You'll find that our APM-001 exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these APM-001 sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Associate in Project Management (APM) practice test comfortably within the allotted time.

Question # 196

Which tool or technique is used to develop the human resource management plan?

A.

Ground rules

B.

Expert judgment

C.

Team-building activities

D.

Interpersonal skills

Question # 197

Which input to the Identify Stakeholders process provides information about internal or external parties related to the project?

A.

Procurement documents

B.

Communications plan

C.

Project charter

D.

Stakeholder register

Question # 198

An input to the Plan Cost Management process is:

A.

Cost estimates.

B.

Resource calendars,

C.

The project charter,

D.

The risk register.

Question # 199

Which Collect Requirements output links the product requirements to the deliverables that satisfy them?

A.

Requirements documentation

B.

Requirements traceability matrix

C.

Project management plan updates

D.

Project documents updates

Question # 200

Which item is a formal proposal to modify any document, deliverable, or baseline?

A.

Change request

B.

Requirements documentation

C.

Scope baseline

D.

Risk urgency assessment

Question # 201

Which item is an example of personnel assessment?

A.

Resource calendar

B.

Tight matrix

C.

Team-building activity

D.

Focus group

Question # 202

Sending letters, memos, reports, emails, and faxes to share information is an example of which type of communication?

A.

Direct

B.

Interactive

C.

Pull

D.

Push

Question # 203

An output of the Plan Quality Management process is:

A.

A process improvement plan,

B.

Quality control measurements.

C.

Work performance information,

D.

The project management plan.

Question # 204

An input to the Plan Procurement Management process is:

A.

Source selection criteria.

B.

Market research.

C.

A stakeholder register.

D.

A records management system.

Question # 205

What is the schedule performance index (SPI) if the planned value (PV) is $100, the actual cost (AC) is $150, and the earned value (EV) is $50?

A.

0.50

B.

0.67

C.

1.50

D.

2.00

Question # 206

Change requests are processed for review and disposition according to which process?

A.

Control Quality

B.

Control Scope

C.

Monitor and Control Project Work

D.

Perform Integrated Change Control

Question # 207

When does the project team determine which dependencies are discretionary?

A.

Before the Define Activities process

B.

During the Define Activities process

C.

Before the Sequence Activities process

D.

During the Sequence Activities process

Question # 208

Typical outcomes of a project include:

A.

Products, services, and improvements.

B.

Products, programs, and services.

C.

Improvements, portfolios, and services.

D.

Improvements, processes, and products.

Question # 209

The only Process Group that comprises processes that typically occur from the beginning to the end of the project life cycle is:

A.

Planning.

B.

Executing,

C.

Monitoring and Controlling.

D.

Closing.

Question # 210

An input used in developing the communications management plan is:

A.

Communication models.

B.

Enterprise environmental factors.

C.

Organizational communications,

D.

Organizational cultures and styles.