You'll find that our AgilePM-Practitioner exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these AgilePM-Practitioner sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Agile Project Management (AgilePM) Practitioner Exam practice test comfortably within the allotted time.

Question # 21

The Business Ambassador assigned to the project is only available 2 days a

week. The Project Manager has stated that the Investigation stage for each

Timebox should, where possible, be planned around the availability of the

Business Ambassador.

Is this an appropriate application of the DSDM lifecycle?

A.

Yes, because this is where any final quality control checks should be

carried out to ensure all products meet the business need.

B.

Yes, because the Investigation stage of a Timebox requires intense

engagement with the Business Ambassador.

C.

No, because it is the Refinement stage of a Timebox that requires intense

engagement with the Business Ambassador.

D.

No, because Timeboxes are only used during Evolutionary Development

and at this point the Business Ambassador is NOT required.

Question # 22

Which 2 actions should the Business Visionary take to implement the new

Must Have requirement?

A.

Send a company-wide communication to explain the implications of the

business change to all interested parties.

B.

Assess the impact of the new Must Have requirement on the original

Business Case.

C.

Source and hire a web developer with experience in developing online

financial transaction functionality.

D.

Ensure the marketing and sales teams are working together to deliver the

most effective outcome.

E.

Consolidate and circulate an agenda for the workshop.

Question # 23

Answer the following questions about the DSDM Lifecycle.

Decide if each observation is an appropriate application of Agile Project Management for

this project and select the option that supports your decision.

When the project was in the Feasibility phase it was initially proposed by the Finance

Manager that it was a fixed price for a fixed specification ' project. The Project Manager

has decided that the best way to tackle it would be to leave the development of the least

valuable features of the product until last.

Is this an appropriate application of the DSDM lifecycle?

A.

Yes, because the later parts of the project should reflect the least valuable features

of the product being built.

B.

Yes, because in a DSDM project there is no detailed specification upfront.

C.

No, because the Solution Development Team should decide which features are left

until last.

D.

No, because the most valuable features of the project should be delivered last.

Question # 24

Answer the following questions about the contents of the DSDM

products.

Each of the following questions includes true statements about the project

but only two statements are appropriate entries for the DSDM product

identified.

Remember to limit your answers to the number of selections requested in

each question.

Which 2 statements represent appropriate entries for the Business Case?

A.

A list of high-level functional and non-functional requirements that the

project should meet written as User Stories.

B.

Coffee shops that sell Fairtrade products and alcohol from local breweries

out perform other coffee shops in the market.

C.

The Sales Manager has been asked to produce a report within the next

two days showing the number of generic insurance policies sold to coffee

shops over the past three years.

D.

The Sales Manager has calculated that the new coffee shop insurance

product will increase revenues by 10% each week.

E.

Market research shows that the number of coffee shop patrons taking

legal action against retailers has increased by 200% over the past two

years.

Question # 25

Which 2 statements represent appropriate entries for the Development

Approach Definition?

A.

The Sales Manager will introduce an awards or bonus scheme, designed

to create competition between the sales assistants.

B.

Once deployed, the number of policies sold through traditional telephone

sales will be compared with the number of sales processed online

through the website.

C.

An easy to use web development tool called ' WebMatrix ' is to be used to

develop and maintain the website extension.

D.

The Finance Director has requested a detailed report be produced after

12 weeks, showing costs to date and forecast cost to complete.

E.

Accessibility and performance of the new online quotation area is to be

tested using a tool called Sitebeam.

Question # 26

Xan Insurance Company operates from one location - a large, open-plan

office in the centre of a city. Those employees that will be working within the

Solution Development Team are all based in this office but work at different

ends of the office in separate departments.

What action should the Project Manager suggest to ensure the most effective

collaboration of the Solution Development Team?

A.

Create an email group for the Solution Development Team to collaborate

on ideas.

B.

Set up a telephone or video conferencing facility so that all members of

the team can collaborate effectively.

C.

Relocate these employees to a new project area, with a number of desks

where the Solution Development Team can sit together.

D.

No action required as these employees are located in the same office.

Question # 27

Answer the following questions about actions to be taken by different

roles.

The Business Sponsor has decided that the new coffee shop insurance

product website pages will include the financial transaction functionality to

support the end-to-end sales process. The Business Sponsor views this as a

valuable sales tool, enabling customers to pay for insurance policies online. If

successful, this new financial transaction functionality is to be made available

across all other insurance products. This is a new Must Have requirement.

All parties are to be invited to a workshop to discuss the additional work

required to deliver the required solution including the new Must Have

requirement. The areas to be discussed include specialist skills required and

possible legal, financial and technical standards to be adhered to.

Remember to limit your answers to the number of selections requested in

each question.

Which 2 actions should the Business Sponsor take to implement the new Must

Have requirement?

A.

Check for any documented standards which need to be applied to the

development of online financial transaction functionality.

B.

Check the viability of the project, following the inclusion of the new Must

Have requirement.

C.

Source and hire a web developer with experience in developing online

financial transaction functionality.

D.

Send a company-wide communication to explain the implications of the

business change to all interested parties.

E.

Assess the impact of the new Must Have requirement on the original

Business Case.

Question # 28

The Web Content Manager has provided the Web Developer with a mock up

of the ' Contact Us ' page, to be created for the new coffee bar insurance

product. When producing the code, the Web Developer has created a button

that reads ' Delete ' instead of ' Cancel ' .

What action should the Web Content Manager take?

A.

Prepare a defence for when the problem is identified, ensuring the

responsibility is with the Web Developer.

B.

Hide the problem and hope that this detail can be changed at a later date.

C.

Raise an issue to the Project Manager when the solution is deployed.

D.

Discuss the issue with the Web Developer and decide what action is

required to change this detail.

Question # 29

Which 2 actions should the Workshop Facilitator take to implement the new

Must Have requirement?

A.

Add the tasks required to develop the new financial transaction

functionality to the Delivery Plan.

B.

Consolidate and circulate an agenda for the workshop.

C.

Send a company-wide communication to explain the implications of the

business change to all interested parties.

D.

Assess the impact of the additional development costs on the original

Business Case.

E.

Encourage all parties to contribute, irrespective of their views.

Question # 30

Once the change of priority has been approved, who is then responsible for including the requirement for a secondary exit from the upstairs of the building to the Timebox

Plan for Timebox B?

A.

Marketing Director, in the role of Business Visionary.

B.

Team Leader.

C.

Project Manager and Architect, in the role of Technical Co-ordinator.

D.

Architecture Angels ' Senior Management Team.