You'll find that our RCDDv14.1 exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these RCDDv14.1 sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any BICSI Registered Communications Distribution Designer – RCDDv14.1 practice test comfortably within the allotted time.

Question # 11

A critical program for a company fails lo delivers its intended benefits. The CEO and program sponsor are both held accountable and. ultimately, their employment is terminated by the board of directors

What should the program manager do before formally closing the program?

A.

Update the benefits register

B.

Establish a program management information system (PMIS)

C.

Share lessons learned with an program team members

D.

Transfer all program documentation to the deputy program manager

Question # 12

A program manager learns that their company ' s organizational strategy has changed This change impacts one component project of a program misaligning it with both the program objectives and the new organizational strategy This component project, however, is already 90 percent complete.

What should the program manager do next?

A.

Immediately submit a component project closure request to the program sponsor so that resources can be reallocated to strategically aligned component projects.

B.

Assess the impact of closure on other component projects, and generate a recommendation for submission to the program governance board

C.

Recommend that the component project manager complete work activity to deliver benefits to the organization

D.

Update the benefits management plan to reflect the impact of the change on the program and its intended benefits

Question # 13

Which type of protection for electrical power stations provide isolation against a rise in potential of station ground and also provide drainage protection against longitudinally-induced voltages?

A.

Isolating transformers

B.

Neutralizing transformers

C.

Mutual drainage reactors

D.

Unit-type neutralizing transformers

E.

2-winding neutralizing transformers

Question # 14

In which of the following design phases does the ICT distribution designer perform coordination with stakeholders and other disciplines (e.g.. mechanical, architectural, electrical) to ensure that the design is constructive and that any conflicts are resolved early in the process?

A.

Concept Design

B.

Design Development (DD)

C.

Schematic Design (SD)

D.

Construction Document (CD)

Question # 15

The program manager wants to increase the team ' s commitment to the program objectives. The program manager should do which of the following?

A.

Work with the sponsor lo identify the organization ' s best practices

B.

Work with the program stakeholders and program management office to identify the organization ' s best practices

C.

Work with the program management office to identify the organization ' s best practices

D.

Work with the sponsor, program stakeholders, and the program management office to identify the organization ' s best practices

Question # 16

For a six story building (plus a basement) each of the six floors has a useable area of =3716 m2 (40.000 ft2) There are two riser systems, each serving halt of the useable area on each Moor What are the sleeves quantity and configuration required from fifth floor to sixth floor?

A.

Two sleeves

B.

Three sleeves

C.

Four sleeves

D.

Five sleeves

Question # 17

When designing for horizontal pathways in an environment that requires fire-stopping for penetrating a rated wall, what is the MAXIMUM till ratio for telecommunications cabling in a cable tray?

A.

20 percent

B.

40 percent

C.

50 percent

D.

There is no fill ratio for cable tray

Question # 18

The type of apparatus housed in ERs varies greatly in size, purpose and function. Which two of the following active equipment is included? (Select two options.)

A.

Cross-connect facilities

B.

Telecommunication’s equipment

C.

Environmental controls

D.

Lighting controls

E.

Building system equipment

Question # 19

A municipal agency manages a city ' s water and wastewater infrastructure. A regulation requires the replacement of sewer lines throughout the city at a cost of US$2 billion over 30 years

The city has been managing this program with various program teams, and has a project controls office In place to track protects separate from the program management team A program manager is hired to standardize all deliverables from component projects under the program.

What should the program manager do next?

A.

Develop a program management framework

B.

Create a program performance analysis report

C.

Generate a program charter

D.

Establish a program management office (PMO)

Question # 20

Program A is dependent upon program B lo complete benefits sustainment for two benefits Program A is on track to meet program benefits However program B ' s program manager has just advised that program B has been closed.

What should program A ' s program manager update and review first with the stakeholders?

A.

Benefits sustainment plan

B.

Benefits register

C.

Benefits management plan

D.

Benefits transition plan