You'll find that our PSPO-I exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these PSPO-I sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Professional Scrum Product Owner (PSPO I) Exam practice test comfortably within the allotted time.

Question # 21

Why would you expect a Product Owner to care that the Scrum Team adheres to its Definition of Done?

(choose the best two answers)

A.

The Product Owner should not concern themselves with meeting the Definitionof Done, it is the Developer ' s responsibility.

B.

To be able to punish the team when they do not meet their velocity goal for the Sprint.

C.

To forecast the team ' s productivity over time.

D.

The Definition of Done can affect the product ' s total cost of ownership.

E.

To have complete transparency into what has been done at the end of eachSprint.

Question # 22

You are the Scrum Master for four Scrum Teams working from the same Product Backlog

Several of the Developers come to you complaining that work identified for the upcoming two

Sprints will require full-time commitment from a specialist who is external to the teams.

What should the Scrum Master consider in this situation?

(choose the best two answers)

A.

The need to have enough work to keep all Developers busy.

B.

The benefit of Developers figuring out a solution for themselves.

C.

The desire to maintain a stable velocity.

D.

The ability of the Scrum Teams to produce integrated Increments.

Question # 23

Scrum requires that the Product Owner must use which of the following techniques?

(Choose the best answer)

A.

Feature burn-up.

B.

There is no required technique.

C.

Critical Path Analysis.

D.

Burndown chart.

Question # 24

The timebox for a Daily Scrum is?

(choose the best answer)

A.

4 hours.

B.

The same time of day every day.

C.

Two minutes per person.

D.

15 minutes.

Question # 25

True or False: When there are multiple teams working on one product, each Scrum Team should have a separate Product Owner.

A.

True

B.

False

Question # 26

If Product Backlog refinement is needed, when is the ideal time for refinement to take place and

who should participate?

(choose the best two answers)

A.

The Scrum Team during the current Sprint, if they have been unable duringpreceding Sprints to define Product Backlog items with enough precision tobegin work.

B.

Business analysts in the organization should do this work for the Scrum Team 1- 2 Sprints ahead of the development Sprints.

C.

The Product Owner must do this as essential work in Sprint O.

D.

The Product Owner takes the time between the end of one Sprint and the startof the next Sprint to complete refinement.

E.

The Scrum Team on an ongoing basis, defining Product Backlog items intosmaller more precise items that are ready for selection.

Question # 27

Who determines when it is appropriate to update the Sprint Backlog during a Sprint?

(choose the best answer)

A.

The Project Manager.

B.

The Scrum Team.

C.

The Developers.

D.

The Product Owner.

Question # 28

When should the Product Owner update the project plan?

(choose the best answer)

A.

Before the Sprint Planning to know how much work will have to be done in the Sprint.

B.

The Product Backlog is the plan in Scrum. It is updated as new information and insights emerge.

C.

After the Daily Scrum to ensure an accurate daily overview of project progress.

D.

The project plan must be updated prior to the Sprint Retrospective.

Question # 29

True or False: The Product Owner must write all of the Product Backlog items (e.g., user stories, requirements, etc.) on the Product Backlog before handing them over to the Scrum Team.

A.

True

B.

False

Question # 30

When can Developers cancel a Sprint?

(choose the best answer)

A.

When functional expectations are not well understood.

B.

When the selected Product Backlog items for the Sprint become unachievable.

C.

They cannot. Only Product Owners can cancel Sprints.

D.

When the Product Owner is absent too often.

E.

When a technical dependency cannot be resolved.