You'll find that our Prince2-Foundation exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these Prince2-Foundation sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any PRINCE2 7 Foundation written Exam practice test comfortably within the allotted time.

Question # 1

Where should a team manager look for information about the quality required for a product?

A.

Project initiation documentation

B.

Product description

C.

Team plan

D.

Quality management approach

Question # 2

Which statement about time-driven controls is CORRECT?

A.

Time-driven controls are used for monitoring the progress of work packages and management stages

B.

Time-driven controls take place when specific events happen

C.

Time-driven controls are produced at the end of a stage

D.

An exception report is a time-driven control

Question # 3

Which is a purpose of the 'directing a project' process?

A.

To exercise overall control over the project

B.

To take corrective action to control risks and issues

C.

To do the minimum in order to decide whether the project is feasible

D.

To update the project plan before the next stage

Question # 4

The project manager reviews whether there has been a Change in the way team members relate to each other.

Which principle is the project manager applying as part of the 'people' element?

A.

Manage by stages

B.

Focus on products

C.

Tailor to suit the project context

D.

Learn from experience

Question # 5

What is the project manager role responsible for?

A.

Approving the completion of each management stage

B.

Ensuring that the project produces the required products

C.

Defining the project-level tolerances

D.

Verifying that the project gives value for money

Question # 6

Which are purposes of the quality theme?

1. To implement continuous improvement during the project

2. To establish how the project will ensure that products created will be acceptable to key stakeholders

3. To ensure that the project is desirable and achievable

4. To identify, assess and control uncertainty

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Question # 7

In which step of the 'risk management technique should the organization's environment be considered?

A.

Identify

B.

Assess

C.

Plan

D.

Implement

Question # 8

Which is a description of a purpose of the communication management approach?

A.

To document for stakeholders the future business required to meet project objectives

B.

To document how the project team should control its interactions with stakeholders

C.

To document how to use financial incentives to motivate project team members

D.

To document the responsibilities of project team members for testing whether products are acceptable to users

Question # 9

Why is the 'initiating a project' process used?

A.

To decide which project approach is suitable for the project

B.

To fully understand how the project objectives will be achieved before committing significant resources

C.

To produce the required work packages

D.

To enable corporate or programme management to give authorization to deliver a project

Question # 10

What is an advantage of dividing the project into stages?

A.

Detailed plans can be prepared closer to the time events will take place

B.

the project board can delegate management of the project to team managers

C.

The project can be authorized by the project manager on a stage by stage basis

D.

The project brief can be updated towards the end of each stage