You'll find that our AgilePM-Practitioner exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these AgilePM-Practitioner sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Agile Project Management (AgilePM) Practitioner Exam practice test comfortably within the allotted time.

Question # 51

Which statement should be recorded under the High-level change approach heading?

A.

Existing UniCo staff only have skills in providing the installation of large-scale computer systems.

B.

Fast-track training of the Sales staff means taking a member of staff away from the sales operational work.

C.

The senior management will be asked to share examples of other companies undertaking, and successfully overcoming, similar challenges.

D.

All four Change Initiative elements will be required to produce a monthly formal report for the CEO.

Question # 52

The Change Manager is discussing the relocation of the Selco staff to the UniCo office with the Operations Director. They are using the SCARF framework of people ' s social experience to guide management actions.

Answer the following questions about the use of David Rock ' s SCARF framework to increase the motivation for change.

The founder of Selco, now the Applications Manager, is moving from an individual office to a desk in the shared area for the Operations Director ' s leadership team in the UniCo building. At the last Operations ' group meeting, the Operations Director thanked the Applications Manager for cooperating fully with the relocation.

Is this an appropriate approach to reward the brain in the need for ' status ' , and

why?

A.

No, because ' status ' should be rewarded by ensuring open, two-way

communication using rich channels.

B.

No, because the Application Manager ' s knowledge and skills are still

relevant and there no threat to ' status ' .

C.

Yes, because highlighting cooperation provides an opportunity for the

Applications Manager to learn and develop.

D.

Yes, because praising people publicly helps to improve a person ' s

informal importance in the organization.

Question # 53

The Customer Services Director has announced the new structure at a large presentation for all Customer Services staff. The scale and design of the change have surprised many of the staff.

In the weeks immediately following the Customer Services Director’s initial presentation, there have been rumors of the Help Desk staff talking unhappily in small groups, with blame directed at " the management " for a recent period of poor performance of the department.

Which approach is the MOST appropriate way for the Customer Services Director to create early involvement in the change?

A.

Target those staff in the Help Desk who are change-averse so that they are the first ones involved in the program.

B.

Delay communications a few weeks so that all staff have time to think for themselves about the benefits of the new structure.

C.

Identify those staff who would be willing to trial new Help Desk processes and work on pilots in the department.

D.

Encourage the Help Desk staff to begin setting goals for themselves under the new structure.

Question # 54

The Applications Manager, who is already very busy, is proposed as a Change Agent.

Which action by the Change Manager is MOST likely to make this department ' s change agent role effective?

A.

Provide an anonymous complaints system for use if the team cannot raise concerns directly.

B.

Appoint a junior team member as change agent with the Applications Manager as support ' buddy. '

C.

Train the Application Manager in time management techniques and approaches.

D.

Publish the timetable of the Operational delivery process workstream objectives to staff.

Question # 55

The Change Manager is looking to develop the change agent network that will support the changes related to the Operational delivery processes workstream.

Which action is MOST likely to promote success in the induction of the change agent network to the Operational delivery processes workstream?

A.

Allocate bonus payments to change agents who deliver quicker than planned.

B.

Ensure that the CEO, as Sponsor, allows time to get to know the change agents.

C.

Transfer the change agents for a short period to help the other three workstreams.

D.

Negotiate that the change agents have direct authority to implement changes.