You'll find that our PSPO-I exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these PSPO-I sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Professional Scrum Product Owner (PSPO I) Exam practice test comfortably within the allotted time.

Question # 11

User documentation is part of your Definition of Done. However, there are not enough technical

writers for all teams. Your Scrum Team does not have a technical writer. What should the

Scrum Team do?

(choose the best answer)

A.

The Developers on the Scrum Team should write the user documentation.

B.

Wait until you have a technical writer on your Scrum Team to take care of this.

C.

Form a separate team of technical writers that will work on an on-demand basis for

the various Product Owners. Work order will be first in, first out.

D.

Let the user documentation remain undone and accumulate until after the last

development Sprint. It will then be done by any available technical writers.

Question # 12

You have just been hired by a company new to Scrum. Your management has assigned you to be the Scrum Master of six new Scrum Teams. These teams will build one product. Select two conditions you should strive for in this scenario.

(choose the best two answers)

A.

Each Scrum Team should have a separate Product Backlog.

B.

There should be only one Product Owner.

C.

The product has one Product Backlog.

D.

There should be six Product Owners, one for each Scrum Team.

E.

There should be six Product Owners, reporting to a Chief Product Owner.

Question # 13

True or False: The Product Owner makes sure the Developers select enough from the Product

Backlog for a Sprint to satisfy the stakeholders.

A.

True

B.

False

Question # 14

Who owns the Sprint Backlog?

(choose the best answer)

A.

The Scrum Master.

B.

The Scrum Team.

C.

The Product Owner.

D.

The Developers.

Question # 15

Why do the Developers need a Sprint Goal?

(choose the best answer)

A.

A Sprint Goal only gives purpose to Sprint O.

B.

Sprint Goals are not valuable. Everything is known from the Product Backlog.

C.

The Developers are more focused with a common yet specific goal.

D.

A Sprint Goal ensures that all of the Product Backlog items selected for the Sprint are implemented.

Question # 16

True or False: When there are multiple teams working on one product, each Scrum Team should have a separate Product Owner.

A.

True

B.

False

Question # 17

During a Sprint Retrospective, the Developers propose moving the Daily Scrum to only occur

on Tuesdays and Thursdays. Which two are the most appropriate responses for the Scrum

Master to recommend?

(choose the best two answers)

A.

Have the Developers vote.

B.

Acknowledge and support the self-managing team's decision.

C.

Coach the team on why the Daily Scrum is important as an opportunity to update

the plan.

D.

Consider the request and decide on which days the Daily Scrum should occur.

E.

Learn why the Developers want this and work with them to improve the outcome

of the Daily Scrum.

Question # 18

Every Scrum Team should have:

(choose the best answer)

A.

One Lead Developer and no more than 8 other members.

B.

The competencies and skills needed to deliver an Increment in a Sprint.

C.

At least one representative from each major department, such as, Quality Assurance,

Development, and Marketing.

Question # 19

Which two ways of creating Scrum Teams are consistent with Scrum's values?

(choose the best two answers)

A.

Managers personally re-assign current subordinates to new teams.

B.

The Chief Product Owner determines the new team structures and assignments.

C.

Managers collaborate to assign individuals to specific teams.

D.

Existing teams propose how they would like to go about organizing into the new

structure.

E.

Bring all the people together and let them organize into Scrum Teams.

Question # 20

When might a Sprint be cancelled?

(choose the best answer)

A.

When the Developers determine the product plan is infeasible.

B.

When it becomes clear that not everything will be finished by the end of the Sprint.

C.

When the sales department has an important new opportunity.

D.

When the Sprint Goal becomes obsolete.