You'll find that our APM-001 exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these APM-001 sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Associate in Project Management (APM) practice test comfortably within the allotted time.

Question # 136

Which of the following is a tool or technique used in the Determine Budget process?

A.

Variance analysis

B.

Three-point estimating

C.

Bottom-up estimating

D.

Historical relationships

Question # 137

The completion of the project scope is measured against the:

A.

requirements documentation.

B.

project scope statement.

C.

project management plan.

D.

work performance measurements.

Question # 138

Activity cost estimates are quantitative assessments of the probable costs required to:

A.

Create WBS.

B.

complete project work.

C.

calculate costs.

D.

Develop Project Management Plan.

Question # 139

Inputs to the Plan Risk Management process include the:

A.

cost management plan.

B.

risk management plan,

C.

activity list,

D.

risk register.

Question # 140

During project selection, which factor is most important?

A.

Types of constraints

B.

Internal business needs

C.

Budget

D.

Schedule

Question # 141

The project has a current cost performance index of 0.80. Assuming this performance wi continue, the new estimate at completion is $1000. What was the original budget at completion for the project?

A.

$800

B.

$1000

C.

$1250

D.

$1800

Question # 142

What is project management?

A.

A logical grouping of project management inputs, outputs, tools, and techniques

B.

Applying knowledge, skills, tools, and techniques to project activities to meet the project requirements

C.

Launching a process that can result in the authorization of a new project

D.

A formal, approved document that defines how the project is executed, monitored, and controlled

Question # 143

Which baselines make up the performance measurement baseline?

A.

Scope baseline, cost baseline, and schedule baseline

B.

Scope baseline, project management baseline, and quality baseline

C.

Cost baseline, schedule baseline, and risk baseline

D.

Cost baseline, project management baseline, and schedule baseline

Question # 144

The three processes of Project Cost Management are:

A.

Estimate Costs, Control Schedule, and Control Costs.

B.

Estimate Costs, Determine Budget, and Estimate Activity Resources.

C.

Determine Budget, Control Schedule, and Estimate Activity Resources.

D.

Estimate Costs, Determine Budget, and Control Costs.

Question # 145

When a permitting agency takes longer than planned to issue a permit, this can be described as a risk:

A.

event.

B.

response,

C.

perception.

D.

impact.

Question # 146

Risk responses reflect an organization ' s perceived balance between:

A.

risk taking and risk avoidance.

B.

known risk and unknown risk.

C.

identified risk and analyzed risk.

D.

varying degrees of risk.

Question # 147

In which type of contract are the performance targets established at the onset and the final contract price determined after completion of all work based on the sellers performance?

A.

Firm-Fixed-Price (FFP)

B.

Fixed Price with Economic Price Adjustments (FP-EPA)

C.

Fixed-Price-Incentive-Fee (FPIF)

D.

Cost Plus Fixed Fee (CPFF)

Question # 148

The technique of subdividing project deliverables into smaller, more manageable components until the work and deliverables are defined to the work package level is called:

A.

a control chart.

B.

baseline.

C.

Create WBS.

D.

decomposition.

Question # 149

Which type of dependency is contractually required or inherent in the nature of the work?

A.

External

B.

Lead

C.

Discretionary

D.

Mandatory

Question # 150

Which of the following is an output of Define Scope?

A.

Project scope statement

B.

Project charter

C.

Project plan

D.

Project schedule