You'll find that our PRINCE2-7-Practitioner exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these PRINCE2-7-Practitioner sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any PRINCE2 Project Management Practitioner (Version 7) practice test comfortably within the allotted time.

Question # 1

BUSINESS CASE

Here are three statements related to the ‘business case’ practice.

In which management product should each statement be recorded?

Choose only ONE management product for each statement. Each management product can be used once, more than once, or not at all.

A.

Business case

B.

Benefits management approach

C.

Sustainability management approach

D.

End stage report

E.

Project brief

F.

Commercial management approach

Statement 1:

The project will use a linear-sequential delivery method, and a reputable external supplier will deliver most of the specialist work.

Statement 2:

One sustainability target is to reduce the number of visitors arriving in internal-combustion vehicles. The Chief Technology Officer will implement monitoring technology, and the Business Opportunities Director will

Question # 2

RISK

Here are three items of information relating to the ‘risk’ practice.

In which management product (A–E) should each item be recorded?

Choose only ONE management product for each item of information. Each management product may be used once, more than once, or not at all.

A.

Risk register

B.

Issue register

C.

Quality management approach

D.

Issue report

E.

Risk management approach

Item 1:

A cracked pane has already been identified and replacement is planned for next week. The project manager records the separate uncertainty that the supplier may miss that future replacement date and delay subsequent work.

Item 2:

The agreed procedure states that the project board and project manager will review all open risks during every end stage assessment.

It

Question # 3

The LouisShopping project is part of the LOB portfolio and is now in the ‘initiating a project’ process. The project manager asks the portfolio office to support preparation of the digital and data management approach.

Why is this involvement appropriate during the ‘agree the management approaches’ activity?

A.

Because the sequencing within the ‘agree the management approaches’ activity requires the digital and data management approach to be finalized before other management approaches, including the communication management approach

B.

Because the primary purpose of the digital and data management approach is to identify what data the project will need and to establish the appropriate security and access controls for that data

C.

Because a linear-sequential delivery method inherently generates a greater volume of formal data and documentation than an iterative or incremental approach, which justifies seeking specialist portfolio support

D.

Because the digital and data management approach must be consistent with the data governance standards and technical requirements that the portfolio office applies across all projects in the LOB portfolio

Question # 4

At the stage 2 boundary, the project manager recommends adding the replacement subcontractor’s account manager to the project board to represent supplier interests during stage 3.

Which practice is being applied in ‘managing a stage boundary’?

A.

Plans

B.

Organization

C.

Quality

D.

Progress

Question # 5

During initiation, the project executive asks the project manager to evaluate a credible business option that omits the underground car park. The project manager includes an investment appraisal of that option in the full business case, despite the main contractor’s objection.

Is this an appropriate application of the business case practice, and why?

A.

Yes, because developing the business case includes comparing credible business options to select the most appropriate investment

B.

Yes, because customer and supplier organizations must always maintain completely separate project business cases regardless of the given investment

C.

No, because a requirement in the initial scope may never be tested as part of an alternative option

D.

No, because anticipated parking income means that no alternative should be assessed

Question # 6

BuildyBrick is demobilizing after delivering the shopping centre on time and within budget. Before the remaining supplier personnel leave, the project manager checks that the Council’s operations and facilities teams are ready to receive, operate and maintain the completed centre.

Why is this an appropriate application of the ‘confirm project acceptance’ activity?

A.

Because the project manager should complete the end project performance assessment before any supplier demobilizes

B.

Because the project manager should arrange a celebration before the contractor leaves the site

C.

Because all project information should be archived before the completed project product is accepted

D.

Because the project manager should confirm that handover to the operational and maintenance environment is complete

Question # 7

The risk register states that excavation may cause subsidence and damage nearby historic buildings. The planned response is to survey the buildings and monitor vibration during excavation. The project executive is named as risk owner and the project manager as the sole risk action owner, even though operational specialists will perform the surveys and monitoring.

Is this an appropriate assignment, and why?

A.

Yes, because the project executive is sufficiently senior to own the risk and the project manager should coordinate every response action

B.

Yes, because the project executive should own risks that could affect business justification

C.

No, because the project manager must be both the risk owner and the risk action owner

D.

No, because the owner monitors the risk and the action owner implements the response

Question # 8

At the start of stage 3, an approved request for change adds a promotional video to the stage. BuildyBrick has agreed to produce it, a product description has been prepared, and the project manager now needs to instruct the BuildyBrick team manager to begin the work.

During which ‘controlling a stage’ activity should this instruction be given?

A.

Authorize a work package

B.

Evaluate work package status

C.

Capture issues and risks

D.

Take corrective action

Question # 9

PROCESSES

During the ‘starting up a project’ process, the Head of the Portfolio Office explains to the prospective project executive that LouisShopping is strategically important to the LOB portfolio, must support increased business opportunities and is expected to open by the end of financial year three.

During which activity should this clarification of the mandate and business expectations take place?

A.

Appoint the project management team

B.

Appoint the project executive and manager

C.

Select the project approach

D.

Plan the initiation stage

Question # 10

At the start of stage 3, the project board inserts detailed recycling tolerances directly into each work package without the project manager agreeing the delegated targets with the relevant team managers.

Is this an appropriate application of the progress practice, and why?

A.

Yes, because team managers generally need to comply with sustainability metrics set directly by the project board

B.

Yes, because the project board should collect and review work-package progress directly from each delivery team

C.

No, because the project manager should authorize the work packages and agree the delegated sustainability tolerances

D.

No, because sustainability tolerances should be recorded only at project level rather than delegated through work packages