You'll find that our PSP exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these PSP sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Planning & Scheduling Professional (PSP) Exam practice test comfortably within the allotted time.

Question # 41

Identify the late finish to develop plans and specs.

A.

9 months.

B.

10 months.

C.

8 months.

D.

7 months.

Question # 42

The work breakdown structure is used to organize

A.

" Smart activity ID codes " representing similar items of scheduled work

B.

The chart of accounts

C.

Similar activity coding of schedule activities

D.

The smallest defined work packet

Question # 43

Using the normal schedule, what is the owner ' s total cost of the project?

A.

S13.990.600

B.

S12.990.000

C.

S13.102.900

D.

S12.953.600

Question # 44

Which activity is drawn in the incorrect position?

A.

Activity G.

B.

Activity E.

C.

Activity C.

D.

Activity D.

Question # 45

SUBCO is a potential concrete bridge contractor based in a metropolitan area 300 miles away from your project. They have offered to supply manpower and equipment t BILCO at a per diem rate of $3,000 above their dir ect labor and equipment rates. In doing a cost benefit analysis, which of the following is NOT a consideration?

A.

SUBCO direct labor and equipment rates

B.

BILCO liquidated damages in the SDOT contract

C.

Pending negotiations with GOUGE.

D.

The distance o f SUBCO to your project

Question # 46

How many entities/subcontractors should a scheduled activity cover?

A.

More than one it the activity is in a single calendar period

B.

More than one it the subcontractors agree

C.

Only one

D.

More than one if the concurrent work cannot be split between subcontractors

Question # 47

What is the cycle time?

A.

5 minutes

B.

17 minutes

C.

14 minutes

D.

6 minutes

Question # 48

Considering the information provided for the project, what is the factor that most influences the successful crashing of the schedule?

A.

Avoiding a late delivery penalty from the owner

B.

Maximizing the $500,000 bonus

C.

Avoiding the 2023-2024 winter/wet weather season

D.

Minimizing the indirect expenditure chargeable to the contractor

Question # 49

Based on the stated costs, what percentage of the total cost comes from the 2000 series of activities?

A.

3.3%

B.

2.2%

C.

23%

D.

2 4%

Question # 50

During proofing of the product manual, a problem was discovered requiring 15 days additional time to affect a correction. How can the date of availability be maintained?

A.

Expedite Draft Product Manual by 5 days

B.

Delay Release for Manufacture by 5 days

C.

Delay Manufacture Product by 5 days

D.

Expedite Package Product by 5 days