Which of the following statements about customer's quality expectations and acceptance criteria are true?
1. Customer's quality expectations form a specific and precise list of measurable criteria that a project product should meet in order to be acceptable to key stakeholders.
2. Acceptance criteria are often expressed in broad terms as a means to gain common understanding of general quality requirements.
Which is assumed to be a customer's responsibility in the PRINCE2 customer/supplier environment?
Who should act as the communication channel between a project and corporate or programme management?
Identify the missing word in the following sentence. The guiding obligations and good practices which determine whether the project is genuinely being managed using PRINCE2 form the [ ? ] of the method.
Which product identifies the management stages and timescales of a project?
Which level of management uses the mechanisms established by the Progress theme to control any unacceptable deviations?
What product is used to maintain a record of those who have an interest in the project and their information requirements?
What product would enable the Project Manager to review how a Work Package is performing against its cost tolerance?
Which characteristic of a project reflects that there are different perspectives and motivations for customers and suppliers?
Identify the missing word in the following sentence. A member of the Project Board is responsible for [ ? ] assurance.
Which should be used to document any uncompleted work that needs to be done to a project product after the project has closed?
Which of the following can be done to control the size of the Project Board on a project that involves multiple users and suppliers?
Identify the missing word(s) in the following sentence. The Quality theme provides a set of rules and procedures which ensure that the [ ? ] created meet(s) the needs of the business.
Which PRINCE2 principle is supported by the setting of tolerances for the three levels of plan?
Which details the identified threats and Opportunities related in the project?
Which principle should ensure that a project remains aligned with the objectives of the investing organizations?
Which is a description of a purpose of the 'managing product delivery’ process?
The project manager needs to know what modifications have been proposed to an approved product during the stage. Which management product should the project manager review?
In which step of the Issue management’ technique should Superseded versions be archives?
Which TWO are objectives of the closing a project: process?
1. To ensure the benefit reviews enable the project benefits to the confirmed
2. To update the business case so that the project hoard can decide whether to continue with the project
3. To ensure that the project team deliver the products to quality expectations
4. To hand over any open threats to operations
The project manager needs to record what will make file Users satisfied with the final product
Where should the project manager record this?
The project manager needs to know whether the response to a threat to the project has been actioned.
Which should the project manager review?
The project board is reviewing the project initiation documentation (PID) to decide whether the project should continue or close. What should the project board ensure the PID is aligned with?
Which process defines the work to deliver the major products ensuring that an organization uses its resources effectively?
Which plan should only be produced if the project is large and complex enough?
Identify the missing word(s) in the following sentence:
[ ? ] dependency is one between two products of a project, over which the project team has control.
Which is the BEST reason for a PRINCE? project to have at least two stages?
Which TWO are objectives of the ‘starting up a project’ process?
1. To create a common view of How the required quality will be achieved
2.To give authority to initiate the project
3. To appoint the resources needed to do the work to initiate the project
4. To ensure that projects are initiated based or agreed acceptance criteria for the project product.
According to the ‘exception management technique, which roles are MOST LIKELY to identity issues that exceed stage tolerances?
According to the ‘manage by exception’ principle, which aspect of performance sets limits against the cost of aggregated threats?
As part of the ‘closing a project’ process, the project manager needs to assess whether the outcomes are likely to deliver the expected performance improvements post-project.
In which step of 'business case management' technique should the project manager assess this?
Which term is defined as a product that will not meet is quality specifications?
How should effective issue management be applied When changing management products?
Which TWO are objectives of the ‘starting up a project’ process?
1. To provide an interface between the corporate layer and the project
2. To provide the required authority to initiate the project
3. To plan the work required for project initiation
4. To provide business justification for initiating the project
The senior user needs to ensure that the outputs will be used effectively to achieve the autcomes and realize the benefits.
Which element of effective business case management is the senior user applying?
The benefits Management approach has been reviewed by the project board to ensure there are sufficient benefit reviews after the project has closed.
Which principle is the project board applying?
Which term is defined as being achieved as a result of the activities undertaken to facilitate the change?
Which role is responsible for focusing on the safety and well-being of the project team?
What should set the expected success level for benefits, time, cost, quality, scope, sustainability and risk?
What is being addressed when the project manager plans to keep the CO2 emissions of the project aligned with the business strategy?
According to the guidance for effective quality management, when should the requirements for a product be captured?
The project manager has created a list of tasks to produce the project's products.
Which step of the ‘organizational design and development’ technique should be informed ty this 1st?
What should be recorded in a quality register?
1. Activities to ensure the products are fit for purpose
2. Identified threats and opportunities
3. Problems and concerns to be managed informally
4. Roles responsible for reviewing the project's products
Based on a review of lessons reports from previous projects, some proposals have been made on how to apply PRINCE to a project:
Which role should be accountable for approving these proposals?
Identify the missing word(s) in the following sentence.
The 'controlling a stage' process is used to manage and control each [ ? ] of a project.
A new team member has joined the project team and wants to understand who else is on the project team, and who they report to.
Which management product should the team member review?
Identify the missing words in the following sentence.
Project assurance personnel [ ? ] the project manager.
Identify the missing words in the following sentence.
The 'managing product delivery' process provides a controlled link between [ ? ] and a project manager.
Identify the missing words in the following sentence.
The 'starting up a project" process is triggered when a [ ? J is available.
According to the ‘defined roles and responsibilities’ principle, how many categories of stakeholder interest need to be represented in the project management team?
Identify the missing word in the following sentence.
[ ? ] is the measurable decline resulting from a negative outcome.
How often should the 'controlling a stage' process be used during a project?
Which statement describes the context of the 'initiating a project" process?
In which step of the 'planning' technique should a team manager break down the cost of delivering a work package?
What should be implemented using a risk budget?
1. A request for change
2. A contingent plan
3. Actions to avoid a risk from occurring
4. Responses to dis-benefits
What must be produced to meet the minimum requirements when applying the change theme?
According to the ‘exception management’ technique, when should the team manager raise an issue?
During the ‘initiating a project’ process, who specifies the required level of management control?
When tailoring PRINCE2 to suit the project, [?] may be changed to suit other standards or policies.
What should be considered when defining the number of management stages in a project?
What should the 'managing product delivery' process ensure?
1. That the planned products meet their quality criteria
2. That the stage plan is kept up to date
3. That the project board is provided with progress information
4. That the planned products are delivered within tolerance
Which statements about quality assurance and project assurance are CORRECT?
1. They are both independent of the project manager
2. They are both the responsibility of the project board
3. They are both independent from the project management team
4. They both assure that applicable standards are being used
Which of the following refers to the actions identified to bring a situation to a level where exposure to a risk is acceptable?
How does the project plan help to support the 'manage by stages' principle?
Identify the missing word in the following sentence.
The PRINCE2 method addresses project management with four integrated elements: principles, themes, [ ? ] and tailoring PRINCE2 to the project environment.
Which process provides the Project Board with sufficient information for it to review the success of a completed stage and confirm continued business justification?
Which is a purpose of the 'identify the risks' step within the recommended risk management procedure?
The application of which principle helps to define what should be included in a project?
Which product defines how the project board should approve the management products produced during the 'initiating a project' process?
What must be included in the risk management approach, as a minimum requirement for applying the risk theme?
Which role is responsible for appointing the senior user in a project that is independent from a program?
Where should a team manager look for information about the quality required for a product?
How does the project board use the 'manage by stages' principle to control the project?
To meet the minimum requirements for applying the progress theme, when must the business justification be reviewed?
What action is taken as part of the 'controlling a stage' process?
1. Create an exception plan
2. Authorize work to be done
3. Take corrective action
4. Obtain approvals for completed products