You'll find that our APM-001 exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these APM-001 sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Associate in Project Management (APM) practice test comfortably within the allotted time.

Question # 166

An input to the Collect Requirements process is the:

A.

stakeholder register.

B.

project management plan.

C.

project scope statement.

D.

requirements management plan.

Question # 167

The process for performing variance analysis may vary, depending on:

A.

scenario building, technology forecasting, and forecast by analogy.

B.

working relationships among various stakeholders and team members.

C.

application area, the standard used, and the industry,

D.

work to be completed next.

Question # 168

A project manager at a publishing company decides to initiate the editing phase of the project as soon as each chapter is written. Which type of Sequence Activities tool and technique is involved, considering that there was a start-to-start relationship with a 15-day delay?

A.

Slack

B.

Float

C.

Lag

D.

Lead

Question # 169

Which process requires implementation of approved changes?

A.

Direct and Manage Project Execution

B.

Monitor and Control Project Work

C.

Perform Integrated Change Control

D.

Close Project or Phase

Question # 170

The total of the planned value (PV) is also known as:

A.

work breakdown structure (WBS).

B.

schedule target.

C.

performance measurement baseline (PMB).

D.

earned value baseline.

Question # 171

The group technique that enhances brainstorming with a voting process used to rank the most useful ideas for prioritization is called the:

A.

majority rule technique.

B.

nominal group technique.

C.

Delphi technique,

D.

idea/mind mapping technique.

Question # 172

Progressively elaborating high-level information into detailed plans is performed by the:

A.

project management office

B.

portfolio manager

C.

program manager

D.

project manager

Question # 173

Organizational process assets, a lessons-learned database, and historical information are all inputs to which process?

A.

Plan Cost Management

B.

Plan Scope Management

C.

Plan Stakeholder Management

D.

Plan Schedule Management

Question # 174

The process of monitoring the status of the project and product scope as well as managing the changes to the scope baseline is known as:

A.

Validate Scope.

B.

Plan Scope Management.

C.

Control Scope.

D.

Define Scope.

Question # 175

The scope management plan and scope baseline are contained in:

A.

organizational process assets

B.

a requirements traceability matrix

C.

the project charter

D.

the project management plan

Question # 176

Technical capability, past performance, and intellectual property rights are examples of:

A.

performance measurement criteria

B.

source selection criteria

C.

product acceptance criteria

D.

phase exit criteria

Question # 177

The degree, amount, or volume of risk that an organization or individual will withstand is known as its risk:

A.

Analysis

B.

Appetite

C.

Tolerance

D.

Response

Question # 178

Which type of dependency used in the Sequence Activities process is sometimes referred to as preferred logic, preferential logic, or soft logic?

A.

Internal

B.

External

C.

Discretionary

D.

Mandatory

Question # 179

Project deliverables that have been completed and checked for correctness through the Control Quality process are known as:

A.

Verified deliverables.

B.

Validated deliverables.

C.

Acceptance criteria.

D.

Activity resource requirements.

Question # 180

The following chart contains information about the tasks in a project.

Based on the chart, what is the schedulevariance (SV) for Task 8?

A.

-2,000

B.

-1,000

C.

1,000

D.

2,000

Go to page: