You'll find that our CPIM-8.0 exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these CPIM-8.0 sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Certified in Planning and Inventory Management (CPIM 8.0) practice test comfortably within the allotted time.

Question # 166

A plant uses a level production strategy due to the high costs of hiring and letting go of skilled employees. The constrained resource is due to be upgraded in the fourth month of the planning horizon, and that will reduce capacity for that month by 17%.

Which of the following actions would be appropriate in this situation to maintain current levels of customer service and gross margin?

A.

Increase planned production for the next three periods.

B.

Defer the upgrade to a period beyond the planning time fence.

C.

Increase planned production from the fifth period on.

D.

Defer the upgrade to the period in which the highest stock level is planned.

Question # 167

The project manager for a new application development is building a test framework. It has been agreed that the framework will Include penetration testing; however, the project manager is keen to identify any flaws prior to the code being ready for execution. Which of the following techniques BEST supports this requirement?

A.

System vulnerability scans

B.

Database injection tests

C.

System reliability tests

D.

Static source code analysis

Question # 168

Which of the following activities is an example of collaboration between suppliers and operations which would give more lead time visibility?

A.

Conducting a facility tour for a supplier

B.

Sharing of demand data with a supplier

C.

Sending the supplier an annual forecast for materials

D.

Conducting a qualification meeting with the supplier of a new material

Question # 169

Which software development methodology is an iterative customer-value-centric approach which helps teams deliver value to their customers faster and with fewer problems?

A.

Agile model

B.

Cleanroom model

C.

Waterfall model

D.

Incremental model

Question # 170

During an onsite audit, an assessor inspected an organization’s asset decommission practice. Which of the following would MOST likely be a finding from a security point of view?

A.

Solid State Drives (SSD) were degaussed along with hard drives.

B.

The Non-Disclosure Agreement (NDA) between the organization and its data disposal service was more than 3 years old.

C.

Hard drives from older assets replaced defective hard drives from current assets of similar classification levels.

D.

Data classifications were not clearly identified.

Question # 171

After a recent cybersecurity incident, a manufacturing organization is interested in further hardening its Identity and Access Management (IAM) solution. Knowing that the organization limits the use of personal devices in the facility, which could BEST be implemented to enhance the manufacturing organization ' s IAM solution?

A.

Enhanced background checks

B.

Mobile Multi-Factor Authentication (MFA) application

C.

Biometric system

D.

Personal Identification Number (PIN) code

Question # 172

In which of the following situations would you use an X-bar chart?

A.

Track the number of defects that are found in each unit.

B.

Measure the difference between the largest and the smallest in a sample.

C.

Determine the average value of a group of units.

D.

Estimate a subgroup variation.

Question # 173

A manufacturer has a forecasted annual demand of 1,000,000 units for a new product. They have to choose 1 of 4 new pieces of equipment to produce this product. Assume that revenue will be $10 per unit for all 4 options.

Which machine will maximize their profit if the manufacturer anticipates market demand will be steady for 3 years and there is no residual value for any of the equipment choices?

MachineFixed CostVariable Cost per UnitAnnual Capacity

AS100.000$6 00800,000 units

B$200,000$5 501.000,000 units

C$250,000$5 001,200,000 units

D$1 000.000$4 501 400.000 units

A.

Machine A

B.

Machine B

C.

Machine C

D.

Machine D

Question # 174

Which of the following outcomes Is a benefit of mixed-model scheduling?

A.

Increased inventory

B.

Improved demand response

C.

Fewer setups

D.

Fewer material shortages

Question # 175

Which of the following circumstances would cause a move from acceptance sampling to 100% inspection?

A.

History shows that the quality level has been stable from lot to lot.

B.

The company uses one of its qualified suppliers.

C.

Downstream operators encounter recurring defects.

D.

The percent of defects is expected to be greater than 5%.