You'll find that our CTAL-TM exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these CTAL-TM sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Certified Tester Advanced Level Test Management (CTAL-TM) v3.0 practice test comfortably within the allotted time.

Question # 61

Which of the Mowing Is commonly used by a test manager to identity risks'

A.

Lines of code in the system under test

B.

Function points within the software

C.

Experience with similar projects

D.

Record/playback test automation tools

Question # 62

Your team has decided that they will build their own test management tool This will allow them to link the requirements and test cases together providing full traceability It will also allow them to create fully customized reporting and color-coded dashboards They have estimated the time required to create the new tool and the cost These fit within the project schedule and budget

What other consideration should be taken before this decision is made?

A.

Relative benefits to your vendors

B.

Maintenance costs

C.

Licensing fees to other parts of the organization

D.

Reduction of manual repetitive testing

Question # 63

At what testing level do the test management activities Include coordinating with end users7

A.

Component testing

B.

Component Integration testing

C.

System testing

D.

Acceptance testing

Question # 64

Your company is installing a third-party enterprise-wide business software package. This is the first time the company has done anything like this.

Which technique would be the best one to use to estimate the testing effort? [3]

A.

Estimated developer effort and lines of code

B.

Industry averages

C.

Review of the installation guide

D.

Past experience with in-house projects

Question # 65

You are a newly appointed Test Manager in an organisation that has no separate test team, no formal testing process and testing is considered to be, at best, ad-hoc in approach. The IT director is keen to introduce improvement across all areas of the organisation, not just testing. This is so that the current level of maturity can be assessed and roadmaps outlined for improving processes in a staged way. He has asked you to recommend a test process improvement model and you have suggested TMMi.

Which ONE of the following is a valid reason for your recommendation? SELECT ONE OPTION

A.

It provides the fastest way to take testing to an optimized state.

B.

It provides bench-marking against industry averages using objective measurements.

C.

It helps address highest priority testing issues with limited formality.

D.

It naturally complements the IT director's process improvement goals for the organisation.

Question # 66

Consider the following metrics:

a Percentage of all product risks identified during initial risk analysis

b. Average time taken by developers to fix defects for each severity level

c. Statement coverage achieved by the component test suite

d. Breakdown of defects detected by test level

How many of the five primary dimensions for test progress monitoring have been addressed by these metrics?

SELECT ONE OPTION

A.

2

B.

4

C.

1

D.

3

Question # 67

The diagram shows a defect workflow in which two states do not have appropriate names.

Which option could correctly provide the missing state names?

A.

State X = Open, State Y = Clarification

B.

State X = Confirmation, State Y = Resolved

C.

State X = Terminated, State Y = Archived

D.

State X = Duplicate, State Y = Postponed

Question # 68

Club 65 to 90 is a holiday club for retired people run by a small company, the IT department consists of 1 Designer, 3 Developers and 1 System Tester Their booking system has been "live" for a number of years and the company has a loyal client base. A variety of automation tools are used for development and testing to improve effectiveness and efficiency.

A new project will introduce a loyalty scheme and both a Business Requirement Specification and a System Design Specification have been produced A Rapid Application Development (RAD) lifecycle model will be used where time is crucial. In the past there have been problems with updates to the existing system, which has affected existing functionality. Testers have not used representative and realistic operational profiles and data, which has led to significant production problems. The following test policy statements have been proposed for the project:

a. Testing must be risk based;

b. A Master Test Plan, confirming to IEEE829, must be produced for each test project;

c. Test procedures must be run by a tester who did not write the procedure;

d. Regression testing should be carried out on all releases;

e. The testers are accountable for all defects found in production;

f. Time must be given to designing test environments so that they are representative of the live environment. Which of the following options identifies the three policy statements that would be MOST beneficial for this project?

A.

a, d and e.

B.

a. b and e.

C.

a. d and f.

D.

b. c and f.