Halloween Special Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: buysanta

Exact2Pass Menu

Question # 4

In the middle of a project, a new requirement was added to the scope. The business analyst must determine if any impacts, dependencies, or risks are associated with the addition to the scope.

What task should the business analyst perform in order to identify these impacts?

A.

Manage solution scope.

B.

Manage requirements traceability.

C.

Manage requirements prioritization.

D.

Manage assumptions and constraints.

Full Access
Question # 5

A project team has been assembled to reduce production costs. The business analyst is working with the project team to review and approve requirements. A stakeholder from the assembly line area has an issue with one of the requirements since it is dependent on using existing equipment that is set to be retired within the next six months.

Which of these techniques would the business analyst use to manage issues identified by stakeholders with requirements to ensure that

those issues are resolved?

A.

A Interviews

B.

Process modeling

C.

Estimation

D.

Problem tracking

Full Access
Question # 6

The business analyst has been assigned to a project which delivers functionality for a much larger solution. The project has many requirements but has not received adequate funding. In addition, the stakeholders’ views conflict.

Which tools and techniques should the business analyst use to maximize business value while establishing the requirements baseline?

A.

Weighted matrix, process flow, and organizational chart

B.

Stakeholder register, decision tree, and capability matrix

C.

Traceability matrix, context diagrams, and scope document

D.

Decision trees, weighted matrix, and context diagrams

Full Access
Question # 7

Company A would like to enter into a new market. The business analyst has been assigned to a project for which nobody in Company A has any prior experience. The project manager has asked the business analyst to assist in resource planning.

What should the business analyst recommend to the project manager?

A.

Ask the developer's team manager for more resources.

B.

Review the business case to reconsider the project.

C.

Hire external subject matter experts for the core project team.

D.

Ask the sponsor for more resources.

Full Access
Question # 8

The document that defines the process for managing requirements revisions is the:

A.

project management plan.

B.

change management plan.

C.

communications management plan.

D.

scope management plan.

Full Access
Question # 9

Which tool should be used to improve the communication of product needs with the stakeholders and to improve their understanding?

A.

Requirements management tool that documents requirements and their properties and relationships

B.

Document management system and a relationship matrix that groups all related documents

C.

Modeling tool integrated into a version control feature that ensures that team knowledge is captured

D.

Workflow management tool that documents the flow of information

Full Access
Question # 10

Which of the following is an example of a functional requirement?

A.

The system is able to require passwords.

B.

The system can be accessed from multiple locations.

C.

The system provides an user-friendly interface.

D.

The system can handle 3,000 user requests concurrently.

Full Access
Question # 11

The business analyst is in the process of implementing a solution for a customer. The team is having difficulty confirming if certain requirements have been met.

What could have caused this issue?

A.

The test engineer has not properly communicated requirements to the team.

B.

Not all stakeholders were involved during requirements elicitation.

C.

Acceptance criteria for the requirements were not measurable.

D.

Requirements were not adequately reviewed with the project sponsor.

Full Access
Question # 12

The software developers have delivered a completed solution. The quality assurance team has passed the solution. What should the business analyst do next?

A.

Evaluate the solution against the project charter.

B.

Conduct user acceptance testing.

C.

Evaluate the solution with the sponsor(s).

D.

Conduct performance testing.

Full Access
Question # 13

A company is awarded a contract to design and build a custom product. The contract references a detailed technical specification. What is the best action to take to ensure the design meets customer requirements?

A.

Create a system requirements verification matrix to trace the design to the technical requirements and include verification methods.

B.

Conduct a one-on-one interview with each member of the technical team to ensure that they understand the customer's specification.

C.

Generate a design package for the product and ask the customer to verify that the design meets his or her technical needs.

D.

Develop a test plan to verify that the product meets the performance requirements in the technical specification.

Full Access
Question # 14

Which of the following techniques is used to identify ambiguous or unverifiable requirements?

A.

Fishbone analysis

B.

Resource checklist

C.

Traceability matrix

D.

Team peer review

Full Access
Question # 15

Projects have been managed well and completed on schedule and on budget. However, successful completion of the projects has not improved the company’s performance and profitability.

Which of the following should have been implemented to ensure that the projects would improve the company’s performance and profitability?

A.

review with appropriate stakeholders

B.

A project management plan

C.

A risk plan

D.

A strategies and goals analysis

Full Access
Question # 16

After several meetings with different groups of users, a business analyst has gathered the requirements for a large IT project. Now, the business analyst needs to document those requirements in a way that is clearly understood by the development team and provides

enough information to check if the requirement has been met.

Which of the following would work best in this case?

A.

User stories

B.

Functional specifications

C.

Flow chart

D.

Prototyping

Full Access
Question # 17

Which of the following is a properly written requirement statement?

A.

The pot shall be lightweight and heat up quickly.

B.

The pot shall be usable in the oven or on the stove.

C.

The pot shall be manufactured in the following colors: yellow, red, brown, blue.

D.

The pot shall prominently display the company brand.

Full Access
Question # 18

A business analyst assigned to review test output for a project realizes that an approved requirement has been missed. Which technique could the business analyst have used to ensure that requirements were delivered as stated?

A.

Work breakdown structure

B.

Requirements management plan

C.

Use cases

D.

Traceability matrix

Full Access
Question # 19

A company uses a prioritization range of 1-10, in which 10 represents the highest or best. According to the information from the table, which option should the business analyst recommend?

A.

1

B.

2

C.

3

D.

4

Full Access
Question # 20

A project team has been assembled to streamline accounts payable processes in all divisions of the company. As part of the planning activities, the business analyst is working to identify stakeholders.

Which of the following techniques would the business analyst use to identify stakeholders?

A.

Brainstorming

B.

State diagram

C.

Estimation

D.

Prototyping

Full Access
Question # 21

A stakeholder wants to modify an existing feature. Which of the following would be used to determine the scope of the change on the product?

A.

Project schedule and cost baseline

B.

Requirements traceability matrix

C.

Requirements attributes table

D.

Sequence diagram

Full Access
Question # 22

A business analyst has been assigned to Project Y. After a requirements gathering session, the project manager asks the business analyst to identify which requirements would be considered in scope and out of scope, based on the business need.

What document should the business analyst use to determine the relationship of the requirement to the business need?

A.

Traceability matrix

B.

Requirements management plan

C.

Requirements package

D.

Reliability matrix

Full Access
Question # 23

A project affects the marketing unit and procurement unit. The project manager gives the business analyst an overview of the project for the first time.

What should the business analyst do immediately after the discussion?

A.

Schedule time with the process owners.

B.

Put the information into a project plan.

C.

Develop an issues log.

D.

Assess the risks for the project.

Full Access
Question # 24

The test team is reviewing requirements that were written for Project A. They are having difficulty determining if the test results meet the project needs.

Which project artifact could the test team review to help identify acceptance criteria?

A.

Project scope

B.

Use cases

C.

RACI chart

D.

Delphi outcome

Full Access
Question # 25

Which of the following is a method for requirements change control?

A.

Communication management

B.

Scope analysis

C.

Requirements management

D.

Baselining

Full Access
Question # 26

A business analyst has been assigned to a project team that is redesigning the company's website. The business analyst has been documenting the relationships between requirements and has found requirements that do not trace to a business need.

Which type of requirements are these?

A.

In-scope

B.

Tested

C.

Implemented

D.

Out-of-scope

Full Access
Question # 27

A business analyst has been assigned to a project that will design and build two new bridges and, at the same time, redesign a failing bridge for a local structural engineering company. All three bridges must be constructed and meet all safety requirements before flood season next spring.

How would the business analyst define the scope of this project?

A.

Perform a work breakdown structure.

B.

Perform a feasibility study.

C.

Perform process modelling.

D.

Perform a structured walkthrough.

Full Access
Question # 28

A major stakeholder of a project is surprised to learn that a particular requirement was not implemented during the latest launch.

The business analyst tells the stakeholder that the requirement status was changed to "deferred ”

What could have prevented the stakeholder from being surprised about the status change?

A.

The status should have been communicated to the requirement’s source.

B.

The status should have been reviewed prior to project launch.

C.

The status should have been communicated to all project stakeholders.

D.

The status should have been updated in the traceability matrix.

Full Access
Question # 29

A business analyst has captured all of the requirements from the various stakeholders within the organization and has compiled them into a complete list. After reviewing the list of requirements with the stakeholders, it is determined that the list of requirements is too large and will exceed the allotted budget.

Which tool or technique should the business analyst use with the stakeholders to prioritize the requirements to determine which requirements are approved, deferred, or rejected?

A.

SMART Goals

B.

Moscow Analysis

C.

SWOT Analysis

D.

Timeboxing Analysis

Full Access
Question # 30

Which technique or tool is used to obtain acceptance of the delivered product?

A.

Expert judgment

B.

Facilitated workshops

C.

Inspection

D.

Contextual inquiry

Full Access
Question # 31

Which of the following tools will help facilitate the decision-making process when stakeholders do not agree on the value of an initiative?

A.

PEST analysis

B.

B. Force-field analysis

C.

Feasibility analysis

D.

Gap analysis

Full Access
Question # 32

An insurance company embarks on a project to replace its current enrollment and billing software application, which will no longer be supported by the end of the calendar year. The new enrollment and billing application must be implemented before the current vendor contract ends. The business analyst gathers the initial requirements for the new enrollment and billing application. Based on the large

volume of requirements, the business analyst realizes that the requirements will need to be prioritized.

Which requirements prioritization method should the business analyst use for this project?

A.

Time-boxing

B.

Weighted ranking

C.

MoSCoW

D.

Risk analysis

Full Access
Question # 33

A few months into a project, the business analyst determines that the costs are exceeding the perceived benefits. The business analyst wants to address the possible risks of having to cancel the product.

Which of the following documents should be used?

A.

Stakeholder impact matrix

B.

Business analysis plan

C.

Project charter

D.

Business case

Full Access
Question # 34

A business analyst is leading a project to implement automated order entry software at a local pizza restaurant. The business analyst has very little information about the project: the ordering process takes too long and often ends in incorrect orders.

What step should the business analyst take next?

A.

Schedule a requirements gathering sessions with the manager of the ordering department.

B.

Request information on the current ordering process and compare it with other companies.

C.

Identify testing resources to support the implementation.

D.

Select the software to implement and start working with the technical resources.

Full Access
Question # 35

The project team is working on the requirements specifications for a new product. The team reached a decision on which requirements will be included in the next release. A third of the stakeholders endorse one approach while no other approach achieved more than a quarter of the vote.

Which decision role was used?

A.

Majority

B.

Plurality

C.

Consensus

D.

Unanimity

Full Access
Question # 36

A sponsor requests a new requirement. The business analyst explains that most of the information needed for this requirement does not exist and that the requirement cannot be implemented. The business analyst recommends deferring the requirement until the needed information is available and then adding it to a subsequent project. The sponsor agrees.

What should the business analyst do next?

A.

Bring the subsequent project to the change control board (CCB).

B.

Ask the stakeholders to review the requirement before any other action is taken.

C.

Communicate that the status of this requirement has changed.

D.

Mark the requirement as complete so that it is not forgotten.

Full Access
Question # 37

The sales team of a company has won a time-and-material project. The business analyst discovers that the sales team has underestimated the required budget and schedule.

Which course of action should the business analyst take?

A.

Refrain from working on the project and request that the customer cancel the contract.

B.

Accept the contract, and then notify the customer about the potential for a cost overrun.

C.

Accept the contract, and deliver only the requirements that fit within the budget and schedule.

D.

Develop a requirements baseline document and use it to negotiate the scope in the contract.

Full Access
Question # 38

One of the main purposes for creating a requirements traceability matrix is to:

A.

track how requirements can be connected to the solution.

B.

provide test cases to validate solution deliverables.

C.

document stakeholder approval of project requirements.

D.

track the project solution scope.

Full Access
Question # 39

The business analyst generated a design specification for a new product. What is the best type of formal review to conduct with the customer to establish an approved requirements baseline?

A.

Test readiness review

B.

Production readiness review

C.

System requirements review

D.

Critical design review

Full Access
Question # 40

The technology department identified a defect in the company's software, which leads to an increase in human resource requirements to perform manual transactions as a workaround for tasks that should have been automated. The company begins losing money, so it hires a business analyst to produce a business case that outlines the problem/opportunity, potential options, and a recommendation for how to proceed.

Which of the following analyses must the business analyst perform in order to complete the business case and arrive at a solid

recommendation?

A.

Gap

B.

Risk

C.

Cost-benefit

D.

SWOT

Full Access
Question # 41

An organization is evaluating the possibility of conducting business internationally. Which factors should be investigated at the onset of the initiative?

A.

Deliverables to be produced

B.

Impacts on requirements baseline

C.

External dependencies

D.

Change control processes

Full Access
Question # 42

A business analyst is assigned to a business process re-engineering project. In addition to planning a workshop to elicit requirements, the business analyst wants to send out a survey to gather data to use in a statistical analysis on user satisfaction with the current business process.

Which of the following types of surveys would be most appropriate to create and why?

A.

A closed-ended survey to pose several multiple-choice questions and ask the users if the current business process Is correct

B.

A closed-ended survey using the Likert scale to rank specific areas of the current business process

C.

An open-ended survey to allow users the opportunity to explain their opinions on the current business process

D.

An open-ended survey to collect different opinions on the current business process

Full Access
Question # 43

A company is developing a new risk management system. The company expects the system to evolve in the near future due to changing government regulations.

Which approach will better cope with the requirements’ volatility?

A.

Storyboarding

B.

Multivoting

C.

Phased baselining

D.

Comparative analysis

Full Access
Question # 44

How should a business analyst determine whether a solution satisfies business requirements?

A.

By reviewing the results of user acceptance testing

B.

By evaluating the solution against the project charter

C.

By conducting a brainstorming session with end users

D.

By reviewing the traceability matrix

Full Access
Question # 45

A business analysis team has collected the main business requirements from the major stakeholders of a project. The team wants to be sure that each stakeholder has a clear understanding of the areas of analysis that will be in scope.

Which model should the team employ to ensure the most effective representation of analysis boundary?

A.

Data flow diagram

B.

Context diagram

C.

State diagram

D.

Entity relationship diagram

Full Access
Question # 46

A project team has completed the system use cases along with accompanying screen mockups. The business analyst schedules a review meeting with the client team to walk through the artifacts.

What is the purpose of this meeting?

A.

To verify that the system is aligned with the quality requirements

B.

To verify that the documents are aligned with the transition requirements

C.

To validate that the system is aligned with the stakeholder requirements

D.

To validate that the documents are aligned with the solution requirements

Full Access
Question # 47

When managing a product backlog, which statement best describes how to determine the value of backlog items?

A.

The stakeholders provide recommendations with the product owner having the final say.

B.

The stakeholders follow the value-ranking criteria.

C.

The stakeholders do not typically play a major role.

D.

The stakeholders provide input about backlog value when the item is first identified.

Full Access
Question # 48

In the first few weeks after a large implementation of a new web-based application, a critical report failed. Further Investigation determined that a worker had been using a field that was not supposed to be used. This issue was not identified in testing.

Which technique could have prevented this problem from occurring?

A.

Prototyping

B.

Diagrams

C.

Use cases

D.

Document analysis

Full Access
Question # 49

During user acceptance testing, a defect is logged by a user from a department that did not participate in the requirements analysis. To avoid this situation and minimize impact on the project, the user should have been:

A.

interviewed to understand how the user's work would be impacted.

B.

involved in the development and sign-off of the business requirements.

C.

identified as a stakeholder as part of the stakeholder analysis.

D.

given the opportunity to review the user acceptance test scripts.

Full Access
Question # 50

A company is pleased with its delivered solution and reports that it has heard only minimal complaints for the first three months of use.

How can the business analyst determine how well the solution meets the business case?

A.

Conduct a user survey.

B.

Ask the sponsor for feedback.

C.

Survey the project.

D.

Compare the results of day-in-the-life (DITL) testing and integration testing.

Full Access
Question # 51

The business analyst is seriously concerned about the possibility of differing interpretations of data items mentioned in the requirements documents. Which course of action should the business analyst take to minimize the risk of misunderstanding?

A.

Plan a peer review of the requirements specification.

B.

Ask the development teams for a formal acceptance of the requirements specification.

C.

Write a data dictionary that accompanies the requirements specification.

D.

Hold a workshop with the development teams to explain the details of the requirements specification.

Full Access
Question # 52

A business analyst is assigned to the lead analyst role for a project. This project is one of the largest in the history of the company and includes several components and complex interfaces. The system in development will be used by a wide variety of stakeholders.

Which tool should the business analyst use to trace the large number of requirements that will be generated by this project?

A.

Data dictionary

B.

Configuration management system

C.

Sequence diagram

D.

D. Process model

Full Access
Question # 53

A company has just finished the development work for a new software sales tracking application and is in the process of validating that the new application meets all of the acceptance criteria defined for the business requirements. During the validation

process, a stakeholder discovers that the application does not provide the selection criteria needed to produce the sales volume

reporting required by the company's financial department. The business analyst for the project determines that the selection criteria

needed was not specified in the system requirements or design specifications.

Which of the following tools and/or techniques might be used by the business analyst to determine how the selection criteria requirement

was missed?

A.

Root cause analysis, fishbone diagram, and/or the Five Whys

B.

Root cause analysis, problem tracking, and/or benchmarking

C.

Scope modeling, Ishikawa diagram, and/or the Five Whys

D.

Cause and effect diagram, brainstorming, and/or the Five Whys

Full Access
Question # 54

A business analyst has started a project for a system enhancement. In order to determine how the requirements will be approved, the business analyst schedules a meeting with the stakeholders to discuss the proposed approval process.

Which measure of effective decision making allows the business analyst to finalize the process for requirement approval?

A.

The requirements verification process is documented.

B.

The requirements elicitation process is documented.

C.

The requirements validation process is documented.

D.

The requirements approval process is documented.

Full Access
Question # 55

A new project is in the planning phase. What should the business analyst consider with regard to planning the requirements change process?

A.

How requirement changes will impact the requirements baseline

B.

How requirement changes will be implemented

C.

How requirement changes will impact the validation plan

D.

How requirement changes will be communicated

Full Access
Question # 56

A company has launched a new online sales application and engaged a focus group to test how quickly the customer could place an order. The focus group also provided feedback on their satisfaction.

Which metrics tool should the business analyst use to record the results?

A.

Business completion

B.

Sales and marketing

C.

Customer

D.

Focus group

Full Access
Question # 57

The requirements traceability matrix should primarily be used to:

A.

identify the risks associated with dependent requirements.

B.

define a convention to map the requirements to their sources.

C.

ensure that all requirements have been met.

D.

address the responsibility owner for each requirement.

Full Access
Question # 58

Requirements for a project have already been approved and finalized when a stakeholder approaches the project team with a change to one of their requirements. Which method of document control should the business analyst use to document changes in requirement(s)

versioning?

A.

Statement of work

B.

Project plan

C.

Problem or opportunity statement

D.

Traceability matrix

Full Access
Question # 59

After reviewing a business case, project goals, and objectives, a business analyst determines that the organization prefers taking an exploratory approach to finding the solution that best meets the business need. Which approach best aligns with the business need for this organization?

A.

Plan-driven approach

B.

Waterfall approach

C.

Analytical approach

D.

Change-driven approach

Full Access
Question # 60

Which of the following is the best approach to enable developers and product owners to be in constant communication so that changes or issues that occur during development are exposed and discussed as they develop?

A.

Iterative

B.

Waterfall

C.

Linear

D.

Agile

Full Access