You'll find that our APM-001 exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these APM-001 sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Associate in Project Management (APM) practice test comfortably within the allotted time.

Question # 121

The most commonly used type of precedence relationship in the precedence diagramming method (PDM) is:

A.

start-to-start (SS)

B.

start-to-finish (SF)

C.

finish-to-start (FS)

D.

finish-to-finish (FF)

Question # 122

Which of the following is contained within the communications management plan?

A.

An organizational chart

B.

Glossary of common terminology

C.

Organizational process assets

D.

Enterprise environmental factors

Question # 123

Organizational planning impacts projects by means of project prioritization based on risk, funding, and an organizations:

A.

Budget plan

B.

Resource plan

C.

Scope plan

D.

Strategic plan

Question # 124

Most experienced project managers know that:

A.

every project requires the use of all processes in the PMBOKĀ® Guide.

B.

there is no single way to manage a project.

C.

project management techniques are risk free.

D.

there is only one way to manage projects successfully.

Question # 125

Perform Quality Control is accomplished by:

A.

Identifying quality standards that are relevant to the project and determining how to satisfy them.

B.

Monitoring and recording the results of executing the quality activities to assess performance and recommend necessary changes.

C.

Ensuring that the entire project team has been adequately trained in quality assurance processes.

D.

Applying Monte Carlo, sampling, Pareto analysis, and benchmarking techniques to ensure conformance to quality standards.

Question # 126

Managing ongoing production of goods and services to ensure business continues efficiently describes which type of management?

A.

Portfolio

B.

Project

C.

Program

D.

Operations

Question # 127

What is an objective of the Develop Project Team process?

A.

Feelings of trust and improved cohesiveness

B.

Ground rules for interaction

C.

Enhanced resource availability

D.

Functional managers becoming more involved

Question # 128

When would resource leveling be applied to a schedule model?

A.

Before constraints have been identified

B.

Before it has been analyzed by the critical path method

C.

After it has been analyzed by the critical path method

D.

After critical activities have been removed from the critical path

Question # 129

Which statement is true about the project management body of knowledge?

A.

Recognized by every project manager

B.

Constantly evolving

C.

The sum of all knowledge related to project management

D.

A sum of knowledge that should be applied on every project

Question # 130

Which risk response strategy is common for both positive and negative risks?

A.

Share

B.

Accept

C.

Mitigate

D.

Transfer

Question # 131

The contract in which the seller is reimbursed for all allowable costs for performing the contract work and then receives a fee based upon achieving certain performance objectives is called a:

A.

Cost Plus Incentive Fee Contract (CPIF).

B.

Cost Plus Fixed Fee Contract (CPFF).

C.

Fixed Price Incentive Fee Contract (FPIF).

D.

Time and Material Contract (T & M).

Question # 132

A project manager has created an issue log to document issues communicated by project team members during weekly team meetings. This is an input of:

A.

Manage Stakeholder Expectations.

B.

Monitor and Control Risks.

C.

Plan Risk Management.

D.

Report Performance.

Question # 133

The risk shared between the buyer and seller is determined by the:

A.

assumption log.

B.

quality checklist.

C.

risk register.

D.

contract type.

Question # 134

Which of the following is an input to the Develop Project Charter process?

A.

Work performance information

B.

Project management plan

C.

Business case

D.

Change requests

Question # 135

An input to the Estimate Activity Resources process is:

A.

Activity resource requirements.

B.

Published estimating data.

C.

Resource calendars.

D.

Resource breakdown structure (RBS).