Labour Day Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: buysanta

Exact2Pass Menu

Question # 4

A PM is meeting with the project team to identify the baseline go-live date, the operational training, and the handoff procedures. Which of the following phases is the project team performing?

A.

Initiation

B.

Closing

C.

Execution

D.

Planning

Full Access
Question # 5

A PM is working on the preliminary scope statement and identifies that this project has the same approach as another project that was completed last year. Which of the following actions would the PM most likely perform?

A.

Call the previous PM for advice on risks and issues.

B.

Ask the project sponsor to provide previous final project report results.

C.

Complete the project charter using the other PM's subject matter expertise.

D.

Use existing artifacts and accommodate based on the current project success criteria.

Full Access
Question # 6

Which of the following software programs would be BEST to use lo store information related to business transactions?

A.

Record management system

B.

Customer relationship management

C.

Enterprise resource planning

D.

Content management system

Full Access
Question # 7

While working in a collaborative, online brainstorming session, team members send private messages to the facilitator about challenges understanding others when they are speaking due to accents and background noises. Which of the following should the facilitator do to overcome the challenges?

A.

Instruct the team members to set their speakers to maximum volume and mute their microphones.

B.

Require everyone to turn on their cameras and use the same background filter.

C.

Encourage the use of the chat and use plain language when speaking.

D.

Allow one person to speak at a time after receiving acknowledgment from the facilitator.

Full Access
Question # 8

A project team gathers weekly to review its progress. Which of the following is the project manager MOST likely to have prepared to ensure team members who are absent remain informed about assignments?

A.

Status report

B.

Project plan

C.

Change log

D.

Meeting minutes

Full Access
Question # 9

A team is working on a project that has different stages, such as initiation, planning, execution, and closure. Which of the following is this an example of?

A.

Agile

B.

Waterfall

C.

Standard

D.

Hybrid

Full Access
Question # 10

Which of the following is a consideration when determining a project's ESG factors?

A.

Project management methodology

B.

IT infrastructure security

C.

Proper accounting practices

D.

Corporate values compliance

Full Access
Question # 11

A new junior PM who has ownership of a project does not understand how to manage conflicts involving multiple personalities. Which of the following is the best order of the stages the PM should follow to nurture the team to high performance?

A.

Forming, storming, performing, norming, adjourning

B.

Forming, performing, storming, norming, adjourning

C.

Forming, norming, storming, performing, adjourning

D.

Forming, storming, norming, performing, adjourning

Full Access
Question # 12

A project is moving into the user acceptance testing phase. Several resources will be needed to execute different steps in the testing plan. Which of the following would be the best tool to allow the resources to remain at their desks and only react when needed?

A.

Ticketing system

B.

Videoconference

C.

Simple messaging system

D.

Corporate social media

Full Access
Question # 13

During the execution phase of a project, the project team faced an unexpected website downtime The project manager how a brainstorming session and the team identified causes and effects tor the problem Now the project team needs to analyze and determine whether the particular cause and effect are related by using one of the following charts. Which of the following should the team use?

A)

B)

C)

D)

A.

Option A

B.

Option B

C.

Option C

D.

Option D

Full Access
Question # 14

Which of the following requires the MOST availability from the business team?

A.

SDLC

B.

Scrum

C.

PRINCE2

D.

Waterfall

Full Access
Question # 15

A project manager was just assigned to a new project. Which of the following activities should the project manager undertake after accepting the project? (Select TWO).

A.

Review the detailed plan.

B.

Develop a preliminary scope.

C.

Develop a transition plan.

D.

Develop a project management plan.

E.

Review the resource pool.

F.

Review the project objectives.

Full Access
Question # 16

A project team is working remotely from different locations across the country. As part of a lessons-learned exercise, the project manager would like to

identify the level of engagement among project team members. Which of the following would be the best tool for the project manager to use?

A.

Meeting chat

B.

Email

C.

Real-time survey

D.

Whiteboard

Full Access
Question # 17

A stakeholder raises a concern with a project manager because of the number of emails that have been received before a coding release. Which of the following actions should the project manager take next?

A.

Inform the CCB to stop communication.

B.

Establish a RACI matrix.

C.

Escalate the communication issues.

D.

Revise the communication plan.

Full Access
Question # 18

Which of the following is the main reason for documenting artifacts?

A.

To provide a record of the project's progress and achievements for future reference

B.

To show stakeholders that the project is on track and progressing as planned

C.

To help team members be aware of roles and responsibilities

D.

To ensure that the project team understands the importance of the project to the organization

Full Access
Question # 19

A PM needs to calculate the progress of the whole project scope for a presentation to the sponsor. Which of the following is the first document the PM should update?

A.

Project network diagram

B.

Gantt chart

C.

Issue log

D.

Risk report

Full Access
Question # 20

One of the key steps in controlling changes lo software is obtaining approval. Which of the following statements best describes the reason for this key objective?

A.

To send the appropriate customer notifications

B.

To avoid a negative impact on other software functionalities

C.

To ensure adequate resources are in place to implement the change

D.

To confirm that the software is a business priority

Full Access
Question # 21

A global franchise requests that a company provide a solution to unify its operation worldwide. Additionally, the company would like the solution to provide operation reports in real time without asking the country franchise manager for these reports. Which of the following cloud models would the company suggest to the global franchise?

A.

laaS

B.

XaaS

C.

PaaS

D.

SaaS

Full Access
Question # 22

After months of recruiting, a team finally found the right candidate for a very specific coding language assignment. Due to this delay, the team has a tight timeline without any float. A day before the candidate is scheduled to join the team, the project manager realizes the candidate has a non-compete agreement from the previous employer. Which of the following should the project manager do?

A.

Withdraw the offer to the candidate and raise this as a risk.

B.

Ignore a potential lawsuit since this is a critical project.

C.

Use a third-party company for the contract to legally avoid responsibility.

D.

Have a meeting with the project sponsor to discuss the situation.

Full Access
Question # 23

A project team participates in a brainstorming session to define the guidance, direction, and approach for monitoring established procedures for developed products. Which of the following plans is the team creating?

A.

Project transition

B.

Project management

C.

Project communications

D.

Project quality assurance

Full Access
Question # 24

Which of the following describes three-tier architecture?

A.

Conceptual, design, and implementation stages

B.

Presentation, application, and data processing

C.

Network, software, and security

D.

Development, testing, and production environment

Full Access
Question # 25

During a quality analysis review, the causes of several issues have been highlighted. Which of the following should the project manager use to identify the MOST important causes?

A.

Ishikawa diagram

B.

Scatter diagram

C.

Pareto chart

D.

Decision tree

Full Access
Question # 26

In order to complete a major project deliverable, very specialized resources are required for some tasks. The PM failed to take into consideration during planning that the required resources would be available for fewer hours than required. Which of the following should the PM do first to make schedule changes?

A.

Add a new risk.

B.

Perform an impact analysis.

C.

Escalate to the sponsor.

D.

Raise a change request.

Full Access
Question # 27

A project manager sent equipment to a global project team for testing purposes. Only 70% of the project team received the equipment for testing. Which of the following considerations is impacting the rest of the team?

A.

Quality assurance

B.

Organizational branding restrictions

C.

State privacy acts

D.

Country legal regulations

Full Access
Question # 28

While in the closing phase of a project, the project manager gathers feedback from stakeholders. Which of the following best describes a benefit of this feedback?

A.

It highlights the performance issues of the project manager and team members.

B.

It lets the project manager know which stakeholders are allies for future projects.

C.

It helps the project manager create a more structured lessons-learned session.

D.

It identifies the stakeholders' real opinions about the project.

Full Access
Question # 29

Two team members have a minor disagreement on how a task should be performed. The project manager plans to meet with the team members to discuss the matter. Which of the following techniques should the project manager use to emphasize the areas of agreement and downplay the opposing views?

A.

Compromising

B.

Forcing

C.

Smoothing

D.

Collaborating

Full Access
Question # 30

When introducing a new information asset, what is the MOST important responsibility of the asset owner?

A.

Information disposal

B.

Information classification

C.

Information access administration

D.

Information backup

Full Access
Question # 31

A project manager does not have the power to reward team members when they accomplish something or penalize them when they fail to perform well. As a result, the project manager is having issues with team members. Which of the following describes this organizational structure?

A.

Flat

B.

Projectized

C.

Weak matrix

D.

Functional

Full Access
Question # 32

A project manager and team are reviewing a task that is supposed to take nine days to complete and cost $3,000. There is a 20% chance that an associated risk related to changing requirements could occur, resulting in rework that would add an additional five days and $1,000 in costs. Which of the following represents the total amount that should be budgeted for the task?

A.

9 days and $3,000

B.

10 days and $3,200

C.

12 days and $3,800

D.

14 days and $4,000

Full Access
Question # 33

In the initiation phase, a PM is reviewing the objectives, the high-level requirements, the success criteria, and the budget resources. Which of the following action items will benefit from this analysis?

A.

Developing a RACI

B.

Identifying and assessing stakeholders

C.

Assigning project resources

D.

Establishing communication channels

Full Access
Question # 34

A PM is working on the schedule for a project that has technical tasks and requires a SME's knowledge. The PM decides the best way to track this project is to have the project lead provide high-level updates. Which of the following is the best tool to track this data?

A.

Gantt chart

B.

Project organization chart

C.

Program Evaluation Review Technique chart

D.

Milestone chart

Full Access
Question # 35

The project team determines that software installation can only begin after the desktops have been installed and can be powered on. Which of the following dependencies does this represent?

A.

External

B.

Internal

C.

Mandatory

D.

Discretionary

Full Access
Question # 36

Due to budgetary and time constraints, a PM scheduled a meeting with all stakeholders during the planning phase to review the requirements and come to an agreement on the minimum viable product that would be acceptable. Which of the following would be used to document this input?

A.

Project change management plan

B.

Project management plan

C.

Project transition plan

D.

Project communication plan

Full Access
Question # 37

A project manager reports that the implementation of a new system is on track to be completed under budget and ahead of the schedule. A stakeholder then asks the manager to add mobile device functionality. Which of the following should the project manager do in response to the request?

A.

Decline because it is not included in the project scope.

B.

Assess the impact of the request and create a change request

C.

Create new functional and non-functional requirements for mobile devices.

D.

Revise the baseline of the project plan by adding the new requirements.

Full Access
Question # 38

Because the project team lacks hands-on experience, the project manager has decided to involve a third-party vendor to complete the development of a product. Which of the following documents should the project manager expedite first?

A.

RFI

B.

RFP

C.

RFQ

D.

RFB

Full Access
Question # 39

After new capabilities were deployed in a system, issues with preexisting capabilities were reported. Which of the following testing cycles should be used to prevent this issue?

A.

Performance testing

B.

User acceptance testing

C.

Stress testing

D.

Unit testing

Full Access
Question # 40

During the planning phase, a PM reviews the SOW from the contractor, grades the full-time equivalents' resumes, evaluates the titles and salaries, and estimates the number of hours for each milestone by full-time equivalents. The PM is most likely:

A.

negotiating resources.

B.

assigning resources.

C.

assessing the resource pool.

D.

adding resources to the schedule.

Full Access
Question # 41

A risk management team for a software project decided to outsource the development of a specific portion of a system due to a lack of internal resources. Which of the following risk responses does this demonstrate?

A.

Avoid

B.

Transfer

C.

Accept

D.

Share

Full Access
Question # 42

Two project team members are assigned to set up new work areas and are disagreeing about the placement of hardware and peripherals at the end users' desks. The requirements do not specify where to place the items, just what is needed in each space. Which of the following should the project manager do to resolve the conflict?

A.

Send out a survey to the potential end users to gather information about the best functional setup for work productivity.

B.

Provide clear instructions based on personal preference and aesthetics for setup of the work areas.

C.

Explain to team members that the placement of the items is not too important, as long as everything is connected and working.

D.

Facilitate a meeting between team members to review the pros and cons of the different configurations so as to encourage an amicable solution.

Full Access
Question # 43

Which of the following PRINCE2 processes includes creating the project plan?

A.

Starting up a project

B.

Initiating a project

C.

Managing product delivery

D.

Directing a project

Full Access
Question # 44

Two team members have a minor disagreement on how a task should be performed. The project manager plans to meet with the team members to discuss the matter. Which of the following techniques should the project manager use to emphasize the areas of agreement and downplay the opposing views?

A.

Compromising

B.

Forcing

C.

Smoothing

D.

Collaborating

Full Access
Question # 45

A visual that displays team progress was created for stand-up meetings. Which of the following BEST describes what is being represented on the visual?

A.

Decision board

B.

Whiteboard

C.

Task board

D.

Dashboard

Full Access
Question # 46

Which of the following items must be protected as Pll? (Select TWO).

A.

Job title

B.

Home address

C.

Work phone number

D.

Time zone

E.

Date of birth

F.

Blood type

Full Access
Question # 47

A PM has identified all the resources involved in a project. The next step is to identify which resources are responsible for which tasks. Which of the following should be used to document this information?

A.

RFI

B.

RACI

C.

WBS

D.

SOW

Full Access
Question # 48

Which of the following provides a layered approach to logging in to systems that contain an organization's most valuable intellectual property?

A.

Remote access

B.

Password protection

C.

Multifactor authentication

D.

Virtual private network

Full Access
Question # 49

A project sponsor asked the PM to provide a summary of the current financial status. The PM uses the following burn up chart for the analysis:

Based on the chart, which of the following is the current status of the project?

A.

Behind schedule and over budget

B.

Behind schedule and under budget

C.

Ahead of schedule and over budget

D.

Ahead of schedule and under budget

Full Access
Question # 50

A project manager is reviewing a signed legal document pertaining to the hiring of a vendor who will develop an experimental solution. The vendor could not provide accurate estimates at this time because the requirements will probably be changing. The document also contains information about the resources involved and the rates the vendor will charge for the work. Which of the following best describes the legal document the project manager is reviewing?

A.

Time and materials contract

B.

Master service agreement

C.

Fixed-price contract

D.

Non-disclosure agreement

Full Access
Question # 51

A financial manager reports that several employees' allocations from the past month appear to be 200% even though they are only assigned to a particular project. Which of the following could MOST likely be the cause of this issue?

A.

A project manager assigned the wrong resources.

B.

A project manager did not release the resources

C.

A project manager did not remove the system access.

D.

A project manager did not provide the project sign-off.

Full Access
Question # 52

A team member identifies a critical issue in production. Which of the following should the project manager apply?

A.

Compliance check

B.

Release plan

C.

Rollback plan

D.

Validation check

Full Access
Question # 53

Halfway through a project, the sponsor states that the project is taking too long to complete. Which of the following should the project manager consult?

A.

Gantt chart

B.

Maintenance window schedule

C.

Functional requirements

D.

Test results

Full Access
Question # 54

A project manager has been assigned to a new project. During the planning phase, the project manager needs to get an understanding of the purpose of the project. Which of the following should the project manager do?

A.

Collate the lessons learned.

B.

Perform a gap analysis.

C.

Review existing artifacts.

D.

Conduct a retrospective.

Full Access
Question # 55

Which of the following tools is best to use when conducting project meetings across time zones?

A.

Text

B.

Calendaring tools

C.

Videoconference

D.

Email

Full Access
Question # 56

A development team, which is working on a software project demonstrates software functionality 10 project stakeholder a week before the implementation date. Several stakeholders comment that the software does not meet the communicated expectations. Which of the following tools should the project manager use to validate the functionality?

A.

Project status report

B.

Requirements Traceability Matrix

C.

Detect log

D.

Signed project charter

E.

Work breakdown structure

Full Access
Question # 57

A project manager is monitoring team performance by comparing committed versus completed work. The project manager creates the following:

Which of the following most likely represents the number of items in the backlog?

A.

23

B.

5

C.

10

D.

15

Full Access
Question # 58

Which of the following tools is best to use for storing lessons learned?

A.

Whiteboard

B.

Wiki knowledge base

C.

Content management system

D.

Workflow platform

Full Access
Question # 59

For an upcoming project kickoff. a PM is looking for a way to illustrate roles for major project activities. Which of the following would be the MOST useful option?

A.

Resource plan

B.

Organizational chart

C.

Project charter

D.

RACI chart

Full Access
Question # 60

While managing a project, a PM is assigned to work on a second project. The second project becomes more complex and monopolizes the PM's time. The PM learns that a similarly time-consuming project was executed previously in the organization. Which of the following actions should the PM take?

A.

Perform a root cause analysis.

B.

Organize a stakeholder meeting

C.

Escalate the issue to the CCB

D.

Contact the PMO for assistance.

Full Access
Question # 61

An IT intern was assigned to set up workstations as part of a project. The IT intern was very careful to do the task well and initially referred to notes while performing the task. By the end of the two-week rotation, the IT intern no longer needed the notes and completed more set-ups in less time. Which of the following MOST likely represents the observed relationship in this scenario?

A)

B)

C)

D)

A.

Option A

B.

Option B

C.

Option C

D.

Option D

Full Access
Question # 62

During an agile project, a team member checked the project artifacts in order to anticipate when all the work should have been completed. Which of the following charts was the team member most likely consulting?

A.

Pareto chart

B.

Milestone chart

C.

Burndown chart

D.

Gantt chart

Full Access
Question # 63

A project manager realizes that a project will not be completed on time due to resource constraints. Which of the following actions should the project manager take NEXT?

A.

Trigger the contingency plan and communicate with the stakeholders.

B.

Work with the functional managers to create a work-around.

C.

Submit a change request to the change control board.

D.

Transfer the risk by hiring a new vendor who was successful on a previous project.

E.

Set up an escalation meeting with the sponsor.

Full Access
Question # 64

A company needs to have structured cabling installed in one of its buildings. Which of the following would be the best document for the company to use to obtain and compare information on cabling services and costs from various vendors?

A.

RFB

B.

RFQ

C.

RF

D.

RFP

Full Access
Question # 65

A sponsor prefers to communicate with the team using email, phone calls, conversations in the hallway, and impromptu meetings. Which of the following types of communication is the sponsor using?

A.

Informal communication

B.

Formal communication

C.

Synchronous communication

D.

Asynchronous communication

Full Access
Question # 66

How does data discovery assist with data classification'?

A.

It shows where specific data is stored

B.

It automatically classifies data by keywords

C.

It helps to identify the data owner

D.

It provides assurance of data integrity

Full Access
Question # 67

A developer recommends modifying an existing portion of code that is not part of the scope and is causing low performance on the current solution. Which of the following actions should the project manager most likely take?

A.

Ask a developer to create a change request.

B.

Do nothing because recommendation is scope creep.

C.

Ask a developer to implement the recommendation.

D.

Communicate the change status.

Full Access
Question # 68

A stakeholder works in a remote location and has not been replying to emails. The Internet service in that location is intermittent, and the stakeholder prefers to be contacted by telephone. Which of the following artifacts should the project manager have prepared to avoid this situation?

A.

Responsibility assignment matrix

B.

Acceptable communication channels

C.

Risk registry

D.

Staff directory

Full Access
Question # 69

A project is running over budget, and due to new legislation in the country, the company needs to release all its contractors on the project or hire them as full-time employees. Which of the following should the PM do next to comply with the new legislation?

A.

Use only full-time employees even if the project is delayed.

B.

Hire all team members to avoid any delay in the project.

C.

Close the contract and pay the contractors cash for the remainder of the project.

D.

Look for an overseas vendor to finalize the project work.

Full Access
Question # 70

A project manager prefers to have immediate contact with team members because it allows for faster response times and more interactive discussions. Which of the following communication methods should the project manager use?

A.

Synchronous

B.

Informal

C.

Asynchronous

D.

Formal

Full Access
Question # 71

Which of the following software programs would be best to use to store information related to business transactions?

A.

Record management system

B.

Customer relationship management

C.

Enterprise resource planning

D.

Content management system

Full Access