Weekend Sale Special - 75% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 75epass

Exact2Pass Menu

PRINCE2 Project Management Practitioner (Version 7)

Last Update 2 hours ago Total Questions : 56

The PRINCE2 Project Management Practitioner (Version 7) content is now fully updated, with all current exam questions added 2 hours ago. Deciding to include PRINCE2-7-Practitioner practice exam questions in your study plan goes far beyond basic test preparation.

You'll find that our PRINCE2-7-Practitioner exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these PRINCE2-7-Practitioner sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any PRINCE2 Project Management Practitioner (Version 7) practice test comfortably within the allotted time.

Question # 11

During stage 3, the project manager forecasts that the stage-level recycling tolerance will be exceeded. The project manager records the matter in the issue register and sends only an issue report to the project board.

Is this an appropriate application of the progress practice, and why?

A.

Yes, because an issue report is sufficient whenever a sustainability target is forecast to be missed

B.

Yes, because the forecast shortfall should be treated only as an off-specification in the issue report

C.

No, because the forecast breach should be escalated to the portfolio office rather than the project board

D.

No, because it is an exception which should be escalated in an exception report

Question # 12

The target state for LouisShopping requires the car park to be monitored continuously, 24 hours a day and seven days a week, as an ongoing safety routine.

Under which heading of the change management approach should this requirement be recorded?

A.

State characteristics

B.

Enabling activities

C.

Resources

D.

Responsibilities

Question # 13

While selecting the project approach, the team identifies that a traditional delivery method and the proposed use of external suppliers could make the sustainability requirements harder to achieve. The risk is recorded in the project log for consideration during initiation.

Is this an appropriate application of ‘starting up a project’, and why?

A.

Yes, because the primary purpose of assessing the project approach at this stage is to clarify the prospective obligations of the project team and each external supplier when delivering the project products

B.

Yes, because the way the project work will be delivered directly influences how the management approaches are designed, and identifying risks early helps ensure the PID accurately reflects how sustainability will be managed

C.

No, because a risk that is classified as manageable does not pose a threat to overall project viability and should be deferred for consideration during the initiation stage when more detailed planning takes place using the traditional delivery method

D.

No, because any sustainability requirements that the project must satisfy should be captured as user quality expectations in the project product description, not as risks in the project log

Question # 14

During the ‘starting up a project’ process, the project team decides that the complex LouisShopping infrastructure project will use a traditional, linear-sequential delivery method.

Which role is accountable for selecting the project approach?

A.

Business layer

B.

Project executive

C.

Project manager

D.

Senior supplier

Question # 15

Immediately after initiation is authorized, the Head of the Portfolio Office instructs the LouisShopping project to adopt the Council’s mature issue management approach without any project-specific review or tailoring.

Is this an appropriate application of the issues practice, and why?

A.

Yes, because a mature organizational approach should always be used without alteration

B.

Yes, because portfolio funding gives the portfolio office authority to prohibit all project-level tailoring

C.

No, because the project manager should consider the nature of the products, delivery method and project context when preparing the issue management approach

D.

No, because product version control must be decided outside the issue management approach by the delivery teams alone

Question # 16

During the ‘starting up a project’ process, the project manager works with key business, user, and supplier stakeholders to co-create the project product description, clarify the shopping centre’s scope and agree its quality expectations and acceptance criteria.

What is the MAIN benefit of co-creating the project product description in this way?

A.

It transfers accountability for approving the project product description to the stakeholders involved

B.

It removes the need for a communication management approach later in the project

C.

It confirms that stakeholders will accept the shopping centre when it is handed over

D.

It brings together business, user, and supplier perspectives, improving adoption and reducing handover risks

Go to page: