You'll find that our SAFe-RTE exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these SAFe-RTE sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any SAFe Release Train Engineer (RTE 6.0) practice test comfortably within the allotted time.

Question # 41

Which two actions can be taken immediately during the management review and prob-lem-solving meeting? (Choose two.)

A.

Change the business priorities

B.

Recognize the team with the highest velocity

C.

Combine teams to increase velocity

D.

Change the scope

E.

Hire new people

Question # 42

Which statement is true about estimating Features using Story points?

A.

More than one team may be involved in the estimation

B.

T-shirt sizing is the best way to estimate features

C.

Feature estimation is performed solely by Product Managers

Question # 43

Which tool can the Release Train Engineer use to visualize the flow of value?

A.

Weighted shorted job first

B.

Team burn-down charts

C.

Velocity trend charts

D.

Kanban systems

Question # 44

Which statement is true about using a Program Kanban system

A.

All work is visualized, progress is continually tracked

B.

WIP limits are used to provide any needed buffers

C.

Work is pushed through the Kanban to ensure train capacity is utilized

D.

The board tracks features, dependencies and milestones

Question # 45

How are the 5 Whys used?

A.

To coach a team through powerful questions

B.

To brainstorm ideas

C.

To define acceptance criteria for a Story

D.

To identify a root cause(s) of a problem

Question # 46

In systems thinking, value of a system passes through its what?

A.

Integrations

B.

Interactions

C.

Interdependencies

D.

Interconnections

Question # 47

What is an anti-pattern for a Release Train Engineer facilitating a scrum of scrums meet-ing?

A.

Run the meeting in front of the program board

B.

Facilitate the meeting using a focused and visible agenda and timebox

C.

Address the most important questions for Program Increment (PI) execution

D.

Review individual team performance

Question # 48

When does the Plan-Do-Check-Adjust cycle occur in scrum?

A.

As part of the lteration retrospective

B.

In the daily stand-up

C.

At the lteration review

D.

A cross all scrum events

Question # 49

Which of the following roles should help facilitate an ART Sync?

A.

Business Owner

B.

Epic Owner

C.

Product Owner (PO)

D.

Product Management

Question # 50

Which two activities take place during Team Breakout #1 on the first day of Program In-crement (PI) Planning? (Choose two.)

A.

Risks on the teams ' planning boards are resolved by the Release Train Engineer

B.

Teams use color-coding for their backlog items as a reminder that they are re-quired to have all backlog item types on their planning boards

C.

Draft objectives and uncommitted objectives are written

D.

All teams ' planning boards are visible and use the same color-coding

E.

Draft objectives are written but do not include exploration Enablers