You'll find that our PK0-005 exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these PK0-005 sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any CompTIA Project+ Certification (2026) practice test comfortably within the allotted time.

Question # 121

A system is scheduled to go live, and the client signed an SLA. Which of the following elements is part of the agreement?

A.

Resolution time

B.

Issue list

C.

Work breakdown structure

D.

Cost optimization

Question # 122

During a kickoff call, a project was rejected by the legal department due to the risk of violating new legislation. Which of the following was applied?

A.

Awareness of the local environment

B.

Awareness of the brand value

C.

Awareness of the resource constraints

D.

Awareness of the company ' s mission

Question # 123

The goal of a project is to fulfill specific technical features requested by customers. Which of the following actions should the product owner take?

A.

Define the success criteria.

B.

Create a communication plan.

C.

Use a task board.

D.

Perform a root cause analysis.

Question # 124

A PM is working on the preliminary scope statement and identifies that this project has the same approach as another project that was completed last year. Which of the following actions would the PM most likely perform?

A.

Call the previous PM for advice on risks and issues.

B.

Ask the project sponsor to provide previous final project report results.

C.

Complete the project charter using the other PM ' s subject matter expertise.

D.

Use existing artifacts and accommodate based on the current project success criteria.

Question # 125

During a brainstorming session, a team member expressed concerns that solar flares could cause intermittent outages for those individuals working on the project. Which of the following would be the best tool to communicate this information to stakeholders?

A.

Status report

B.

Issue log

C.

Risk report

D.

Risk register

Question # 126

A project manager needs to update the project sponsor and senior stakeholders about the progress of a project. Which of the following tools will the project manager MOST likely use?

A.

Dashboard

B.

Gantt chart

C.

Work breakdown structure

D.

Requirements Traceability Matrix

Question # 127

A project manager is reviewing quality planning techniques. Which of the following involves comparing results of similar activities?

A.

Performing a cost-benefit analysis

B.

Defining metrics

C.

Benchmarking

D.

Brainstorming

Question # 128

A developer recommends modifying an existing portion of code that is not part of the scope and is causing low performance on the current solution. Which of the following actions should the project manager most likely take?

A.

Ask a developer to create a change request.

B.

Do nothing because recommendation is scope creep.

C.

Ask a developer to implement the recommendation.

D.

Communicate the change status.

Question # 129

A contractor attended a project meeting that was exclusively for company employees. Which of the following actions should the PM take?

A.

Escalate to vendor management.

B.

Consult the request for proposal.

C.

Review the meeting cadence.

D.

Reinforce the rules of engagement.

Question # 130

Which of the following items must be protected as Pll? (Select TWO).

A.

Job title

B.

Home address

C.

Work phone number

D.

Time zone

E.

Date of birth