You'll find that our INSTC_V8 exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these INSTC_V8 sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any BICSI Installer 2 - Copper Exam practice test comfortably within the allotted time.

Question # 31

Which of the following items may be used as a substitute device for a pulling eye?

A.

Wire mesh grip

B.

Fan-out kit

C.

Innerduct

D.

D rings

Question # 32

Which of the following must be measured before the length of a coaxial cable can be calculated?

A.

Propagation delay

B.

Insertion loss

C.

DC loop resistance

D.

Delay skew

Question # 33

Which of the following is a measure of the amount of information being transported over media?

A.

Megabits

B.

Volt-amperes

C.

Kilowatt hours

D.

Megahertz

Question # 34

According to BICSI guidelines, which of the following best describes the maximum pulling tension recommended for a 4-pair UTP cable during installation (without using special pulling grips)?

A.

11 kg (25 lb)

B.

22 kg (50 lb)

C.

44 kg (100 lb)

D.

66 kg (145 lb)

Question # 35

What is the recommended minimum amount of aisle space between and around equipment?

A.

0.6 m (2 ' )

B.

1 m (3.3 ' )

C.

1.2 m (4 ' )

D.

1.52 m (5 ' )

Question # 36

How much sheath of the cable needs to be removed in order to properly terminate an 8P8C?

A.

6.3mm (0.25 " )

B.

12.7mm (0.5 " )

C.

25mm (1 " )

D.

38 mm (1.5 " )

Question # 37

Which of the following is a floor serving space that serves as a point of termination for horizontal and backbone cables?

A.

EF

B.

ER

C.

TR

D.

TE

Question # 38

What is the most appropriate administration class for an infrastructure with multiple telecommunications spaces within one building?

A.

Class 1

B.

Class 2

C.

Class 3

D.

Class 4

Question # 39

A third 90-degree bend may be permitted in a conduit run if the run does NOT exceed ______?

A.

5 m (16.5 ' )

B.

10 m (33 ' )

C.

15 m (50 ' )

D.

30 m (100 ' )

Question # 40

When specifying cable routing within an Equipment Room (ER), BICSI guidelines recommend that ladder racks be mounted with adequate clearance from the top of the equipment racks. What is the TYPICAL recommended vertical clearance?

A.

15 cm (6 in)

B.

30 cm (12 in)

C.

45 cm (18 in)

D.

60 cm (24 in)