Spring Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: buysanta

Exact2Pass Menu

ISTQB® Certified Tester Advanced Level - Test Manager [Syllabus 2012]

Last Update 19 hours ago Total Questions : 130

The ISTQB® Certified Tester Advanced Level - Test Manager [Syllabus 2012] content is now fully updated, with all current exam questions added 19 hours ago. Deciding to include CTAL-TM_Syll2012 practice exam questions in your study plan goes far beyond basic test preparation.

You'll find that our CTAL-TM_Syll2012 exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these CTAL-TM_Syll2012 sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any ISTQB® Certified Tester Advanced Level - Test Manager [Syllabus 2012] practice test comfortably within the allotted time.

Question # 11

When scheduling performance testing, which of the following approaches would be most advisable? [1]

A.

Starting the performance testing during unit and integration testing

B.

Deferring the start of performance testing until all functional defects have been resolved

C.

Leveraging end users to do unit-level performance testing and automated tools for system-level performance testing

D.

Requiring all performance tests to pass before starting functional testing

Question # 12

Assume that no additional product risks have been identified during the first week of test execution.

Which of the following answers would you expect to best describe the residual risks associated with the identified product risks, at the end of the first week of test execution?

Number of correct responses: 1

K3 2 credits

A.

Since R3 is the only risk for which all test cases have passed, the risk has been reduced by 20%

B.

The test execution status table indicates that the risk has been reduced by 56%

C.

The residual risk level can’t be determined, because it requires that all the test cases have been executed

D.

The test execution table doesn’t give an indication of the risk level of the open defects and the test cases that failed or are not run yet

Question # 13

Test Management

Assume you have some data related to confirmation testing during system testing of a past project.

In that project 240 bug reports have been opened once, 80 were opened twice, 10 were opened three times and no bug reports have been opened more than three times.

You estimate that a bug report, which has failed its confirmation test, costs, on average, 3 person-hours.

Which of the following statements correctly describe the value of these confirmatory testing activities based on cost of quality?

Number of correct responses: 1

K3 2 credits

A.

300 person-hours have been spent on the project during the system testing phase, because of the failed confirmation tests and this cost belongs to the costs of internal failure

B.

340 person-hours have been spent on the project during the system testing phase, because of the failed confirmation tests and this cost belongs to the costs of external failure

C.

340 person-hours have been spent on the project during the system testing phase, because of the failed confirmation tests and this cost belongs to the costs of internal failure

D.

300 person-hours have been spent on the project during the system testing phase, because of the failed confirmation tests and this cost belongs to the costs of detection

Question # 14

Test Management

You are performing a quality risk analysis for a CSCI (Computer Software Configuration Item) used to implement a CBIT (Continuous Built-In Test) module of a safety-critical system.

During the quality risk analysis you are trying to identify the ways in which failures of the CBIT module can occur, for each of them trying to determine the potential causes and likely effects, and the risk level (calculated as the product of three factors: severity, occurrence and detection).

Which of the following risk analysis techniques are you working with?

Number of correct responses: 1

K2 1 credit

A.

A lightweight product risk analysis technique

B.

Failure Mode and Effect Analysis

C.

Wide Band Delphi

D.

Cost of Exposure

Question # 15

Test Management

In the next two months some new features will be constantly added to new releases of a project you are working on as Test Manager.

You have identified as one of the main project risks, that the requirements specification will still be incomplete when your team starts the test design and implementation phase.

Some requirements will most likely be completed too late to allow a proper test preparation.

You and your test team have already worked on several similar past projects in the same organization.

Which one of the following options would you expect to be the most effective at mitigating this risk?

Number of correct responses: 1

K4 3 credits

A.

Don’t prepare any test and just run the regression test suite to check that the new features don’t introduce regression

B.

Make reasonable assumptions about the missing details and design lightweight tests that can be easily updated during test execution

C.

Don’t design any test until the test execution starts, then communicate that test execution is blocked due to incomplete requirements

D.

Even if there are only few details missing, escalate the risk to the project manager without preparing any tests

Question # 16

Reviews

You are the Test Manager of a project that adopts a V-model with four formal levels of testing: unit, integration, system and acceptance testing.

On this project reviews have been conducted for each development phase prior to testing, which is to say that reviews of requirements, functional specification, high-level design, low-level design and code have been performed prior to testing.

Assume that no requirements defects have been reported after the release of the product.

Which TWO of the following metrics do you need in order to evaluate the requirements reviews in terms of phase containment effectiveness?

Number of correct responses: 2

K3 2 credits

A.

Number of defects found during the requirements review

B.

Total number of defects attributable to requirements found during unit, integration, system and acceptance testing

C.

Total number of defects found during functional specification review, high-level design review, low-level design review, code review, unit testing, integration testing, system testing and acceptance testing

D.

Time to conduct the requirements review

E.

Total number of defects attributable to requirements, found during functional specification review, high-level design review, low-level design review, code review, unit testing, integration testing, system testing and acceptance testing

Question # 17

Which classification information would be most useful to capture for newly identified defects? [2]

A.

The priority that the business assigned to the project that the defect was found in

B.

The system build that the defect was found in

C.

The name of the configuration manager who built the system

D.

The number of test steps in the test script that found the defect

Question # 18

Your test team has created a custom automation tool that will be used for an upcoming release. Now that the tool has been coded, what

should be the next step? [1]

A.

Create the tool support guide

B.

Perform an ROI study

C.

Compare the new tool to open source tools

D.

Test the tool

Question # 19

During the follow-up phase the following conditions are checked:

X1. The code has been completely reviewed

X2. All the identified defects have been correctly fixed and the modified code has been compiled successfully and run through all the static analyzers used by the project without warnings and errors

X3. The modified code is available under the configuration management system with a new version number for the specified CI

If these conditions are fulfilled then the review process terminates.

Which of the following characteristics of a formal review is missing in this description?

Number of correct responses: 1

K2 1 credit

A.

Defined entry and exit criteria

B.

Checklists to be used by the reviewers

C.

Deliverables such as reports, evaluation sheets or other review summary sheets

D.

Metrics for reporting on the review effectiveness, efficiency, and progress

Question # 20

Reviews

You are a Test Manager working for a software organization where reviews have never been applied. After a meeting with your managers examining a business case for reviews, (including their costs, benefits, and potential issues), the management finally decides to adopt formal reviews for future projects.

You have been given a budget that you have spent to provide training in the review process and to introduce the review process on a pilot project.

On that pilot project the introduction of reviews has been very positive in terms of positive involvement from all the participants. All the reviews applied to different documents have been very effective for their purposes (especially at revealing defects).

Which of the following answers describes an important success factor for the introduction of formal reviews which is missing in this scenario?

Number of correct responses: 1

K4 3 credits

A.

Management support

B.

Participant support

C.

Definition and use of metrics to measure the ROI (Return On Investment)

D.

Training in the review process

Go to page: