You'll find that our LEED-AP-BD+C exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these LEED-AP-BD+C sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any LEED AP Building Design + Construction (LEED v5 AP BD+C) practice test comfortably within the allotted time.

Question # 41

Which of the following are the major factors determining the total irrigation requirement for a particular landscaping design?

A.

Planting density, soil conditions, irrigation efficiency and rainfall

B.

Relative humidity, site exposure, plant species and planting density

C.

Plant species, rainfall, evapotranspiration rate, site exposure and irrigation efficiency

D.

Plant species, rainwater tank size, evapotranspiration rate, site exposure and irrigation efficiency

Question # 42

A luxury hotel project is in the design phase and is located on a scenic waterfront. It is one point away from attaining LEED Platinum certification. The LEED AP is recommending that the team pursue Innovation Credit, Innovation, Option 3. Additional Strategies. Which of the following credits would be desirable considering the location of the project?

A.

Energy and Atmosphere Credit, Optimize Energy Performance, Exemplary Performance

B.

Indoor Environmental Quality Credit, Quality Views, Exemplary Performance

C.

Indoor Environmental Quality Credit, Acoustic Performance, Exemplary Performance

D.

Energy and Atmosphere Credit, Enhanced Commissioning, Exemplary Performance

Question # 43

Which views would qualify as a quality view for Indoor Environmental Quality Credit, Quality Views?

A.

A, B, C

B.

B, C, D

C.

C, D, E

D.

A, B, D

Question # 44

Which approach will contribute to maintaining compliance with Sustainable Sites Credit, Rainwater Management?

A.

Installing bioretention area

B.

Installing on-site renewable power generation facility

C.

Substituting impervious surface area with high-albedo paving materials

D.

Increase artificial turf on the roof

Question # 45

Which of the following products are eligible for a WaterSense label?

A.

Tankless toilets

B.

Waterless urinals

C.

Public lavatory faucets

D.

Private lavatory faucets

Question # 46

The design team and project owner decided not to pursue Energy and Atmosphere Credit, Enhanced

Commissioning, but would hire a Commissioning Authority (CxA) to oversee the requirements for Energy and Atmosphere Prerequisite, Fundamental Commissioning and Verification. What is a required responsibility for the CxA to achieve the stated objective?

A.

Verify that training requirements are completed

B.

Develop systems manual for the commissioned systems

C.

Review contractor submittals for the commissioned systems

D.

Verify installation and performance of the commissioned systems

Question # 47

For an emergency care facility project, which of the following credits can be achieved if the total cost of

permanently installed products are 25% cradle-to-cradle V3 Gold and 25% GreenScreen List Translator?

A.

Materials and Resources Credit, Building Life-Cycle Impact Reduction, Option 3. Building and Material Reuse & Innovation Credit, Innovation, Exemplary Performance

B.

Materials and Resources Credit, Furniture and Medical Furnishing, Option 3. Multi-Attribute Assessment ofProducts & Innovation Credit, Innovation, Exemplary Performance

C.

Materials and Resources Credit, Building Product Disclosure and Optimization, Material Ingredients, Option 2.Material Ingredient Optimization & Innovation Credit, Innovation, Exemplary Performance

D.

Materials and Resources Credit, Furniture and Medical Furnishings, Option 3. Multi-Attribute Assessment ofProducts & Materials and Resources Credit, Building Product Disclosure and Optimization, Material Ingredients, Option 2. Material Ingredient Optimization

Question # 48

What issue must be present on the project site to achieve Location and Transportation Credit, High-Priority Site, Option 3. Brownfield Remediation?

A.

Mercury containing lamps

B.

Contaminated soil or groundwater

C.

Asphalt construction waste

D.

Asbestos tile and glue

Question # 49

A Core and Shell developer pursuing the IPc2 Green Leases credit has drafted lease language. Which provision meets the intent of the credit for binding tenant sustainability commitments?

A.

Tenant shall submit quarterly energy and water consumption reports and achieve a minimum 50% waste diversion rate verified through waste hauler documentation.

B.

Owner will provide tenant with LEED design guidelines and green building best-practices handbook within 30 days of lease execution for reference.

C.

Tenant acknowledges that the building has achieved LEED certification and agrees to maintain awareness of sustainable building operations during occupancy.

Question # 50

Which of the following could be considered diverted construction waste?

A.

Excavated soil

B.

Land-clearing debris

C.

Alternative daily cover

D.

Asphalt with aggregate