You'll find that our SAFe-SPC exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these SAFe-SPC sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any SAFe Practice Consultant SPC (6.0) practice test comfortably within the allotted time.

Question # 41

Who typically facilitates the ART Sync meeting?

A.

Agile coach

B.

Senior Scrum Master

C.

Development manager or QA manager

D.

Release Train Engineer

E.

Value Stream Engineer

Question # 42

What description best represents Capabilities as defined in SAFe?

A.

Capabilities are simply a level of abstraction above Epics, exhibiting largely the same characteristics and practices.

B.

Capability is a different name for Features, one that is preferred by some organizations.

C.

Capabilities are simply a different kind of Epic, exhibiting largely the same characteristics and practices.

D.

Capabilities are simply a level of abstraction above Features, exhibiting largely the same characteristics and practices.

Question # 43

What is Cost of Delay?

A.

Cost incurred when system integration appears too late in the PI.

B.

Opportunity cost and deferred revenue.

C.

Penalty for nonperformance.

D.

Cost of not addressing risk early on.

Question # 44

WSJF is recommended for prioritizing the Team Backlog.

A.

True

B.

False

Question # 45

(Select 3) What are the primary reasons to limit WIP?

A.

Reduce multiplexing

B.

Decrease wait times

C.

Expand context switching

D.

Make it easier to visualize the important work

E.

Increase throughput

Question # 46

Vikas is a new Solution Architect and is trying to understand the Solution Context. What is the most important factor for him to consider?

A.

The acceptance criteria for the Capabilities.

B.

Job sequencing for the Epics in the Value Stream Backlog.

C.

The Economic Framework for the Value Stream.

D.

The environment in which the Solution is deployed.

Question # 47

What role would a traditional program manager most likely take on in SAFe?

A.

Release Train Engineer or Value Stream Engineer.

B.

Scrum Master

C.

Business Owner

D.

Product Manager

Question # 48

(Select 2) Why is Architectural Runway important?

A.

It supports a stable velocity.

B.

It provides the documentation on which Features and Capabilities are built.

C.

It iteratively evolves the architecture to meet changing needs.

D.

It allows for nontechnical changes

Question # 49

SAFe uses Story points for estimating the size of Stories, Features, Capabilities, and Epics.

A.

True

B.

False

Question # 50

(Select 3) Which behaviors are typically associated with Lean-Agile Leaders?

A.

Establish clear objectives for managing.

B.

Develop Solutions.

C.

Protect subordinates from interference by outside stakeholders.

D.

Support decentralized decision-making.

E.

Emphasize lifelong learning.