Spring Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: buysanta

Exact2Pass Menu

Planning & Scheduling Professional (PSP) Exam

Last Update 6 hours ago Total Questions : 216

The Planning & Scheduling Professional (PSP) Exam content is now fully updated, with all current exam questions added 6 hours ago. Deciding to include PSP practice exam questions in your study plan goes far beyond basic test preparation.

You'll find that our PSP exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these PSP sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Planning & Scheduling Professional (PSP) Exam practice test comfortably within the allotted time.

Question # 11

Time-scaled logic diagrams are

A.

Only calculated using a computer.

B.

The same as a pure-logic diagram.

C.

Used to calculate the most probable activity duration.

D.

Logic networks that are drawn to match the calendar.

Question # 12

Control Level Schedule activities are NOT one of the following:

A.

always analogous with Control Accounts

B.

always used to establish the scope and track the status of automation control systems

C.

may be composed form multiple WBS deliverable packages

D.

always reporting the status of phase deliverables

Question # 13

Should activities be coded with the EBS value?

A.

Yes. the project coding should roll up to EBS values

B.

No. only a few EBS values exist at the activity level

C.

No. the EBS Is much higher than activity coding

D.

Yes. the EBS is the most important project coding level

Question # 14

Theoretically construct a summary activity for activities 6001 through 6003. Identify the governing predecessor and successor activities for the hammock:

A.

Predecessor is activity 5001, successor is activity 8001

B.

Predecessor is activity 4001, successor is activity 8001

C.

Predecessor is activity 9001, successor is activity 9002

D.

Predecessor is activity 5001, successor is activity 8002

Question # 15

The Organizational Breakdown Structure (OBS) is a hierarchical structure that does NOT include which of the following:

A.

subcontractors

B.

stakeholders

C.

sub-subcontractors

D.

project director

Question # 16

The best source of project risk or opportunities is:

A.

A similar project in another state

B.

Rumors from the local Chamber of Commerce

C.

Failures by other contractors

D.

Internal and external stakeholders

Question # 17

What method would be the best way to determine the most likely as-built critical path of a project that is underway, and the schedule of which has been partially progressed?

A.

Use the progressed portion of the critical path of all the updates previous to the current update.

B.

Use the progressed portion of the critical path of the baseline schedule.

C.

Interview the project personnel for their perceptions and opinions because the schedule is usually inadequate.

D.

Use the forward-looking critical path of the most current updates.

Question # 18

When a fragnet of activities represents a known schedule risk, which activity will most likely change the overall outcome?

A.

The activity with the highest sensitivity.

B.

The activity with the longest duration.

C.

The activity with the lowest total float value.

D.

The activity with the highest resource loading.

Question # 19

Before the work begins, the contractor considers crashing the schedule. How much would the crashed general conditions have to be reduced to break even with the normal cost budget?

A.

$195 per day

B.

S1.772 per day

C.

General conditions do not need to be reduced to break even

D.

$1.223 per day

Question # 20

What is accurate about Activity 7001 in the precedence diagram?

A.

The successor FF lag from 7001 to 11001 is not shown

B.

The LF is correct

C.

The TF is not calculated correctly

D.

The LF is not correct

Go to page: