Planning & Scheduling Professional (PSP) Exam

Last Update 6 hours ago Total Questions : 216

The Planning & Scheduling Professional (PSP) Exam content is now fully updated, with all current exam questions added 6 hours ago. Deciding to include PSP practice exam questions in your study plan goes far beyond basic test preparation.

You'll find that our PSP exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these PSP sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Planning & Scheduling Professional (PSP) Exam practice test comfortably within the allotted time.

Question # 61

For the late finish for Activity 11001, select the most appropriate response for transitioning from the forward pass.

A.

LS.11001 + 25 days.

B.

02-19-04.

C.

EF.11001.

D.

EF.11001 + 1 day.

Question # 62

If Activity E ' s duration changes to 4 months, what is the overall duration of the project.

A.

19 months.

B.

20 months.

C.

22 months.

D.

21 months.

Question # 63

Which of these letters, symbols or words best approximates the graphical shape of a project ' s cumulative BCWS?

A.

/

B.

Bell curve

C.

S

D.

_

Question # 64

What is a key first step in developing a critical path method schedule?

A.

Drawing a bar chart of the key phrases of the work.

B.

Defining the execution plan to meet the required scope of work.

C.

Setting out the resource to be used and its limitations .

D.

Drawing the logic diagram.