Spring Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: buysanta

Exact2Pass Menu

BICSI Registered Communications Distribution Designer - RCDD

Last Update 15 hours ago Total Questions : 361

The BICSI Registered Communications Distribution Designer - RCDD content is now fully updated, with all current exam questions added 15 hours ago. Deciding to include RCDD-002 practice exam questions in your study plan goes far beyond basic test preparation.

You'll find that our RCDD-002 exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these RCDD-002 sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any BICSI Registered Communications Distribution Designer - RCDD practice test comfortably within the allotted time.

Question # 61

The maximum vertical rise is the distance over which the cable is vertically self-supporting. This distance is a function of the weight of the cable and the:

A.

Sheath fire rating

B.

Number of strands of fiber in the cable

C.

Type of hangers used in the riser

D.

Type of fire stop used in the riser

E.

Cable maximum tensile rating

Question # 62

The RECOMMENDED balanced twisted-pair cable for building backbone cabling consists of ________ round solid copper conductors with a nominal characteristic of 100 ohm.

A.

20-24 AWG

B.

22-26 AWG

C.

23-24 AWG

D.

24-22 AWG

E.

26-20 AWG

Question # 63

At the end of the second week of a project, the earned value (EV) of work is $8000 USd and the planned value (PV) of work is $7000 USd. What is true about the project?

A.

The project is ahead of schedule.

B.

The project is over budget.

C.

The project is behind schedule.

D.

The project is under budget.

Question # 64

A scope of work should contain all of the following EXCEPT:

A.

Request for purchase

B.

Project schedule

C.

Project objective

D.

Assumptions

E.

Customer needs

Question # 65

All of the following are true about the post construction phase EXCEPT:

A.

The owner is responsible to update the record copy drawings to reflect " as-built " documents.

B.

The contractors are resolving issues identified on the punch lists.

C.

The architect is involved in final acceptance and contract closeout activities.

D.

The construction manager is coordinating removal of construction equipment and job trailers.

Question # 66

The headend has several modulators assigning frequencies for distribution to the CATV network. What distribution device should you use immediately at the headend to distribute the modulator ' s output signals to CATV system?

A.

Splitter

B.

Directional coupler

C.

Combiner

D.

Multiport tap

Question # 67

What is the appropriate impedance of coaxial cable for use with broadband distribution?

A.

50

B.

75

C.

100

D.

150

Question # 68

The F rating for a framed wall/stud wall is ________ hour(s).

A.

One

B.

Two

C.

Three

D.

Four

Question # 69

Which of the following is a nonmechanical firestop system?

A.

Cable transit system

B.

Firestop blocks

C.

Fire rated pathway device

D.

Factory fabricated sleeve system

Question # 70

Cementitious materials are ________ based materials.

A.

Dry powder

B.

Latex

C.

Solvent

D.

Sand

Go to page: