You'll find that our PSPO-II exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these PSPO-II sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Professional Scrum Product Owner™ II (PSPO 2) practice test comfortably within the allotted time.

Question # 11

You are the Product Owner at a small company with a single product. You have authority over

pricing, promotion, and how much is invested in new features or capabilities. Your product has:

. High Current Value - as indicated by high customer satisfaction.

. High Unrealized Value - as indicated by low market share.

Using those two data points, what is the first action you should take to increase the business

performance of the product?

(choose the best answer)

A.

Increase the number of product features to attract a greater number of customers.

B.

Release an identical product to market, but give it a new product name.

C.

Drop the price for the product to attract a greater number of customers.

D.

Improve the marketing of the product to attract a greater number of customers.

Question # 12

What is the Product Owner responsible for during the Sprint Retrospective?

(choose the best answer)

A.

Capturing requirements for the Product Backlog.

B.

They do not have to be there.

C.

Participating as a Scrum Team member.

D.

Summarizing and reporting the discussions to the stakeholders that they represent in the Scrum Team.

Question # 13

If a Scrum Team uses Product Backlog refinement, when should it occur?

(choose the best two answers)

A.

The Product Owner takes the time between the Sprints to do it.

B.

Business Analysts in the organization should do this work for the Scrum Team 1-

2 Sprints ahead of the development Sprints.

C.

The Product Owner and the Developers can refine the Product Backlog during

any Sprint as needed, ideally in advance of the upcoming Sprint.

D.

The Product Owner must do this as essential work in Sprint 0.

E.

The Product Owner and the Developers do it in the current Sprint if they have

been unable to do it in preceding Sprints.

Question # 14

You are a Product Owner for a product with a rapidly declining customer base.

Despite data that indicates the decline is due to a shrinking market, rather than a lack of new

features, an influential stakeholder insists on adding more features to attract new customers.

The influential stakeholder also says that if you do not add new features you risk losing your

most profitable customer.

Which two of the following actions might you take?

(choose the best two answers)

A.

Collaborate with the stakeholder to run a small experiment to validate their

opinion.

B.

Collaborate with other stakeholders and use a voting system to decide which

options should be considered.

C.

Acknowledge the views of the influential stakeholder but decline to add more

features to the product.

D.

Agree with the stakeholder and add features to the Product Backlog as it might

increase your customer base.

Question # 15

The most important thing a Product Owner can do is:

(choose the best answer)

A.

Determine the release schedule and contents.

B.

Ensure that all stakeholder needs are met.

C.

Function as the single source of truth for all requirements.

D.

Maximize the value delivered by the product.

Question # 16

A " cone of uncertainty " can be used to do what?

(choose the best answer)

A.

Represent the relative level of difficulty for predicting the velocity of individual team

members.

B.

Rapidly identify and prioritize all uncertainties.

C.

Determine whether to cut quality, similar to the " Iron Triangle " of project

management.

D.

Visualize the uncertainty of the potential value that a Scrum Team delivers over time.

Question # 17

Why should the Product Owner care that the Developers adhere to the Definition of Done?

(choose the best two answers)

A.

To influence the Total Cost of Ownership of the product.

B.

To have transparency into what has been done at the end of each Sprint.

C.

To be able to reprimand the team when they do not meet their velocity goal for

the Sprint.

D.

To ensure the Developers achieve a high level of productivity over time.

Question # 18

What is typical work for a Product Owner in a Sprint?

(choose the best two answers)

A.

Collaborate with stakeholders, user communities and other Product Owners.

B.

Work with the Developers on Product Backlog refinement.

C.

Attend every Daily Scrum to answer functional questions about the Sprint

Backlog.

D.

Create financial reporting upon the spent hours reported by the Developers.

E.

Update the work plan for the Developers on a daily basis.

Question # 19

Which of the following statements about the Product Backlog are true?

(choose the best two answers)

A.

The Product Backlog is ordered by the Product Owner.

B.

The Product Backlog should be visible to the Scrum Team and stakeholders.

C.

All Product Backlog items must be expressed as user stories.

D.

All Product Backlog items must be identified before the first Sprint begins.

E.

Only the Product Owner can place items on the Product Backlog.

F.

The Product Backlog represents the input of all stakeholders and eliminates any

need for the Developers to speak to stakeholders.

Question # 20

Which of the following statements is true about the Product Vision?

(choose the best answer)

A.

It evolves as the Scrum Team learns more about customers and their needs.

B.

It is the shared responsibility of the Scrum Team to develop and evolve.

C.

It must be completely free from discussions about strategic technology choices.

D.

All of the above.

E.

None of the above.