You'll find that our PMI-001 exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these PMI-001 sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Project Management Professional v5 practice test comfortably within the allotted time.

Question # 81

Forecasts, requested changes, recommended corrective actions, and organizational process asset updates are all outputs of which process?

A.

Risk response planning

B.

Risk monitoring and control

C.

Performance reporting

D.

Manage stakeholders

Question # 82

The component of the human resource management plan that includes ways in which team members can obtain certifications that support their ability to benefit the project is known as:

A.

recognition and rewards

B.

compliance

C.

staff acquisition

D.

training needs

Question # 83

Which of the following is a measure of the value of work completed compared to the actual cost or progress made on the project?

A.

Schedule performance index (SPI)

B.

Cost performance index (CPI)

C.

Cost variance (CV)

D.

Planned value (PV)

Question # 84

Which schedule compression technique has phases or activities done in parallel that would normally have been done sequentially?

A.

Crashing

B.

Fast tracking

C.

Leads and lags adjustment

D.

Parallel task development

Question # 85

Which Perform Quality Assurance tool or technique is used to identify a problem, discover the underlying causes that lead to it, and develop preventative actions?

A.

Inspection

B.

Quality audits

C.

Design of experiments

D.

Root cause analysis

Question # 86

Which defines the portion of work included in a contract for items being purchased or acquired?

A.

Procurement management plan

B.

Evaluation criteria

C.

Work breakdown structure

D.

Procurement statement of work

Question # 87

Regression analysis, failure mode and effect analysis (FMEA), fault tree analysis (FTA), and trend analysis are examples of which tool or technique?

A.

Expert judgment

B.

Forecasting methods

C.

Earned value management

D.

Analytical techniques

Question # 88

Which schedule development tool and technique produces a theoretical early start date and late start date?

A.

Critical path method

B.

Variance analysis

C.

Schedule compression

D.

Schedule comparison bar charts

Question # 89

Which tool and technique identifies inefficient and ineffective policies, processes, and procedures?

A.

Scope audits

B.

Scope reviews

C.

Quality audits

D.

Control chart

Question # 90

An input to the Identify Stakeholders process is:

A.

The project management plan.

B.

The stakeholder register.

C.

Procurement documents.

D.

Stakeholder analysis.

Question # 91

In which phase of team building activities do team members begin to work together and adjust their work habits and behavior to support the team?

A.

Performing

B.

Storming

C.

Norming

D.

Forming

Question # 92

Configuration identification, configuration status accounting, and configuration verification and audit are all activities in which process?

A.

Perform Quality Assurance

B.

Direct and Manage Project Work

C.

Monitor and Control Project Work

D.

Perform Integrated Change Control

Question # 93

An input to the Perform Quantitative Risk Analysis process is the:

A.

quality management plan.

B.

project management plan.

C.

communications management plan.

D.

schedule management plan.

Question # 94

Cost baseline is an output of which of the following processes?

A.

Control Costs

B.

Determine Budget

C.

Estimate Costs

D.

Estimate Activity Resources

Question # 95

The approaches, tools, and data sources that will be used to perform risk management on a project are determined by the:

A.

Methodology

B.

Risk category

C.

Risk attitude

D.

Assumption analysis

Question # 96

Plan-do-check-act is also known as:

A.

prevention over inspection.

B.

statistical sampling.

C.

management responsibility,

D.

continuous improvement.

Question # 97

Which of the following processes audits the quality requirements and the results from quality control measures to ensure appropriate quality standards and operational definitions are used?

A.

Perform Quality Control

B.

Quality Metrics

C.

Perform Quality Assurance

D.

Plan Quality

Question # 98

An element of the modern quality management approach used to achieve compatibility with the International Organization for Standardization (ISO) is known as:

A.

Forecasting,

B.

Brainstorming.

C.

Historical databases.

D.

Cost of quality.

Question # 99

What is the name of the statistical method that helps identify which factors may influence specific variables of a product or process under development or in production?

A.

Failure modes and effects analysis

B.

Design of experiments

C.

Quality checklist

D.

Risk analysis

Question # 100

Which process is responsible for monitoring the status of the project and product scope and managing changes to the scope baseline?

A.

Variance Analysis

B.

Define Scope

C.

Verify Scope

D.

Control Scope