You'll find that our PSP exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these PSP sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Planning & Scheduling Professional (PSP) Exam practice test comfortably within the allotted time.

Question # 31

Determine the correct formula and date for the late start for Activity 9001.

A.

The early finish is required in order to determine the answer.

B.

LS.6001 Dur.6001 - > 11-20-02.

C.

There is insufficient data provided to calculate the answer.

D.

LF.9001 Dur.9001 - > 11-20-02.

Question # 32

The Scope of Work divides the major deliverables into smaller more manageable components for all of the following EXCEPT to:

A.

improve the accuracy of cost, time, and resource estimates

B.

facilitate clear responsibility assignments

C.

define a baseline for performance measurement and control

D.

establish the Performance Measurement Baseline values

Question # 33

Which of the following risks CANNOT be estimated by BILCO with only a resource-loaded schedule?

A.

Delay due to SDOT ' s other projects

B.

Delay due to labor shortage

C.

Liquidated damages on the SDOT contract

D.

Cost overruns due to cement shortage

Question # 34

Activity durations are normally estimated in an intuitive and subjective way. All of the following will improve duration accuracy EXCEPT

A.

Use gross building square footages. The pluses and minuses all average out.

B.

Look at each activity independently and don ' t follow specific logic paths when assigning activity durations.

C.

Divide activities into smaller activities. This will increase activity detail and duration estimate accuracy.

D.

Use the people responsible for performing the work as a resource to assign activity durations.

Question # 35

When should the project documents be reviewed to assess their impact on the organization and administration of a project?

A.

After the Award and before the NTP

B.

During the Bid Phase

C.

Before the commercial decision to Did on the project

D.

After the NTP

Question # 36

All the following describe the critical path of a schedule EXCEPT:

A.

Determined by network logic and is the chain of activities that controls the overall project completion time.

B.

Frequently defined as the shortest path through the schedule.

C.

Changed by redefining the network logic or changing activity durations or both.

D.

The series of activities having the least amount of total float.

Question # 37

The amount of time that an activity can be delayed from its early start date without delaying project completion is called:

A.

Negative float.

B.

Free float.

C.

Total float.

D.

Interfering float.

Question # 38

Scenario:

The entire network consists of the following activities and relationships. Activity A is twenty days long and is tied to Activity B, a ten-day activity, with a finish-to-finish tie with a lag value of five Activity B is tied to Activity C, a twenty-day activity, with a start-to-start relationship with a lag value of five.

PSP Activities Table

Scope Known about Rock-Filled Dam Project :

The dam requires river diversion and work over two or more rainy seasons. The contract is lump sum, competitively bid, and will be self-performed. The owner has attempted to shift all risk to the contractor by employing " no differing sit conditions " and " no damage for delay " clauses. There is a bonus/penalty provision of $2,500 per calendar day for early or late delivery. The early completion bonus is capped at $500,000, with no cap for late delivery penalty.

Liquidated damages end at the finish of demobi lization. Indirect costs per calendar day are $2,800 for the " normal " schedule and $3,200 for the " crashed " schedule. The winter/wet weather season is 151 days between October 15 and March 25 of each year, reduces the efficiency of the contractor ' s operati ons by 20% and costs the contractor $10,000 per day. Assume a start date of March 5, 2001 and use a 7-day work week.

The following table lists work activities as planned by the contractor.

Theoretically construct a summary activity for only those activi ties with a finish-to-start relationship for Activities 8001 through 10001. Using the " normal " schedule, what is the cost of this hammock?

A.

$420,000.

B.

$307,000.

C.

$524,000.

D.

$552,000.

Question # 39

Why does activity 11001 not show successor activities?

A.

The early finish and late finish are circular

B.

It is the penultimate work required for the project

C.

The scheduler forgot to add the successor activities

D.

It is the final activity for the required work for the project

Question # 40

Which of the following will NOT affect the total float calculation of a non-resource leveled schedule?

A.

Multiple calendars.

B.

Start and finish constraints.

C.

Preferential logic.

D.

Front end loading.