You'll find that our PK0-005 exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these PK0-005 sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any CompTIA Project+ Certification (2026) practice test comfortably within the allotted time.

Question # 111

A highly scored negative risk causes a risk trigger, but the issue has not started yet. Which of the following is the next step the project team should take?

A.

Execute the contingency plan

B.

Perform a work-around

C.

Escalate to senior management

D.

Assign a risk owner

Question # 112

During the initiation phase, a stakeholder and the project manager discuss the business reasons and benefits of the project. The stakeholder requests these items be documented for approval. Which of the following should be used to document this information?

A.

Statement of work

B.

Business case

C.

Requirements document

D.

Work breakdown structure

Question # 113

A project manager is in the closing phase of an IT asset refresh project that involves the disposal of several computers. The project sponsor notified the project manager that the company recently received a penalty as a result of disposing of some computers improperly. Which of the following should have been considered during initial planning to prevent this situation?

A.

ESG

B.

PHI

C.

Pll

D.

ROI

Question # 114

A project sponsor has asked for a log listing all the bugs identified within a specific project. Which of the following tools should the project manager provide to the sponsor?

A.

Change log

B.

Issue log

C.

Risk register

D.

Defect log

Question # 115

A project manager is currently meeting with a vendor who completed the project work. All invoices associated with the project have been paid. Which of the following best describes the project manager ' s objective for the vendor meeting?

A.

Reassigning resources

B.

Removing access

C.

Closing contracts

D.

Evaluating the project

Question # 116

A project scheduler updates the project status with the following information: SPI = 1.25 and CPI = 0.85. Which of the following can the project manager infer about the current project status?

A.

The project is ahead of schedule and under budget.

B.

The project is behind schedule and over budget

C.

The project is ahead of schedule and over budget.

D.

The project is behind schedule and under budget

Question # 117

Which of the following best represents an intellectual property breach?

A.

Internal developers use code from a legacy in-house system to develop a new solution for the marketing department.

B.

The price list to end customers was stored on a stolen external hard drive.

C.

A service provider that worked on a project uses the developed software on a project for a new customer.

D.

Customer data is stored on a shared network drive that is accessible by employees from all departments.

Question # 118

A project manager reports that the implementation of a new system is on track to be completed under budget and ahead of the schedule. A stakeholder then asks the manager to add mobile device functionality. Which of the following should the project manager do in response to the request?

A.

Decline because it is not included in the project scope.

B.

Assess the impact of the request and create a change request

C.

Create new functional and non-functional requirements for mobile devices.

D.

Revise the baseline of the project plan by adding the new requirements.

Question # 119

During the planning phase, a project manager is mapping out the full scope, calculating task durations, and identifying dependencies. Which of the following is the best tool for the project manager to use?

A.

Gantt chart

B.

Milestone chart

C.

Velocity chart

D.

PERT chart

Question # 120

While a team was in a work session developing the QA plan for a project, the project manager realized that the team lacks the skills required for proper quality assurance. Which of the following steps should the project manager take next?

A.

Reassess the resource pool.

B.

Review the QA plan from a similar project.

C.

Check on available resources for additional team members.

D.

Escalate the issue to the project sponsor.