You'll find that our PSP exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these PSP sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Planning & Scheduling Professional (PSP) Exam practice test comfortably within the allotted time.

Question # 51

When are KPIs defined?

A.

At project initiation

B.

At NTP

C.

At the start of the Construction Phase

D.

After the Bidding Phase

Question # 52

Which letter of the alphabet best approximates the graphical shape of a project ' s cumulative cost baseline, or budgeted cost of work scheduled?

A.

C.

B.

B.

C.

S.

D.

W.

Question # 53

You are developing a detailed critical path schedule for a proposed petrochemical plant. The schedule will become a part of t he project baseline document, which will be sent to the company ' s board of directors for its consideration. What document or resource is likely to be MOST valuable in determining the schedule ' s work activity durations?

A.

Industry publications.

B.

Critica l path schedules prepared by you for similar completed projects.

C.

The Petrochemical Industry New Plant Task Duration Handbook.

D.

The cost estimate for the plant prepared by your firm ' s estimating department.

Question # 54

What project cost elements would NOT normally be reflected in the Activity 1000?

A.

Home office expenses

B.

CPM processing and updating

C.

Materials used in the construction

D.

Job site quality control

Question # 55

Using one crane capable of 30 lifts per day. for 3 column pours requiring 28 lifts each, plus assorted work in the area requiring an additional 150 lifts, what are the lowest planned workdays for this work?

A.

3 workdays

B.

18 workdays

C.

8 workdays

D.

7 workdays

Question # 56

Project delays are best analyzed

A.

After either the contractor or the owner acknowledges ^responsibility for the delay.

B.

Contemporaneously with the delay.

C.

By an expert after the project is finished when complete records are available and the impact is known.

D.

Late in the project.

Question # 57

Using the " normal " schedule, given Activity 3001 and the relationship with Activity 4001, what is indicated?

A.

These activities are concurrent with Activity 4001 starting 15 days after the start of Activity 3001.

B.

These activities are concurrent with Activity 4001 starting 15 days earlier than the start of Activity 3001.

C.

The activities occur in series with a 15-day lag.

D.

The activities run concurrently.

Question # 58

What owner action could have mitigated the late completion of the project?

A.

Hire a more senior project manager.

B.

Self-perform more of the work.

C.

Use a procurement agent to monitor and expedite equipment deliveries.

D.

Prepare better structural steel drawings.

Question # 59

A driving relationship is _____________________.

A.

A critical relationship.

B.

A finish-to-start relationship.

C.

The link between two related activities.

D.

The link between a predecessor and the activity whose dates it controls.

Question # 60

In a " crashed " schedule, which is a chain of activities that precede activity 2004?

A.

1001, 2001, 2002, 2003

B.

2001, 2002, 2003, 2007

C.

1001, 2002, 2003

D.

1001, 2002, 2002, 2003, 3001