Spring Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: buysanta

Exact2Pass Menu

BICSI Registered Communications Distribution Designer – RCDDv14

Last Update 5 hours ago Total Questions : 288

The BICSI Registered Communications Distribution Designer – RCDDv14 content is now fully updated, with all current exam questions added 5 hours ago. Deciding to include RCDDv14 practice exam questions in your study plan goes far beyond basic test preparation.

You'll find that our RCDDv14 exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these RCDDv14 sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any BICSI Registered Communications Distribution Designer – RCDDv14 practice test comfortably within the allotted time.

Question # 1

A program manager joins a learn to fix a troubled enterprise-wide customer relationship management (CHM) system Analysis indicates that duplicate customer information data is resulting in redundant client information. The program manager accesses the knowledge repository tor similar programs to gather historical data and trends. A corrective action is identified, and a change in process is implemented to regain data integrity

What should the program manager do with the knowledge gained from this activity?

A.

Include the lessons learned in the weekly program report

B.

Update the communications management plan

C.

Update the lessons learned database

D.

Communicate the corrective action to the program sponsor

Question # 2

A software development program will launch iterative versions of new software called Alpha over two years Following that, a program will be released to the program team and developers to create new software called Beta While the program manager prepares the program closure plan tor Alpha, the program sponsor expresses concern about its support after program closure.

What should the program manager do as part of Alpha ' s program closure plan?

A.

Execute the transition plan and Include Knowledge transfer to transition Alpha support to operations

B.

Keep the Alpha program open until support is no longer required, then execute program closure

C.

Adjust Alpha ' s exit criteria to ensure its support is included in the Beta program

D.

Document the program closure procedure to ensure that resources are released from Alpha to develop Beta

Question # 3

The program manager wants to ensure that a program contributes to shareholder value. The program manager should verify alignment with which of the following?

A.

Program charter

B.

Organizational structures and policies

C.

Organizational strategic objectives

D.

Program governance plan

Question # 4

A large automaker begins a program to create the next-generation car. As the program team is composed, key stakeholders are identified

Key stakeholders for the program should include which of the following?

A.

Potential customers, government regulatory agencies, and competitors

B.

Project management office (PMO), third-party contractors, and agents

C.

Local car dealers, factory workers, and corporate officers

D.

Vice president of logistics, potential customers, and corporate executives

Question # 5

When designing for horizontal pathways in an environment that requires fire-stopping for penetrating a rated wall, what is the MAXIMUM till ratio for telecommunications cabling in a cable tray?

A.

20 percent

B.

40 percent

C.

50 percent

D.

There is no fill ratio for cable tray

Question # 6

A natural disaster shuts down operations for two days. The program has a major milestone that includes a timed payment of USS1 million.

Since the shutdown was not anticipated, what should the program manager do first?

A.

Implement the appropriate risk response plan and inform the stakeholders of the planned actions

B.

Utilize contingency reserves to hire contractors, which will accelerate the schedule to meet the original milestone

C.

Evaluate the impact, reassess the program risks, and determine options to be presented to the governance board

D.

Collaborate with the sponsor to determine options and negotiate a new date for the milestone

Question # 7

A company ' s marketing department Tails an internal compliance audit To comply with the auditor ' s remediation plan the legal department mandates that a content management system (CMS) be implemented After initiating the program for CMS implementation the program manager discovers that the marketing department has already preselected which CMS technology will be implemented.

What should the program manager do to ensure the success of the program?

A.

Meet with the vice president of purchasing to discuss the risks associated with preselecting a solution before the requirements have been gathered

B.

Host a kick-off meeting, request preliminary requirements from the marketing department, conduct a design session present the steering committee with a solution that meets the requirements: and meet with interested vendors

C.

Ask a senior marketing executive to act as the program sponsor and participate on the steering committee: require steering committee representation from the IT legal, and other key departments, validate that the chosen solution meets the requirements

D.

Initiate the program and begin a formal request for proposal (RFP) to validate the chosen solution and gam the confidence of the legal department

Question # 8

The transfer of unwanted signals may occur over one path or several paths. What method addresses the mitigation or suppression of unwanted signals?

A.

Mounting heights in racks and cabinets

B.

Bonding and grounding

C.

Signal coupling

D.

The use of unshielded cables

Question # 9

A company hires a program manager to create a healthcare management system. After five months the program manager identifies an opportunity to integrate an online medical solution, which could provide additional value to the stakeholders. The program sponsor approves the change in scope.

The program manager should ensure that the results obtained by this opportunity are working in tandem with which of the following?

A.

Critical success factors

B.

Key performance indicators

C.

Benefits management plan

D.

Stakeholder engagement plan

Question # 10

An ICT distribution designer is estimating the installation of five units of 1.5 m (5 ft) tong channel basket trays connected together in the ceiling. The total length of the pathway needed is 7 5 m (25 ft). How many supports will be needed ' '

A.

2

B.

5

C.

7

D.

10

E.

20

Go to page: