You'll find that our PSP exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these PSP sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Planning & Scheduling Professional (PSP) Exam practice test comfortably within the allotted time.

Question # 4

Considering the information provided for the project, what is the factor that most influences the successful crashing of the schedule?

A.

Avoiding a late delivery penalty from the owner

B.

Maximizing the $500,000 bonus

C.

Avoiding the 2023-2024 winter/wet weather season

D.

Minimizing the indirect expenditure chargeable to the contractor

Question # 5

For activity 11001. why would the crashed direct cost be greater than the direct cost of the normal schedule?

A.

Additional extended overhead is also being shown in this activity

B.

Some costs resulting from the crashed efforts were forgotten in previous activities

C.

Generally, more equipment is used for a crashed project; therefore, it costs more to demobilize

D.

Management bonuses for early completion were included in this activity

Question # 6

If drafting of the product manual overruns its planned duration by 5 days, how many days may the manufacturing be delayed without affecting release of the product?

A.

15 days.

B.

10 days.

C.

0 days.

D.

5 days.

Question # 7

Determine the correct formula and date for the late finish for Activity 9004.

A.

LS.10002 + 1 day -> 11-29-03.

B.

LS.10002^ Lag.7 + i day -> 11-20-03.

C.

LS.10002 - 1 day -> 11-27-03.

D.

LS.10002 - Lag.7 - l day -> 11-20-03.

Question # 8

Which of the following are NOT considerations or constraints of the planning process for construction scheduling?

A.

Consideration of all stakeholders.

B.

Value engineering.

C.

Project variables.

D.

Interest rate of owner's construction bonds.

Question # 9

Each of the following accurately describes total float in a schedule EXCEPT:

A.

The amount of time an activity can be delayed without delaying the overall project completion time.

B.

Can be positive or negative.

C.

The amount of time an activity can be delayed without delaying the start or occurrence of any other activity or event in the network.

D.

Computed for an activity by subtracting its early finish from its late finish, or its early start from its late start.

Question # 10

Activity 1001 started on the scheduled date but has slipped 10 days. Activity 10002 will slip 35 days. All remaining activities retain their original duration. What is the revised completion date?

A.

02-19-04

B.

03-21-04

C.

03-11-04

D.

03-20-04