You'll find that our APM-001 exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these APM-001 sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Associate in Project Management (APM) practice test comfortably within the allotted time.

Question # 76

A tool and technique used during the Perform Qualitative Risk Analysis process is:

A.

risk data quality assessment.

B.

variance and trend analysis.

C.

data gathering and representation techniques.

D.

risk audits.

Question # 77

A purchase order for a specified item to be delivered by a specified date for a specified price is the simplest form of what type of contract?

A.

Cost-reimbursable

B.

Time and material

C.

Fixed price or lump-sum

D.

Cost-plus-fixed-fee

Question # 78

Conflict should be best addressed in which manner?

A.

Early, in private, using a direct, collaborative approach

B.

Early, in public, using an indirect, collaborative approach

C.

Early, in private, using an indirect, cooperative approach

D.

As late as possible, in public, using a direct, confrontational approach

Question # 79

A project team attempts to produce a deliverable and finds that they have neither the expertise nor the time to complete the deliverable in a timely manner. This issue could have been avoided if they had created and followed a:

A.

risk management plan

B.

human resource management plan

C.

scope management plan

D.

procurement management plan

Question # 80

Power, urgency, and legitimacy are attributes of which stakeholder classification model?

A.

Salience

B.

Influence/impact

C.

Power/interest

D.

Power/influence

Question # 81

Which process involves the creation of a document that provides the project manager with the authority to apply resources to a project?

A.

Define Activities

B.

Direct and Manage Project Work

C.

Develop Project Management Plan

D.

Develop Project Charter

Question # 82

The iterative process of increasing the level of detail in a project management plan as greater amounts of information become available is known as:

A.

Continuous improvement.

B.

Predictive planning.

C.

Progressive elaboration.

D.

Quality assurance.

Question # 83

The Plan Stakeholder Management process belongs to which Process Group?

A.

Executing

B.

Initiating

C.

Planning

D.

Monitoring and Controlling

Question # 84

Enterprise environmental factors are an input to which process?

A.

Control Scope

B.

Define Scope

C.

Plan Scope Management

D.

Collect Requirements

Question # 85

Which tool or technique allows a large number of ideas to be classified into groups for review and analysis?

A.

Nominal group technique

B.

Idea/mind mapping

C.

Affinity diagram

D.

Brainstorming

Question # 86

Which of the following reduces the probability of potential consequences of project risk events?

A.

Preventive action

B.

Risk management

C.

Corrective action

D.

Defect repair

Question # 87

Which tool or technique is used in Manage Stakeholder Expectations?

A.

Stakeholder management strategy

B.

Communication methods

C.

Issue log

D.

Change requests

Question # 88

Which output of Project Cost Management consists of quantitative assessments of the probable costs required to complete project work?

A.

Activity cost estimates

B.

Earned value management

C.

Cost management plan

D.

Cost baseline

Question # 89

The definition of when and how often the risk management processes will be performed throughout the project life cycle is included in which risk management plan component?

A.

Timing

B.

Methodology

C.

Risk categories

D.

Budgeting

Question # 90

Which tool or technique is used in the Perform Integrated Change Control process?

A.

Decomposition

B.

Modeling techniques

C.

Resource optimization

D.

Meetings