You'll find that our LEED-AP-BD+C exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these LEED-AP-BD+C sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any LEED AP Building Design + Construction (LEED v5 AP BD+C) practice test comfortably within the allotted time.
The Lakeside Resort is a hotel in a rural area located about 60 mi. (96.6 km) from the nearest town, which has a population of 10,500. There are no other towns for over 200 mi. (321.9 km). The surrounding community is largely made up of ranches and federal- and state-owned land.
The project consists of a single building that includes the following:
• 150 guest rooms
• A small restaurant
• An indoor pool
• Conference spaces
• Event spaces
• Six tenant spaces
A lease has been secured for a future spa, gift shop, coffee shop, and tour operator. Two of the six tenant spaces have not yet been leased. The property is 10 acres, adjacent to a lake, and has trail access to public lands for hiking. It is anticipated that occupants will mostly arrive by car, but there is one public bus trip per day from the nearest town.
The project consists of the building, parking lots for overnight guests and daily visitors, a walking path to the lake, and hiking trails leading to the public lands. The project has a goal of being Gold certified under LEED for New Construction.
When determining occupancy for the project, how should the project team account for the occupancy for the future spa, gift shop, coffee shop, tour operator space, and the two unknown tenant spaces?
During the early stages of a LEED for Schools project, the team was able to reduce the number of lighting fixtures in classrooms by 25% because the project team selected paint color whose light reflectance value was 75% instead of the initially proposed 64% value. This strategy is an example of applying which of the following credits to the project?
Which of the following types of water should a project team focus on utilizing to achieve water savings and acquire points under WEc2: Enhanced Water Efficiency, Option 6. Water Reuse, Path 1. Reuse-Ready System, while reducing reliance on potable water?
During a design charrette, community neighbors raise a concern about potential glare resulting from a project ' s highly reflective roof. Which change should the LEED AP recommend to best address these concerns without negatively impacting other LEED credits?
Which of the following is true regarding LEED Pilot Credits?
For IPp2: Human Impact Assessment, the team wants to use the ground-floor spaces to achieve both social equity and occupant experience. Which design features would achieve this dual objective?
How much value would these two doors contribute toward Material and Resources Credit, Building Product Disclosure and Optimization – Sourcing of Raw Materials, Option 2. Leadership Extraction Practices?
When following the LEED Building Design and Construction Integrative Process credit, which of the following is the approach for the design team to follow?
According to Location and Transportation Credit, Sensitive Land Protection, Option 2: Floodplains requirement, projects that do not have legally adopted flood hazard maps should locate on a site that is:
When the project occupancy is not known, which method is recommended?