You'll find that our APM-001 exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these APM-001 sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Associate in Project Management (APM) practice test comfortably within the allotted time.

Question # 46

Prioritizing risks for further analysis or action by assessing and combining their probability of occurrence and impact takes place in which process?

A.

Monitor and Control Risks

B.

Plan Risk Management

C.

Perform Qualitative Risk Analysis

D.

Perform Quantitative Risk Analysis

Question # 47

Which of the following is an information gathering technique in Identify Risks?

A.

Influence diagrams

B.

Brainstorming

C.

Assumption analysis

D.

SWOT analysis

Question # 48

Project contracts generally fall into which of the following three broad categories?

A.

Fixed-price, cost reimbursable, time and materials

B.

Make-or-buy, margin analysis, fixed-price

C.

Time and materials, fixed-price, margin analysis

D.

Make-or-buy, lump-sum, cost-plus-incentive

Question # 49

Which is an input to the Verify Scope process?

A.

Performance report

B.

Work breakdown structure (WBS)

C.

Requested changes

D.

Project management plan

Question # 50

Control charts, flowcharting, histograms, Pareto charts, and scatter diagrams are tools and techniques of which process?

A.

Perform Quality Control

B.

Perform Quality Assurance

C.

Plan Quality

D.

Report Performance

Question # 51

The process of monitoring the status of the project to update project progress and manage changes to the schedule baseline is:

A.

Control Schedule.

B.

Quality Control.

C.

Perform Integrated Change Control.

D.

Develop Schedule.

Question # 52

A work package has been scheduled to cost $1,000 to complete and was to be finished today. As of today, the actual expenditure is $1,200 and approximately half of the work has been completed. What is the cost variance?

A.

-700

B.

-200

C.

200

D.

500

Question # 53

Which of the following is an output of the Monitor and Control Project Work process?

A.

Change requests

B.

Performance reports

C.

Organizational process assets

D.

Project management plan

Question # 54

The creation of an internet site to engage stakeholders on a project is an example of which type of communication?

A.

Push

B.

Pull

C.

Interactive

D.

Iterative

Question # 55

Which of the following outputs from the Control Schedule process aids in the communication of schedule variance (SV), schedule performance index (SPI), or any performance status to stakeholders?

A.

Performance organizations

B.

Schedule baselines

C.

Work performance measurements

D.

Change requests

Question # 56

A given schedule activity is most likely to last four weeks. In a best-case scenario, the schedule activity is estimated to last two weeks. In a worst-case scenario, the schedule activity is estimated to last 12 weeks. Given these three estimates, what is the expected duration of the activity?

A.

Three weeks

B.

Four weeks

C.

Five weeks

D.

Six weeks

Question # 57

In the Estimate Activity Durations process, productivity metrics and published commercial information inputs are part of the:

A.

enterprise environmental factors.

B.

organizational process assets.

C.

project management plan,

D.

project funding requirements.

Question # 58

Which Plan Schedule Management tool or technique may involve choosing strategic options to estimate and schedule the project?

A.

Facilitation techniques

B.

Expert judgment

C.

Analytical techniques

D.

Variance analysis

Question # 59

Which provides the basic framework for managing a project?

A.

Project life cycle

B.

Work breakdown structure (WBS)

C.

Enterprise environmental factors

D.

Project initiation

Question # 60

Which is one of the major outputs of Sequence Activities?

A.

Responsibility assignment matrix (RAM)

B.

Work breakdown structure (WBS) update

C.

Project schedule network diagram

D.

Mandatory dependencies list