You'll find that our PRINCE2-Agile-Foundation exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these PRINCE2-Agile-Foundation sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any PRINCE2 Agile Foundation (Version 2) Exam practice test comfortably within the allotted time.

Question # 31

Which statement explains the target ‘be on time and hit deadlines’ for flexible delivery?

A.

It reduces testing in order to meet deadlines

B.

It sets the project baseline at the correct level

C.

It enables team dynamics to remain the same

D.

It improves the supplier ' s reputation with the customer

Question # 32

Which statement is CORRECT with respect to the management of risk using PRINCE2 Agile?

A.

It should always be appropriate to the needs of the project

B.

It should always be addressed during the daily stand-ups

C.

It should always be carried out formally

D.

It should always be carried out informally

Question # 33

Which practice has the purpose of controlling uncertainties that would affect the project’s objectives?

A.

Plans

B.

Issues

C.

Quality

D.

Risk

Question # 34

Which statement describes how the PRINCE2 ‘starting up a project’ process can be applied in an agile environment?

A.

PRINCE2 is predictive, but not emergent

B.

PRINCE2 is predictive and can be emergent

C.

PRINCE2 requires a lengthy start to a project

D.

PRINCE2 requires a disruptive start to a project

Question # 35

In which workshop does planning for the next stage occur?

A.

Team planning workshop

B.

Release planning workshop

C.

Team retrospective workshop

D.

Progress review workshop

Question # 36

Which is a purpose of the plans theme?

A.

To identify any deviations from the project’s objectives

B.

To control any approved changes to the baseline

C.

To monitor actual achievements against those planned

D.

To communicate the approach for delivering products

Question # 37

Which statement BEST describes the PRINCE2 Agile guidance for change?

A.

The delivery team should be authorized to make changes at the detailed level

B.

The delivery team should quickly approve changes to the project baseline

C.

The executive should manage changes dynamically at the detailed level

D.

The executive should approve delivery level changes to harness the benefits of positive change

Question # 38

In which process is a workshop conducted to agree the Definition of Ready (DoR) and Definition of Done (DoD)?

A.

Initiating a project

B.

Directing a project

C.

Controlling a stage

D.

Managing product delivery

Question # 39

What is the definition of a timebox?

A.

A tool to write a requirement in the form of who, what and why

B.

A regular event that looks at how processes can be improved

C.

A description of the rate of progress a team is making

D.

A period where work is carried out to achieve a goal

Question # 40

Which statement about the waterfall methodology definition is CORRECT?

A.

It prevents earlier phases of development being revisited

B.

It uses an iterative and incremental approach

C.

It focuses on responding to changing requirements

D.

It delivers products more frequently in shorter phases