Question # 4

Which of the following statements about customer's quality expectations and acceptance criteria are true?

1. Customer's quality expectations form a specific and precise list of measurable criteria that a project product should meet in order to be acceptable to key stakeholders.

2. Acceptance criteria are often expressed in broad terms as a means to gain common understanding of general quality requirements.

A.

Only 1 is true

B.

Only 2 is true

C.

Both 1 and 2 are true

D.

Neither 1 or 2 are true

Full Access
Question # 5

Which is assumed to be a customer's responsibility in the PRINCE2 customer/supplier environment?

A.

Specify the desired result

B.

Provide the resources and skills to deliver the desired result

C.

Ensure the technical integrity of a project

D.

Develop a project's products

Full Access
Question # 6

Which is a purpose of the Managing Product Delivery process?

A.

Enable the Senior Supplier to be provided with sufficient information by the Project Manager so that they can review the success of the current Work Package

B.

Provide a controlled link between the Project Manager and the Team Manager(s)

C.

Enable the Project Board to request updates to the current Team Plan

D.

Establish solid foundations for the project

Full Access
Question # 7

Which is an objective of the Closing a Project process?

A.

Prepare the plan for the next stage

B.

Assess any benefits that have already been realized

C.

Produce a Benefits Review Plan to identify what benefits are expected

D.

Check that all benefits are realized before closing a project

Full Access
Question # 8

Who should act as the communication channel between a project and corporate or programme management?

A.

Project Board

B.

Project Assurance

C.

Project Manager

D.

Project Support

Full Access
Question # 9

What takes place during the Closing a Project process?

A.

The post-project benefits reviews are performed

B.

Ownership of the project's products is transferred to the customer

C.

An End Stage Report is prepared for the final stage

D.

The project closure notification is reviewed and approved

Full Access
Question # 10

Which is a purpose of the Controlling a Stage process?

A.

Assign work to be done and take corrective action to ensure that the stage remains within tolerance

B.

Provide a fixed reference point at which acceptance for the project product is confirmed

C.

Enable the Project Board to be provided with sufficient information to authorize the next stage

D.

Enable the organization to understand the work that needs to be done to deliver the project's products

Full Access
Question # 11

Which is an objective of the Closing a Project process?

A.

Review and approve the plan for project closure

B.

Review the performance of the project against its baseline

C.

Perform any post-project reviews

D.

Create a Benefits Review Plan

Full Access
Question # 12

What theme estimates the cost of delivering the project?

A.

Business Case

B.

Change

C.

Plans

D.

Progress

Full Access
Question # 13

Identify the missing word in the following sentence. The guiding obligations and good practices which determine whether the project is genuinely being managed using PRINCE2 form the [ ? ] of the method.

A.

Principles

B.

Themes

C.

Processes

D.

Techniques

Full Access
Question # 14

Which product identifies the management stages and timescales of a project?

A.

Project Brief

B.

Project Product Description

C.

Project Plan

D.

Initiation Stage Plan

Full Access
Question # 15

What is the definition of a project outcome?

A.

A measurable improvement that is perceived as an advantage by one or more stakeholders

B.

The reason for the project

C.

The result of the change derived from using the project's outputs

D.

The project's specialist products.

Full Access
Question # 16

Which is NOT a purpose of the Organization theme?

A.

Define a project management team structure

B.

Define the level of tolerance for each level of the project management team

C.

Define the Project Board's responsibility for directing the project

D.

Define which role is accountable for the project's success

Full Access
Question # 17

Which level of management uses the mechanisms established by the Progress theme to control any unacceptable deviations?

A.

Only corporate or programme management

B.

Only the Project Board

C.

Only the Project Manager

D.

All levels of management

Full Access
Question # 18

Which is a benefit of using PRINCE2?

A.

Is a method specifically designed for technical projects

B.

Provides for the efficient and economic use of management time

C.

Includes many of the proven planning techniques, such as critical path analysis

D.

Can be used to manage both projects and programmes

Full Access
Question # 19

Which is NOT one of the PRINCE2 integrated elements?

A.

Tailoring PRINCE2 to the project environment

B.

The processes

C.

The products

D.

The themes

Full Access
Question # 20

What product is used to maintain a record of those who have an interest in the project and their information requirements?

A.

Project Plan

B.

Communication Management Strategy

C.

Project Brief

D.

Project Product Description

Full Access
Question # 21

Which is NOT a purpose of a Benefits Review Plan?

A.

Define the period over which the cost-benefit analysis will be based

B.

Describe how to measure the performance of the project's products in operational use

C.

Define the scope, timing and ownership of the benefit reviews required

D.

Describe how to measure and confirm any benefits that are to be realised after the project is closed

Full Access
Question # 22

Which is a recommended quality review team role?

A.

Project Manager

B.

Assurance

C.

Project Support

D.

Administrator

Full Access
Question # 23

What is the first task of product-based planning?

A.

Produce the Initiation Stage Plan

B.

Write the Project Product Description

C.

Identify dependencies

D.

Create the product breakdown structure

Full Access
Question # 24

What product would enable the Project Manager to review how a Work Package is performing against its cost tolerance?

A.

Configuration Item Record

B.

Quality Register

C.

Highlight Report

D.

Checkpoint Report

Full Access
Question # 25

Which characteristic of a project reflects that there are different perspectives and motivations for customers and suppliers?

A.

Change

B.

Cross-functional

C.

Unique

D.

Risk

Full Access
Question # 26

Identify the missing word in the following sentence. A member of the Project Board is responsible for [ ? ] assurance.

A.

quality

B.

supplier

C.

risk

D.

product

Full Access
Question # 27

Which statement defines a risk?

A.

A certain event occurring in the future that will have a negative impact on the project's objectives

B.

An event that has already occurred that the Project Manager must deal with immediately

C.

An uncertain event, or set of events that, should it or they occur, will have an effect on the achievement of objectives

D.

An uncertain event, or set of events that, should it or they occur, will be automatically escalated to the Project Board for a response

Full Access
Question # 28

Which should be used to document any uncompleted work that needs to be done to a project product after the project has closed?

A.

Off-specifications

B.

Follow-on action recommendations

C.

Issue Register

D.

Risk Register

Full Access
Question # 29

Which of the following can be done to control the size of the Project Board on a project that involves multiple users and suppliers?

A.

Create a separate Project Board to manage the supplier elements of the project

B.

Create multiple smaller Project Boards during the process of Starting up a Project, one for each of the project's stages.

C.

Create user and supplier groups

D.

Appoint corporate quality assurance to perform the Project Assurance role for all members of the Project Board

Full Access
Question # 30

Which statement about the quality review technique is FALSE?

A.

It enables a check to be made on a product's fitness for purpose

B.

It defines the quality responsibilities of the project team

C.

It supports the management of future changes by providing a baseline for a product

D.

It is used to gain wider acceptance of a product by involving key interested parties

Full Access
Question # 31

How many roles make up the Project Board?

A.

One

B.

Two

C.

Three

D.

Four

Full Access
Question # 32

Identify the missing word(s) in the following sentence. The Quality theme provides a set of rules and procedures which ensure that the [ ? ] created meet(s) the needs of the business.

A.

controls

B.

products

C.

project management team

D.

stages

Full Access
Question # 33

Which is a purpose of the Initiating a Project process?

A.

Decide if it is worthwhile to initiate a project

B.

Decide on the project approach

C.

Establish solid foundations for a project

D.

Identify the number of Work Packages required

Full Access
Question # 34

Which PRINCE2 principle is supported by the setting of tolerances for the three levels of plan?

A.

Manage by stages

B.

Manage by exception

C.

Continued business justification

D.

Learn from experience

Full Access
Question # 35

Which is an objective of the Managing Product Delivery process?

A.

Sign-off completed Work Packages

B.

Ensure the Business Case is kept under review

C.

Report progress to the Project Board

D.

Ensure that work on products is authorized and agreed with the team

Full Access
Question # 36

Which details the identified threats and Opportunities related in the project?

A.

Risk management approach

B.

Project plan

C.

Risk register

D.

Business case

Full Access
Question # 37

Which principle should ensure that a project remains aligned with the objectives of the investing organizations?

A.

Focus on products

B.

Manage by exception

C.

Tailor to suit the project

D.

Ensure continued business justification

Full Access
Question # 38

How do issue management and change control relate to each other?

A.

Change control and Issue management are separate processes

B.

Issue management is part of change control

C.

change control is part of issue management

D.

issue management and change control are identical

Full Access
Question # 39

Which is a description of a purpose of the 'managing product delivery’ process?

A.

To agree requirements for the delivery of specific products between the project manager and the team manager

B.

To report progress towards the delivery of a stage’s products to the project board

C.

To recognize that the project has no further contribution make towards achieving project objectives

D.

To plan how the project will approach the work to deliver the project products

Full Access
Question # 40

The project manager needs to know what modifications have been proposed to an approved product during the stage. Which management product should the project manager review?

A.

issue register

B.

issue report

C.

Issue management approach

D.

Risk management approach

Full Access
Question # 41

Which is a definition of management?

A.

Directing the execution of project tasks as agreed for the project

B.

Away of working that characterises a group of people

C.

Being accountable to the business for the success of the project

D.

The party responsible for commissioning the project

Full Access
Question # 42

Which is a definition of management?

A.

Instructing the execution of tasks in line with agreed ways of working

B.

Translating stakeholder requirements into quality criteria

C.

Assigning people with specific skills and capabilities to work on multiple projects

D.

Defining, assuring, and accepting products back into the business

Full Access
Question # 43

In which step of the Issue management’ technique should Superseded versions be archives?

A.

Implementing changes

B.

Assessing issues

C.

capturing issues

D.

Deciding on changes

Full Access
Question # 44

Which TWO are objectives of the closing a project: process?

1. To ensure the benefit reviews enable the project benefits to the confirmed

2. To update the business case so that the project hoard can decide whether to continue with the project

3. To ensure that the project team deliver the products to quality expectations

4. To hand over any open threats to operations

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Full Access
Question # 45

The project manager needs to record what will make file Users satisfied with the final product

Where should the project manager record this?

A.

Quality register

B.

Project plan

C.

Project product description

D.

Quality management approach

Full Access
Question # 46

The project manager needs to know whether the response to a threat to the project has been actioned.

Which should the project manager review?

A.

Risk register

B.

Product register

C.

Risk management approach

D.

Checkpoint report

Full Access
Question # 47

When is a work breakdown structure MOST useful?

A.

When there are multiple work packages with a mix of internal and external resources

B.

in a simple project with one work package for the work of a small team

C.

When establishing a change authority aligned to project tolerances

D.

When assuring business, user and supplier aspects of project performance

Full Access
Question # 48

The project board is reviewing the project initiation documentation (PID) to decide whether the project should continue or close. What should the project board ensure the PID is aligned with?

A.

The business objectives

B.

The business’ existing governance practices

C.

The project's delivery method

D.

The ways of working used on previous projects

Full Access
Question # 49

Which process defines the work to deliver the major products ensuring that an organization uses its resources effectively?

A.

Initiating a project

B.

Starting up a project

C.

Controlling a stage

D.

Managing product delivery

Full Access
Question # 50

Which plan should only be produced if the project is large and complex enough?

A.

Project plan

B.

Stags plan

C.

Team plan

D.

Exception plan

Full Access
Question # 51

Identify the missing word(s) in the following sentence:

[ ? ] dependency is one between two products of a project, over which the project team has control.

A.

An internal

B.

A schedule-driven

C.

An external

D.

A resource-driven

Full Access
Question # 52

Which is definition of culture?

A.

The set of shared attitudes, values, goals, and ways of working that characterize a group of people

B.

The process when people from across the project ecosystem work together

C.

An essential aspect of project management that needs to be continually addressed

D.

The tailoring required to take into account the complexity or simplicity of a project

Full Access
Question # 53

Which is the BEST reason for a PRINCE? project to have at least two stages?

A.

It enables the project team to close the project in an orderly fashion

B.

it enables the project board to decide whether to proceed with the delivery of the project product

C.

It enables the project team to change the scope of the project by agreeing the impact on the business case

D.

It enables the project board to approve the appointment of external contractors, when required

Full Access
Question # 54

Which TWO are objectives of the ‘starting up a project’ process?

1. To create a common view of How the required quality will be achieved

2.To give authority to initiate the project

3. To appoint the resources needed to do the work to initiate the project

4. To ensure that projects are initiated based or agreed acceptance criteria for the project product.

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Full Access
Question # 55

According to the ‘exception management technique, which roles are MOST LIKELY to identity issues that exceed stage tolerances?

A.

Project executive AND senior user

B.

Senior supplier AND team manager

C.

Project executive AND project manager

D.

Project manager AND team manager

Full Access
Question # 56

According to the ‘manage by exception’ principle, which aspect of performance sets limits against the cost of aggregated threats?

A.

Risk

B.

Scope

C.

Quality

D.

Cost

Full Access
Question # 57

As part of the ‘closing a project’ process, the project manager needs to assess whether the outcomes are likely to deliver the expected performance improvements post-project.

In which step of 'business case management' technique should the project manager assess this?

A.

Develop

B.

Check ay

C.

Maintain

D.

Confirm

Full Access
Question # 58

Which term is defined as a product that will not meet is quality specifications?

A.

Off-specification

B.

Request for change

C.

Concern

D.

Problem

Full Access
Question # 59

How should effective issue management be applied When changing management products?

A.

By changing the issue management approach at the end of each stage to reflect lessons

B.

By creating new versions of a management product when a change is approved

C.

By Implementing a change budget to fund changes to the project product

D.

By recording the required change to a management product as an off-specification

Full Access
Question # 60

Which TWO are objectives of the ‘starting up a project’ process?

1. To provide an interface between the corporate layer and the project

2. To provide the required authority to initiate the project

3. To plan the work required for project initiation

4. To provide business justification for initiating the project

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Full Access
Question # 61

The senior user needs to ensure that the outputs will be used effectively to achieve the autcomes and realize the benefits.

Which element of effective business case management is the senior user applying?

A.

Aligning products to business objectives and tolerances

B.

The business case lifecycle

C.

Establishing business justification

D.

Planning benefit reviews during the project

Full Access
Question # 62

The benefits Management approach has been reviewed by the project board to ensure there are sufficient benefit reviews after the project has closed.

Which principle is the project board applying?

A.

Manage by exception

B.

Manage by stages

C.

Ensure continued business Justification

D.

Focus on products

Full Access
Question # 63

What is a purpose of the ‘quality’ practice?

A.

To predict whether the project will deliver on time and to cost and whether the benefits will outweigh the costs

B.

To resolve off-specifications, that are Identified during the project, at the end of the project

C.

To plan the project so that there is time to deal with quality defects late in the project

D.

To identify the user's expectations and determine how the project will achieve them

Full Access
Question # 64

Which term is defined as being achieved as a result of the activities undertaken to facilitate the change?

A.

Outcome

B.

Benefit

C.

output

D.

Request for change

Full Access
Question # 65

Which role is responsible for focusing on the safety and well-being of the project team?

A.

Project executive

B.

Project board

C.

Project manager

D.

Team manager

Full Access
Question # 66

Which statement BEST describes how approved plans enable control?

A.

By defining the quality specifications of individual products in product descriptions

B.

By enabling the controlled consideration of business opportunities

C.

By defining the benefits that need to be realized through the benefits management approach

D.

By defining what is within the approved project scope to avoid scope creep

Full Access
Question # 67

What should set the expected success level for benefits, time, cost, quality, scope, sustainability and risk?

A.

Performance target

B.

Project baseline

C.

Integrated elements

D.

Project context

Full Access
Question # 68

How does product-based planning help to determine the project approach?

A.

By Identifying the outputs that the project trust deliver

B.

By planning in detail how to deliver the outputs over a more predictable time scale

C.

By managing constraints to the planned completion date for the project

D.

By dividing the delivery of the project's outputs into stages which do not overlap

Full Access
Question # 69

What is being addressed when the project manager plans to keep the CO2 emissions of the project aligned with the business strategy?

A.

Benefits sustainability

B.

Product sustainability

C.

Delivery sustainability

D.

Quality sustainability

Full Access
Question # 70

According to the guidance for effective quality management, when should the requirements for a product be captured?

A.

When the project team realizes that the product is needed

B.

When the project team needs to test the product

C.

When the project team needs to know whether the product has been approved

D.

When the project team needs to know how the product will be delivered

Full Access
Question # 71

Which is 3 purpose of the ‘plans! practice?

A.

To enable an event that requires project management consideration to be controlled

B.

To provide the standards against which the project products can be quality controlled

C.

To provide the basis of control against which a project's progress can be monitored

D.

To enable control of opportunities and threats, that could Impact on delivery of the business objectives

Full Access
Question # 72

The project manager has created a list of tasks to produce the project's products.

Which step of the ‘organizational design and development’ technique should be informed ty this 1st?

A.

Design the project ecosystem

B.

Understand the organizational ecosystem

C.

Manage the ongoing changes to the project ecosystem

D.

Develop the project ecosystem

Full Access
Question # 73

What should be recorded in a quality register?

1. Activities to ensure the products are fit for purpose

2. Identified threats and opportunities

3. Problems and concerns to be managed informally

4. Roles responsible for reviewing the project's products

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Full Access
Question # 74

What is an advantage of applying the 'manage by stages' principle?

A.

The PRINCE2 method can be used for any type of project

B.

The project delivers benefits that are aligned with strategic objectives

C.

The project has decision points so that it does not run on in an uncontrolled manner

D.

Tolerances can be defined for delegated authority

Full Access
Question # 75

What should the benefits management approach define?

A.

What actions will be taken to ensure the project's outcomes are achieved

B.

What will be used to record the effectiveness of the project's approaches

C.

How the project has progressed against its plans

D.

The suitability of the project management team structure

Full Access
Question # 76

Based on a review of lessons reports from previous projects, some proposals have been made on how to apply PRINCE to a project:

Which role should be accountable for approving these proposals?

A.

Project board

B.

Project manager

C.

Project assurance

D.

Business layer

Full Access
Question # 77

Identify the missing word(s) in the following sentence.

The 'controlling a stage' process is used to manage and control each [ ? ] of a project.

A.

delivery step

B.

benefit

C.

delivery stage

D.

team plan

Full Access
Question # 78

Which is a minimum requirement when applying the 'risk' theme?

A.

To identity and ring-fence an explicit risk budget within the project's budget

B.

To describe the probability impact grid in the risk management approach

C.

To appoint project assurance to maintain the risk register during initiation

D.

To assess if risks might have a material impact on business justification

Full Access
Question # 79

A new team member has joined the project team and wants to understand who else is on the project team, and who they report to.

Which management product should the team member review?

A.

Project plan

B.

Project management team structure

C.

Role descriptions

D.

Project log

Full Access
Question # 80

How are team managers involved in tailoring PRINCE2 suit the project?

A.

Team managers are accountable for the tailoring of the work packages

B.

Team managers may advice on tailoring to improve the management of work packages

C.

Team managers should not be involved in tailoring PRINCE2

D.

Team managers should document the tailoring of the work packages

Full Access
Question # 81

Who are considered as the stakeholders in a project?

A.

Only those benefitting the project

B.

Everyone in the corporate organization

C.

Everyone involved in or affected by the project

D.

Only those who are users of the products

Full Access
Question # 82

Identify the missing words in the following sentence.

Project assurance personnel [ ? ] the project manager.

A.

are able to overturn the decisions of

B.

must be accountable to

C.

should support

D.

report to the project board and

Full Access
Question # 83

Which is a purpose of the 'controlling a stage' process?

A.

To review the success of the project at the end of a management stage

B.

To agree work package acceptance and delivery requirements

C.

To produce regular highlight reports for the project board

D.

To re-plan the current stage and the project when requested

Full Access
Question # 84

Which is an assumption about the PRINCE2 customer/supplier environment?

A.

The supplier will pay for the project

B.

The customer will provide the resources to deliver the products

C.

The customer will specify the desired result

D.

The supplier will tailor the project's application of PRINCE2

Full Access
Question # 85

Identify the missing words in the following sentence.

The 'managing product delivery' process provides a controlled link between [ ? ] and a project manager.

A.

project assurance

B.

the project board

C.

the corporate, programme management or the customer

D.

a team manager

Full Access
Question # 86

Identify the missing words in the following sentence.

The 'starting up a project" process is triggered when a [ ? J is available.

A.

project business case

B.

project mandate

C.

stage plan

D.

work package

Full Access
Question # 87

According to the ‘defined roles and responsibilities’ principle, how many categories of stakeholder interest need to be represented in the project management team?

A.

One

B.

Two

C.

Three

D.

Six

Full Access
Question # 88

Which is a minimum requirement for applying the organization theme?

A.

The project's approach to engaging with its stakeholders must be defined

B.

Roles must be combined to reduce the number of individuals needed on the project

C.

During a procurement the senior supplier must be appointed from the customer organization

D.

The project team must change at each end stage of the project life cycle

Full Access
Question # 89

Identify the missing word in the following sentence.

[ ? ] is the measurable decline resulting from a negative outcome.

A.

An exception

B.

A dis-benefit

C.

An off-specification

D.

A risk

Full Access
Question # 90

Which statement about project roles is CORRECT?

A.

The project organization must be defined using the roles and responsibilities in PRINCE2

B.

The project team structure defined in PRINCE2 must be used, but other roles may be added

C.

The project board roles defined in PRINCE2 must be used, but other roles can be defined as required

D.

Any role can be defined as required the responsibilities defined in PRINCE2 are fulfilled

Full Access
Question # 91

How often should the 'controlling a stage' process be used during a project?

A.

Once, for the whole project

B.

For each delivery stage in the project

C.

Whenever the project board meets

D.

Twice, for initiation and for the rest of the project

Full Access
Question # 92

Which statement describes the context of the 'initiating a project" process?

A.

The project is viewed from the perspective of the project board in this process

B.

This process should result in key stakeholders being committed to the project

C.

This process is triggered by the assembly of the project brief

D.

The 'controlling a stage' process will start immediately after this process

Full Access
Question # 93

In which step of the 'planning' technique should a team manager break down the cost of delivering a work package?

A.

Preparing estimates

B.

Defining and analyzing the products

C.

Organizing work packages

D.

Preparing a schedule

Full Access
Question # 94

Which is a purpose of a quality register?

A.

To record cross-references to issues relating to the quality of the products

B.

To record the date a completed work package was received

C.

To provide the status of quality activities carried out for completed products

D.

To capture quality concerns about completed products

Full Access
Question # 95

Which describes a time-driven control?

A.

The dates for the project's end stage assessment included in the project plan

B.

The expected frequency of progress reports specified in a work package

C.

The expected dates for planned checks of specialist products included in a stage plan

D.

The planned exception assessment meeting to authorize a requested exception plan

Full Access
Question # 96

Which is a purpose of the quality theme?

A.

To check that the project is viable and achievable

B.

To ensure that the project outputs are agreed

C.

To ensure that formal issues are recorded

D.

To enable the project to be managed according to plan

Full Access
Question # 97

What is an advantage of applying the 'learn from experience' principle?

A.

It allows the project board to delegate cost tolerances to the project manager

B.

It allows the project team to fully understand their roles and responsibilities

C.

It allows the project manager to delegate time tolerances to the team managers

D.

It allows the project team to identify improvements to be made during the project

Full Access
Question # 98

What 15the purpose of the ‘progress! practice?

A.

To review whether the use of the products is likely to lead to the expected benefits

B.

To define the roles and responsibilities for monitoring progress

C.

To measure actual achievements against the planned time and cost targets for the project

D.

To control events that could have a positive or negative effect on project objectives

Full Access
Question # 99

Which is a minimum requirement for applying the change theme?

A.

To identify whether an issue affects the continuation of the project

B.

To ensure each change is managed as an exception

C.

To produce a breakdown of the products to be produced

D.

To tailor all changes to improve the quality of the project

Full Access
Question # 100

What should be implemented using a risk budget?

1. A request for change

2. A contingent plan

3. Actions to avoid a risk from occurring

4. Responses to dis-benefits

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Full Access
Question # 101

What must be produced to meet the minimum requirements when applying the change theme?

A.

A change budget for the analysis of change

B.

Records of the decisions made on all issues

C.

Documents recording the version of each product

D.

Status reports on all products being produced

Full Access
Question # 102

According to the ‘exception management’ technique, when should the team manager raise an issue?

A.

When the team manager predicts that a product will cause a stage to exceed its time tolerance

B.

When the team manager identifies that a product is going to be delivered late

C.

when the team manager predicts that a product will cause a work package to exceed its time tolerance

D.

when the team manager identifies that the work package has already exceeded its time tolerance

Full Access
Question # 103

During the ‘initiating a project’ process, who specifies the required level of management control?

A.

Corporate, programme management or customer

B.

Project board

C.

Project manager

D.

Project assurance

Full Access
Question # 104

When tailoring PRINCE2 to suit the project, [?] may be changed to suit other standards or policies.

A.

Defined acceptance criteria

B.

the PRINCE2 principles

C.

the terminology used

D.

the number of themes applied

Full Access
Question # 105

When is the 'managing a stage boundary' process used?

A.

Immediately alter the project board has authorized the previous stage

B.

Immediately after the project board has authorized the next stage

C.

Near the end of each stage

D.

Near the end of delivery stages

Full Access
Question # 106

What should be considered when defining the number of management stages in a project?

A.

When the team managers are available

B.

When key decisions need to be made

C.

When highlight reports will be submitted

D.

When project support will be available

Full Access
Question # 107

Which is part of quality control?

A.

Undertaking quality reviews

B.

Writing product descriptions

C.

Providing assurance that the project is being conducted properly

D.

Documenting the customer's quality expectations

Full Access
Question # 108

What may be funded from a risk budget?

A.

Corrections required due to off-specifications

B.

Impact analysis of requests for change

C.

Implementation of a fallback plan

D.

Preparation of the risk management approach

Full Access
Question # 109

What should the 'managing product delivery' process ensure?

1. That the planned products meet their quality criteria

2. That the stage plan is kept up to date

3. That the project board is provided with progress information

4. That the planned products are delivered within tolerance

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Full Access
Question # 110

Which is a minimum requirement for applying the organization theme?

A.

To document the project management team structure

B.

To define the experience required for each project role

C.

To include external stakeholders on the project board

D.

To train project team members in the use of PRINCE2

Full Access
Question # 111

Which statements about quality assurance and project assurance are CORRECT?

1. They are both independent of the project manager

2. They are both the responsibility of the project board

3. They are both independent from the project management team

4. They both assure that applicable standards are being used

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Full Access
Question # 112

Which of the following refers to the actions identified to bring a situation to a level where exposure to a risk is acceptable?

A.

Risk category

B.

Risk description

C.

Risk response

D.

Risk status

Full Access
Question # 113

How does the project plan help to support the 'manage by stages' principle?

A.

By identifying the customer's quality expectations

B.

By defining products to ensure they are fit for purpose

C.

By identifying the major control points and milestones

D.

By estimating the timescales and costs of the project

Full Access
Question # 114

When should the level of tailoring be defined?

A.

During the initiation stage

B.

When reviewing what has been learned to date

C.

As a response to issues and risks experienced

D.

Before the project is triggered by the project mandate

Full Access
Question # 115

Identify the missing word in the following sentence.

The PRINCE2 method addresses project management with four integrated elements: principles, themes, [ ? ] and tailoring PRINCE2 to the project environment.

A.

activities

B.

processes

C.

products

D.

quality

Full Access
Question # 116

Which process provides the Project Board with sufficient information for it to review the success of a completed stage and confirm continued business justification?

A.

Controlling a Stage

B.

Closing a Project

C.

Directing a Project

D.

Managing a Stage Boundary

Full Access
Question # 117

Which is an objective of the 'starting up a project' process?

A.

To approve the initiation stage

B.

To select the project mandate

C.

To define the project quality management approach

D.

To appoint the project management team

Full Access
Question # 118

Which is a minimum requirement for applying the business case theme?

A.

To provide statements of actual benefits at benefits reviews

B.

To report on project performance at project closure

C.

To define the actions required to confirm the project's benefits are realized

D.

To monitor changes to the project plan to identify exceptions

Full Access
Question # 119

Which is a purpose of the 'identify the risks' step within the recommended risk management procedure?

A.

To identify responses to risks documented in the business case

B.

To identify information about the project environment and objectives

C.

To identify the roles to be involved in risk management activities

D.

To identify uncertainties that may impact on the delivery of the project objectives

Full Access
Question # 120

What is a supplier of a PRINCE2 project responsible for?

A.

Providing the project mandate

B.

Providing resources to deliver the project outputs

C.

Establishing the project's governance

D.

Realizing the benefits from the project

Full Access
Question # 121

The application of which principle helps to define what should be included in a project?

A.

Defined roles and responsibilities

B.

Focus on products

C.

Manage by stages

D.

Continued business justification

Full Access
Question # 122

Which product defines how the project board should approve the management products produced during the 'initiating a project' process?

A.

Communication management approach

B.

Quality management approach

C.

Project plan

D.

Initiation stage plan

Full Access
Question # 123

What must be included in the risk management approach, as a minimum requirement for applying the risk theme?

A.

A description of the risk management procedure

B.

An explanation of the company's risk appetite

C.

The names of the assigned actionees for each risk

D.

Estimations of the likelihood and impact of risks

Full Access
Question # 124

Why is a Project Brief produced?

A.

To act as a trigger for the Starting up a Project process

B.

To record the strategies and management controls to be used by a project

C.

To provide a full and firm foundation for the initiation of a project

D.

To be used by the Project Board as a basis for reviewing the progress of a project

Full Access
Question # 125

Which role is responsible for appointing the senior user in a project that is independent from a program?

A.

The project manager

B.

The executive

C.

Corporate, program management or the customer

D.

Project assurance

Full Access
Question # 126

What must a PRINCE2 project demonstrate?

A.

Application of PRINCE2 principles

B.

Application of proper leadership skills

C.

Application of the activities in each process

D.

Application of tools appropriate for the industry

Full Access
Question # 127

Which describes a risk event?

A.

The area of uncertainty in terms of the threat or opportunity

B.

The derivation or sources of a potential risk to the project

C.

The achievement of a milestone on the project plan

D.

The sequence of events and actions that will be put in place if a risk occurs

Full Access
Question # 128

Where should a team manager look for information about the quality required for a product?

A.

Project initiation documentation

B.

Product description

C.

Team plan

D.

Quality management approach

Full Access
Question # 129

How does the project board use the 'manage by stages' principle to control the project?

A.

By approving the project management team

B.

By reviewing project viability at defined intervals

C.

By ensuring that the benefits are managed and controlled

D.

By reviewing previous project closure documentation

Full Access
Question # 130

Which statement about time-driven controls is CORRECT?

A.

Time-driven controls are used for monitoring the progress of work packages and management stages

B.

Time-driven controls take place when specific events happen

C.

Time-driven controls are produced at the end of a stage

D.

An exception report is a time-driven control

Full Access
Question # 131

Which product identifies how often stakeholders require information?

A.

Communication management approach

B.

Lessons report

C.

Configuration item record

D.

Benefits management approach

Full Access
Question # 132

To meet the minimum requirements for applying the progress theme, when must the business justification be reviewed?

A.

At the start of the project

B.

Throughout each stage

C.

When a change is raised

D.

In exception situations

Full Access
Question # 133

Which describes an off-specification?

A.

An interdependency between products that was previously unidentified

B.

The addition of an improvement to a product description

C.

A prototype demonstrating a possible design solution

D.

The production of more than the defined quantity of a specialist product

E.

That the right people are involved in appropriate roles

Full Access
Question # 134

Which is a purpose of the 'controlling a stage' process?

A.

To produce a team plan for the work to be assigned to a team manager

B.

To select and implement actions that will resolve deviations from a plan within tolerance

C.

To obtain approvals for products delivered in a work package

D.

To update a project plan to incorporate the actuals from a stage plan

Full Access
Question # 135

Who represents the three project interests on a project?

A.

Project manager

B.

Project support

C.

External project stakeholders

D.

Project board

Full Access
Question # 136

What action is taken as part of the 'controlling a stage' process?

1. Create an exception plan

2. Authorize work to be done

3. Take corrective action

4. Obtain approvals for completed products

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Full Access
Question # 137

Why is the 'initiating a project' process used?

A.

To decide which project approach is suitable for the project

B.

To fully understand how the project objectives will be achieved before committing significant resources

C.

To produce the required work packages

D.

To enable corporate or programme management to give authorization to deliver a project

Full Access
Question # 138

Which is a minimum requirement for applying the plans theme?

A.

The project must have at least two management stages

B.

The team managers in the project must prepare team plans

C.

Scope tolerance must be prioritized using MoSCoW

D.

The project plan must be presented as a Gantt chart

Full Access