You'll find that our RCDDv14 exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these RCDDv14 sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any BICSI Registered Communications Distribution Designer – RCDDv14 practice test comfortably within the allotted time.

Question # 31

A request for proposal (RFP) yields a bid with a better delivery schedule and a lower cost, but originates from a vendor not on the prequalified vendor list During the final review of the RFPs the program manager is informed that the new bidder is a relative of the project manager. Although the bid meets all company policies, the program manager is concerned about a conflict of interest.

What should the program manager do?

A.

Select the best bid from the prequalified vendor list

B.

Accept the bid from the new vendor and document the decision.

C.

Advise the sponsor of a possible conflict of interest prior to awarding the bid

D.

Add the new vendor to the prequalified list and replace the project manager

Question # 32

A large program consists of several component projects and six project managers. The program governance board requests that all components within the program undergo user acceptance testing before being released to the production environment

Where should the program manager document this?

A.

Program governance plan

B.

Program requirements

C.

Component test plan and test cases

D.

Program quality management plan

Question # 33

Who prepares the submittals that are reviewed and approved to ensure that the clients design criteria is met in regards to material selection?

A.

General Contractor

B.

ICT distribution designer

C.

Client

D.

Architect. Engineering, Consultant Team

Question # 34

A program manager is concerned because several change requests in a component project are causing delays to the program ' s work package milestones. There are insufficient skilled resources within the component project to complete both the change requests and the milestone tasks.

What should the program manager do next to address this risk?

A.

Prioritize which resources are critical to the project based on an impact analysis of the critical change requests and update the program roadmap.

B.

Prioritize which change requests are critical to the project based on an impact analysis, resource only critical change requests until overdue milestones are achieved, and update the risk register

C.

Mandate that no component project change requests will be processed until overdue milestones have been completed and update the risk register to reflect this

D.

Add the lack of skilled resources to facilitate the large number of change requests to the issue log

Question # 35

In a RFI, an ICT distribution designer instructs the contractor to test all the fibers In a PON Installation. Which of the following testing requirements does the designer include?

A.

Uni-directional 850 nm and 1300 nm

B.

Bi-directional 850 nm and 1300 nm

C.

Uni-directional 1310 nm and 1550 nm

D.

Bi-directional 1310 nm and 1550 nm

Question # 36

A program to implement a new payroll processing system at a healthcare company is nearing completion and is under budget. What should the program manager do next?

A.

Request permission from the program governance board to initiate program closure activities

B.

Present additional opportunities to the program sponsor

C.

Apply the remaining budget to operational activities

D.

Apply the remaining budget to deferred enhancement requests

Question # 37

When designing cable tray pathways under an access floor, what is the MINIMUM free space that should exist between the top of the cable tray side rails and the underside of the stringers?

A.

25 mm (1 in)

B.

51 mm (2 in)

C.

71 mm (3 in)

D.

101.60 mm (4 in)

Question # 38

A 3 trade size conduit is sized at

A.

78 mm (3 in)

B.

91 mm (3 1/2 in)

C.

103 mm (4 in)

D.

129 mm (5 in)

Question # 39

A component is scheduled to close at the end of the week. What should the program manager verity prior to allowing the component to close?

A.

The component has released resources to meet program objectives

B.

The component has met the quality requirements to meet program objectives

C.

The component has met the schedule requirements to meet program objectives

D.

The component has met the benefits realization criteria to meet program objectives

Question # 40

A program receives initial approval from the selection committee to proceed with the program development. What should the program manager do next " ?

A.

Define the program architecture and assign the benefits realization to the component projects.

B.

Complete the program setup to establish a firm foundation of support and approval for the program

C.

Analyze lessons learned and historical information to validate the programs expected outcomes

D.

Continue to develop the high-level program road map