
Question # 73

Someone claiming to be from a tax agency sent an email to a team member asking for access to the project repository. Which of the following BEST describes this scenario?

A.

Social engineering

B.

Phishing

C.

Spoofing

D.

Hacking

Full Access
Question # 74

A company is creating a new technology. The company is concerned that the project details could be compromised if a cloud service is used, and another company could launch the technology before the current projected delivery. Which of the following can the company do to minimize this risk?

A.

Use an on-premises project management scheduling tool.

B.

Limit access to members of the project team.

C.

Mandate overtime to get the project completed sooner.

D.

Ensure all team members have signed a non-disclosure agreement.

Full Access
Question # 75

A company purchases new software. The project manager needs to present the new software’s features to the stakeholders. Which of the following meeting types should the project manager and stakeholders have?

A.

Status

B.

Focus

C.

Brainstorming

D.

Informative

Full Access
Question # 76

Which of the following cloud models is designed to provide compute, storage, and networking resources on demand?

A.

Software as a service

B.

Infrastructure as a service

C.

Data as a service

D.

Platform as a service

Full Access
Question # 77

A car manufacturer is presenting to three vendors the abilities and qualifications required to develop the last module of a data warehouse application. The manufacturer is emphasizing the technical skills necessary to complete the project on time and highlighting its current internal IT project. Which of the following best describes this activity?

A.

Key stakeholder identification

B.

Preliminary procurement

C.

Solution design determination

D.

Critical factor enlistment

Full Access
Question # 78

Which of the following pieces of data are examples of Pll?

A.

Medical record and test result values

B.

IP address and email address

C.

Name and year of birth

D.

X-ray and blood type

Full Access
Question # 79

A project is not progressing as planned following the departure of the project manager. Which of the following would be the best tool to use to document this information?

A.

Issue log

B.

Risk register

C.

Change log

D.

Defect log

Full Access
Question # 80

A project manager is in the closing phase of an IT asset refresh project that involves the disposal of several computers. The project sponsor notified the project manager that the company recently received a penalty as a result of disposing of some computers improperly. Which of the following should have been considered during initial planning to prevent this situation?

A.

ESG

B.

PHI

C.

Pll

D.

ROI

Full Access
Question # 81

Which of the following offers administrators more direct control over operating systems?

A.

Infrastructure as a service

B.

Software as a service

C.

Functions as a service

D.

Platform as a service

Full Access
Question # 82

A stakeholder raises a concern with a project manager because of the number of emails that have been received before a coding release. Which of the following actions should the project manager take next?

A.

Inform the CCB to stop communication.

B.

Establish a RACI matrix.

C.

Escalate the communication issues.

D.

Revise the communication plan.

Full Access
Question # 83

Which of the following activities would force a team to remove a new package and leave the previous one during a smoke test?

A.

Rollback plan

B.

Downtime stage

C.

Maintenance window

D.

Validation checks

Full Access
Question # 84

A developer focused on a single story during an entire sprint. The story was underestimated and, therefore, was not completed. Which of the following steps should the Scrum team take next?

A.

Assign more resources to complete similar stories in the future.

B.

Break the stories into workable items that can be completed within one sprint.

C.

Extend the sprint duration when required with the approval of the product owner.

D.

Release the current progress into production and carry over the rest of the code for the next sprint.

Full Access
Question # 85

Due to budgetary and time constraints, a PM scheduled a meeting with all stakeholders during the planning phase to review the requirements and come to an agreement on the minimum viable product that would be acceptable. Which of the following would be used to document this input?

A.

Project change management plan

B.

Project management plan

C.

Project transition plan

D.

Project communication plan

Full Access
Question # 86

During an agile project, a team member checked the project artifacts in order to anticipate when all the work should have been completed. Which of the following charts was the team member most likely consulting?

A.

Pareto chart

B.

Milestone chart

C.

Burndown chart

D.

Gantt chart

Full Access
Question # 87

A project manager has been informed that the delivery of required IT equipment will be delayed. Which of the following is the FIRST step the project manager should take?

A.

Make an impact assessment.

B.

Prepare a new purchase order.

C.

Select a new vendor.

D.

Create a risk register.

Full Access
Question # 88

Two developers are discussing the design solution for a particular feature. The meeting is taking longer than expected, and the parties have been unable to reach an agreement. The project manager decides to take a break and continue the meeting on another day. Which of the following techniques is the project manager using?

A.

Avoiding

B.

Smoothing

C.

Forcing

D.

Compromising

Full Access
Question # 89

During the planning phase, a team agreed on the tasks, durations, predecessors, and resources needed to complete a project. Which of the following should be developed to formalize this agreement?

A.

Baseline

B.

RBS

C.

WBS

D.

Milestones

Full Access
Question # 90

When creating a project schedule, a project manager adds activities with zero duration. Which of the following describes these types of activities?

A.

Critical paths

B.

Resources

C.

Milestones

D.

Work breakdown structures

Full Access
Question # 91

A quality assurance team is based in three different locations To validate the project deliverables, a project manager sent the hardware for testing purposes to the team in each of the locations. Two teams confirmed the hardware arrived, but one group did not receive it because of local customs Which of the following ESG factors is the project team facing?

A.

Awareness of the company vision, mission statement, and values

B.

Impact of the project on the company's brand value

C.

Awareness of applicable regulations and standards

D.

Impact of the project on the local and global environments

Full Access
Question # 92

By developing a project schedule, a PM has already validated the constraints, outlined the duration of the tasks and the phases, and confirmed the proper sequence and flow of the project. Which of the following activities still needs to be performed to complete the schedule?

A.

Allocate resources.

B.

Determine the project budget

C.

Develop a communication plan.

D.

Establish baselines.

Full Access
Question # 93

A project manager is organizing and running a project closure meeting. Which of the following best describes the objective of this meeting?

A.

To move the system to a production environment

B.

To obtain project sign-off

C.

To formalize the end of the contract

D.

To release resources

Full Access
Question # 94

Which of the following are primary features provided by a standard laaS solution? (Select two).

A.

Encryption

B.

Storage

C.

Networking

D.

User interface

E.

Access

F.

Database

Full Access
Question # 95

A project sponsor asked the PM to provide a summary of the current financial status. The PM uses the following burn up chart for the analysis:

Based on the chart, which of the following is the current status of the project?

A.

Behind schedule and over budget

B.

Behind schedule and under budget

C.

Ahead of schedule and over budget

D.

Ahead of schedule and under budget

Full Access
Question # 96

Which of the following provides the best justification for undertaking a project?

A.

Scope statement

B.

Business case

C.

Sponsor request

D.

Project charter

Full Access
Question # 97

Which of the following can a project manager infer from the following velocity chart?

A.

The project is on schedule.

B.

The project Is ahead of schedule.

C.

The project is behind schedule.

D.

The project is at risk.

Full Access
Question # 98

Which of the following metrics BE ST measures the alignment of the information security program to operational objectives?

A.

Percentage of controls with identified business owners

B.

Percentage of risk investments with defined business cases

C.

Ratio of control cost to operational budget

D.

Senior management satisfaction scores related to the security program

Full Access
Question # 99

A project manager is using an agile methodology to lead the implementation of several features that should be developed concurrently. Which of the following items should the project manager view as a concern?

A.

Each feature will have a different owner.

B.

The majority of the team can only meet on a weekly basis.

C.

The stakeholders have provided a specific deadline to meet.

D.

Each feature has a specific budget allocation.

Full Access
Question # 100

Project A is running behind schedule. The team realizes that Project B is working on an API that was planned to be developed by Project A. The project manager from Project A decides to use the API from Project B. Which of the following risk management strategies describes this example?

A.

Exploit

B.

Share

C.

Transfer

D.

Accept

Full Access
Question # 101

Which of the following concepts represents multiple resources interfaced to run reports?

A.

Code repository

B.

Data warehouse

C.

Storage server

D.

File-sharing system

Full Access
Question # 102

Which of the following contract types would be most beneficial to both parties in cases in which the scope of the project has a large number of unknowns?

A.

Variable costs

B.

Fixed costs

C.

Front-loaded

D.

Time and materials

Full Access
Question # 103

Before a configuration can be made to a system in development, a document containing information about how the new system will interact with other systems within the organization needs to be written. Which of the following relationships best describes this scenario?

A.

Start-to-start

B.

Start-to-finish

C.

Finish-to-finish

D.

Finish-to-start

Full Access
Question # 104

Which of the following best describes why conducting lessons learned sessions is important?

A.

To discuss as a team how to improve and eliminate all the issues in the project

B.

To conduct the team’s performance evaluation and document the results

C.

To report all the mistakes and ensure others do not make the same ones

D.

To document what went right and wrong, as well as possible improvements

Full Access
Question # 105

A contractor attended a project meeting that was exclusively for company employees. Which of the following actions should the PM take?

A.

Escalate to vendor management.

B.

Consult the request for proposal.

C.

Review the meeting cadence.

D.

Reinforce the rules of engagement.

Full Access
Question # 106

Two project team members are assigned to set up new work areas and are disagreeing about the placement of hardware and peripherals at the end users' desks. The requirements do not specify where to place the items, just what is needed in each space. Which of the following should the project manager do to resolve the conflict?

A.

Send out a survey to the potential end users to gather information about the best functional setup for work productivity.

B.

Provide clear instructions based on personal preference and aesthetics for setup of the work areas.

C.

Explain to team members that the placement of the items is not too important, as long as everything is connected and working.

D.

Facilitate a meeting between team members to review the pros and cons of the different configurations so as to encourage an amicable solution.

Full Access
Question # 107

Which of the following tools should a project manager use to assess the activities performed, work effort applied, and the productivity of a project?

A.

Project status report

B.

Project evaluation review

C.

Project management software

D.

Requirements traceability matrix

Full Access
Question # 108

Which of the following aspects are true of waterfall as compared to agile? (Select two).

A.

Waterfall is composed of smaller teams working together

B.

Waterfall reinforces customer collaboration

C.

In waterfall, solution validation occurs later in the development cycle.

D.

In waterfall, working software is more of a focus than comprehensive documentation.

E.

Waterfall is less tolerant to changes in scope.

F.

Waterfall is made up of sprints

Full Access