Pre-Summer Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: buysanta

Exact2Pass Menu

Agile Project Management (AgilePM) Practitioner Exam

Last Update 8 hours ago Total Questions : 184

The Agile Project Management (AgilePM) Practitioner Exam content is now fully updated, with all current exam questions added 8 hours ago. Deciding to include AgilePM-Practitioner practice exam questions in your study plan goes far beyond basic test preparation.

You'll find that our AgilePM-Practitioner exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these AgilePM-Practitioner sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Agile Project Management (AgilePM) Practitioner Exam practice test comfortably within the allotted time.

Question # 31

Using the project timeline given in the Project Scenario, answer the following question about application of Timeboxing on the Hoy Hall project.

Lines 1 to 5 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies.

Each option can be used once, more than once or not at all.

Assertion :

1. All internal works to be assigned to Timber Tigers throughout the project should be consolidated into one Structured Timebox.

BECAUSE

The Investigation step within each Structured Timebox requires everyone working within the team to jointly agree how the requirements of the Timebox will be met.

2. Acceptance criteria for the front rooms to be developed in Timebox A should be described in detail and agreed during the Timebox Kick-Off

BECAUSE

The aim of the Investigation step within each Timebox is to complete as much of

the development work as possible.

3. It is appropriate that both the Evolutionary Development phase and Deployment phase are shown in the first Project Increment.

BECAUSE

Each Timebox should comprise an Evolutionary Development phase and

Deployment phase.

4. It is appropriate that the outputs of Timebox C are scheduled for deployment at the end of the first Project Increment.

BECAUSE

A typical Timebox Plan should provide a schedule of high-level activities for the

imminent Project Increment.

5. It is appropriate that Earth Excavations create a detailed plan of activities they will complete during Timebox C.

Reason

BECAUSE

The Solution Development Team is responsible for planning the detail of all the

work of each Timebox.

Question # 32

How should the lack of provision of a fire escape from the upstairs of the building in Timebox B initially be dealt with?

A.

The Solution Development Team should revise the Timebox Plans for Timeboxes B and C.

B.

The Solution Development Team should commence understanding and delivering the new requirement.

C.

The Architect, in the role of Technical Co-ordinator, should escalate the issue to Architecture Angels ' Senior Management Team.

D.

The Project Manager should escalate the issue to the Marketing Director, who is in the role of Business Visionary.

Question # 33

During Timebox B, the ' Hoy for Hoy Hall ' Action Group disagreed about the planned outcome of the Timebox. The Project Manager organised a Facilitated Workshop to re-

engage this group and explore discrepancies in understanding.

Is this an appropriate application of Agile Project Management for this project?

A.

Yes, because Facilitated Workshops provide a forum for each member of the team to present a short progress report.

B.

Yes, because discussing requirements in the presence of other stakeholders increases the whole group ' s awareness.

C.

No, because the Project Manager should have escalated this disagreement as an issue before any action was taken.

D.

No, because the local Action Group should have attended the Daily Stand-up meetings.

Question # 34

Column 1 is a list of actions taken within the project. For each action in Column 1, select from Column 2 the iterative development activity that the action represents. Each selection from Column 2 can be used once, more than once or not at all.

Column 1:

1. The Solution Development Team cleared and prepared the area, ready for the bar infrastructure to be installed.

2. The Gardener decided the order in which the flowers would be planted in the borders and jotted it down in a notebook.

3. Before the Solution Development Team built the infrastructure for the bar area, the Architect pointed out what was required.

4. The Architect checked with the decorators that tasks had been completed to a satisfactory standard, and agreed a list of items that needed further coats of paint or cleaning up.

5. The Gardener began planting the borders and has placed an order for further bulbs to complete this task.

Column 2:

A) Thought

B) Action

C) Conversation

Question # 35

Which 2 statements explain why the Timber Tigers ' Site Manager would be an appropriate Solution Developer?

A.

Accustomed to bringing in contract staff for short periods of time.

B.

Closely manages the building team so that they consistently produce high-quality work.

C.

Is able to represent the team in all daily meetings.

D.

An experienced builder who is good at turning a brief into a practical design.

E.

Is empowered by Timber Tigers ' management to make decisions on the building work.

Question # 36

Using the Project Scenario and the additional information provided for this question in the Scenario Booklet, answer the following questions about Feasibility.

Remember to limit your answers to the number of selections requested in each question.

Which 2 statements describe the appropriate application of Agile Project Management when developing the Solution Architecture Definition (SAD)?

A.

Paper-based drawings are to be used for each option being considered for the building and gardens.

B.

The SAD must include a physically-built miniature model of the Hoy Hall building.

C.

The Architecture Angels ' Marketing Director can request a SAD to illustrate the achievability of complex elements of the solution.

D.

The views of the ' Hoy for Hoy Hall ' Action Group members are NOT relevant to the business decision made by Architecture Angels ' Finance Director when approving the final option.

E.

The SAD should contain high-level costs for all elements of each solution option.

Question # 37

Using the additional information provided for this question in the Scenario Booklet, answer the following questions about the requirement for a fire exit from the

upstairs of the building.

What is an appropriate reason to classify the need for a secondary exit from the upstairs of the building as a Must Have requirement?

A.

Provision of a secondary exit from the upstairs of the building will ensure compliance with national fire safety regulations.

B.

A secondary exit from the upstairs of the building would help ease congestion in busy periods during festivals.

C.

A secondary exit from the upstairs of the building will provide a shorter and more direct route into the garden than the main stairway.

D.

The requirement for a secondary exit from the upstairs of the building has to be made a higher priority in order to be moved to an earlier Timebox.

Question # 38

Which 2 statements explain why the Architecture Angels ' Chief Accountant would be an appropriate Business Ambassador?

A.

Has been authorised by the Architecture Angels ' Marketing Director to take decisions on behalf of the business areas.

B.

Has three Accounts Clerks as staff.

C.

Has been with the company for six months so is keen to make an impression.

D.

Understands the financial realities about what can be afforded and what is needed.

E.

Runs a personal refurbishment project in any spare time so will be able to interact with the technical staff.

Question # 39

What action should the Project Manager take regarding the remaining windows?

A.

All requirements that have not been met are automatically carried over to the next increment.

B.

Extend the time allocated to Timebox C, to allow time to complete these.

C.

Insist that all available resources within the Solution Development Team are redirected to this work over the remaining two days.

D.

Decompose the individual elements of work to be completed on the windows and reprioritise them to meet the Minimum Usable Subset.

Question # 40

Answer the following questions about the acceptance criteria within the project.

Decide whether the approach to setting and using acceptance criteria has been applied appropriately and select the response that supports your decision.

During Solution Development Timebox A, a new Health and Safety requirement arises: the front door is required to have wheelchair access. This is a legal requirement and is a Must Have before any staff or general public access can be allowed. The Solution Development Team will work with the Local Planning Authority Officer, the specialist who identified the requirement, to identify further acceptance criteria for Solution Development Timebox A.

Is this an appropriate action related to acceptance criteria?

A.

Yes, because the new requirement needs to be understood, built and delivered in this Timebox.

B.

Yes, because the Local Planning Authority Officer owns the justification for the new requirement.

C.

No, because this new requirement would NOT be included in the original Prioritised Requirements List and therefore does NOT need acceptance criteria to be defined.

D.

No, because the Business Visionary is responsible for defining acceptance criteria.

Go to page: