Labour Day Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: buysanta

Exact2Pass Menu

Question # 4

Which statement about the ‘protect the level of quality’ target is CORRECT?

A.

It is achieved by ensuring that all features are delivered

B.

It is unlikely to be achieved if incomplete user documentation is provided

C.

It allows change at the detailed level to be handled dynamically

D.

It avoids the use of extra people to improve progress during a timebox

Full Access
Question # 5

How is the ‘tailor to suit the project’ principle applied in an agile context?

A.

By flexing what is produced to stay in control and deliver value

B.

By emphasizing tolerances on what is being delivered

C.

By using the Agilometer to assess the project environment

D.

By fitting releases into planned management stages

Full Access
Question # 6

Which should be an objective of a retrospective?

A.

To identify many process improvements and implement them

B.

To identify key process improvements to implement in the next sprint

C.

To encourage the team to bond by allowing social activities to take place

D.

To focus on objective learning rather than subjective feelings and emotions

Full Access
Question # 7

How should product-based planning be used as part of PRINCE2 Agile?

A.

To track progress against the team plan

B.

To create the project plan using empiricism

C.

To enable team planning to be predictive

D.

To plan by focusing on the features required

Full Access
Question # 8

Who needs to be aware that flexing what is delivered may affect the expected benefits of the project?

A.

Customer subject matter expert and the supplier representative

B.

The team manager and the senior supplier

C.

The project manager and the project board

D.

The team quality assurance and project support

Full Access
Question # 9

Which is a benefit of the Lean Startup approach to releasing a product?

A.

It provide a technique to reduce the testing of a product before release

B.

It enables the release plans to be synchronized with the PRINCE2 plans

C.

It reduces the number of people needed to manage a release of a product

D.

It provides quick feedback that can be responded to at the earliest opportunity

Full Access
Question # 10

What is typically displayed on a board to show progress to people working on a project?

A.

Agilometer assessment

B.

Product backlog

C.

Information radiator

D.

User story

Full Access
Question # 11

When tailoring the plans theme in an agile environment, what is recommended about using a Gantt chart?

A.

It should be used when planning at the delivery level

B.

It should be used when planning at the project level

C.

It should be used when controlling the quality of the products delivered

D.

It should be used when monitoring the amount of products delivered

Full Access
Question # 12

How does PRINCE2 Agile describe Scrum?

A.

Scrum is an IT method

B.

Scrum is agile and agile is Scrum

C.

Scrum is the most well-known agile framework

D.

Scrum is a project management framework

Full Access
Question # 13

Which statement describes how the PRINCE2 ‘starting up a project’ process can be applied in an agile environment?

A.

PRINCE2 is predictive, but not emergent

B.

PRINCE2 is predictive and can be emergent

C.

PRINCE2 requires a lengthy start to a project

D.

PRINCE2 requires a disruptive start to a project

Full Access