You'll find that our SAFe-RTE exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these SAFe-RTE sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any SAFe Release Train Engineer (RTE 6.0) practice test comfortably within the allotted time.

Question # 21

What might an RTE do to embrace relentless improvement and a growth mindset as an individual?

A.

Establish personal KPIs to be able to quantify progress

B.

Identify personal challenges and create personal actions to be taken

C.

Use personal gemba to find useful improvements

D.

Frequently execute the SAFe individual self-assessment

Question # 22

How can a Release Train Engineer support decentralized decision making?

A.

Update team Program Increment (PI) Objectives when shipping a time critical re-lease

B.

Empower knowledge workers to manage their dependencies with other teams

C.

Evaluate the strategy for the Value Stream

D.

Change the cadence of the Agile Release Train

Question # 23

What is one method for developing a sufficient Architectural Runway for the ART?

A.

Create alignment with the System Architect and Product Management that the first PI is all about Enablers to plan for creating business value in the second PI

B.

Ask the Business Owner which Enablers have high business value

C.

Ask the teams to commit only to Enablers as their PI Objectives during the PI Planning and address Features as uncommitted objectives for the first PI

D.

Work with Product Management and System Architects to identify future Features and determine the Enablers to achieve them

Question # 24

Which two practices are most important for the Agile Release Train to best support Re-lease on Demand? (Choose two.)

A.

Aligning around organizational value streams

B.

Centralized risk management

C.

Decouple deployment from release

D.

Change board community of practice

E.

Continuous Integration

Question # 25

Which SAFe tool might the RTE use to identify areas for an ART to improve how its Con-tinuous Delivery Pipeline (CDP) functions?

A.

Agile Product Delivery core competency assessment

B.

Facilitate a CDP sync every iteration

C.

Conduct empathy interviews with system architects/engineers

D.

Architectural runway program backlog enablers

Question # 26

What is ultimately intended to be supported by the use of a Program board?

A.

Problem solving

B.

Program predictability

C.

Feature delivery

D.

Dependency review

Question # 27

What are the three measurement domains supporting Business Agility?

A.

Outcomes, Competency, and Flow

B.

PI Objectives, ART predictability measure, and KPIs

C.

ART predictability measure, SAFe outcomes, and Competency

D.

Key Performance Indicators (KPIs), PI Objectives, and Flow

Question # 28

The RTE collaborates with which other two roles to help focus the ART on delivering value and

operational excellence?

A.

Enterprise Architect and Solution Management

B.

Product Management and System Architect

C.

Solution Architect and Enterprise Architect

D.

Solution Management and Solution Architect

Question # 29

Why do teams have an Iteration retrospective?

A.

To identify acceptance criteria

B.

To adjust and identify ways to improve

C.

To evaluate Metrics

D.

To iterate on Stories

Question # 30

During PI Planning, the Release Train Engineer (RTE) sees the team ' s excitement decline as Product

Management changes priorities, including the top ten Features in the ART Backlog. In addition,

Product Management is asking for new estimates, timelines, and scope changes. What is the likely

reason for this behavior?

A.

People are over-controlled and under-utilized

B.

Cadence and synchronization are not in alignment

C.

Management stakeholders are not involved in changing the system

D.

Lack of training and preparation for PI Planning