You'll find that our PMI-002 exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these PMI-002 sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Certified Associate in Project Management (CAPM) Certification practice test comfortably within the allotted time.

Question # 4

Under what circumstances is it better for a contractor to subcontract?

A.

The subcontractor possesses special technical and engineering skills that the contractor does not have.

B.

The work to be subcontracted represents almost all of the overall work effort.

C.

The subcontractor can perform the work at a lower cost than the contractor.

D.

Both A and c

Question # 5

You are working with an organization and you found that one stakeholder not disclosing all of the costs involved with an upcoming project. Rather, this CAPM is constructing a WBS that does not include all the tasks necessary to get the project done. What you should do?

A.

Talk to the CAPM about the WBS to see if you can rework it to reflect actual costs of the project

B.

Confront the other project manager immediately

C.

Mail t0 PMI headquarters

D.

Ignore it

Question # 6

Administrative closure is the process that ________.

A.

Closes all activities pertaining to a specific project

B.

Collects user acceptance of the project product or service

C.

Includes all the activities needed to validate the project products and services

D.

Al1 of the above

Question # 7

You are the project manager of a project. If there are approved changes to the original scope, what you do with the old original scope?

A.

Save the old versions

B.

No need to save old version

C.

Scrap the old version

D.

Old version is not required

Question # 8

Market conditions are a part of ________.

A.

Enterprise environmental factors

B.

Project management concerns

C.

Organizational process assets

D.

Cost factor

Question # 9

In which phase project manager is assigned to a project?

A.

During the initiation stage

B.

During the planning stage

C.

After approval of budget

D.

After the project is proven feasible

Question # 10

Which of the following techniques accounts for path convergence and generally estimates project durations more accurately?

A.

CPM

B.

PERT

C.

Schedule simulation

D.

Path convergence method

Question # 11

18 You are the project manager of a software company. As software development can be very chaotic, your company has decided to follow a more rigorous approach to software development. Specifically your company has chosen to adopt the extreme programming XP methodology for your current software project. The XP methodology is highly iterative, and produces numerous deliverables include UML diagrams, architecture diagrams, prototypes and test-cases. Assume you are in the Sequence Activities phase of the project. Which of the following sequencing methods should you use to identify the logical relationships between tasks, so that the activities can be sequenced correctly?

A.

ADM

B.

PDM

C.

GEPT

D.

A0A

Question # 12

A project schedule can be presented in various formats. All of the following are valid formats of the project schedule EXCEPT:

A.

Activity-on-node diagram

B.

Logic bar chart

C.

Time-scaled schedule network diagram

D.

Flow charts

Question # 13

The quality management plan includes all of the following EXCEPT quality:

A.

Planning

B.

Definitions

C.

Assurance

D.

Control

Question # 14

Activity duration estimates include all of the following EXCEPT for:

A.

Project team knowledge.

B.

Time studies.

C.

Information from previous experience.

D.

Commercial duration databases.

Question # 15

The overall intentions and direction of an organization with regard to quality as formally expressed by top management is a ____________.

A.

Quality Plan

B.

Quality Statement

C.

Quality Policy

D.

TQM