You'll find that our RCDDv14.1 exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these RCDDv14.1 sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any BICSI Registered Communications Distribution Designer – RCDDv14.1 practice test comfortably within the allotted time.

Question # 71

The program sponsor requests a weekly performance report. The tools and techniques to monitor and control program performance include which of the following?

A.

Program management performance variances business criteria reweighting, root cause identification, and statistical sampling

B.

Interviewing, SWOT analysis, run chart and matrix-based charts

C.

Earned value management financial reporting systems, performance measurement techniques and program management information systems

D.

Delphi technique, scatter diagram. Pareto chart, and organization charts

Question # 72

An organization initiates an innovation program to deliver exceptional performance and benefits. After the program transition plan is in place and the implementation of a benefits sustainment plan starts the program manager discovers the program may be shut down due to lack of funding.

To ensure continued funding for the program, what should the program manager do next?

A.

Complete the benefits sustainment plan and update the benefits register

B.

Present a revised ROl to the program sponsors based on the remaining investment.

C.

Conduct a cost-benefit analysis to ensure the program sponsors understand the program ' s long-term benefits

D.

Review the program business case and the program ' s strategic alignment and long-term benefits with the program governance board.

Question # 73

A client hired an ICT distribution designer who is designing some additional capacity for a customer owned aerial outside plant. Which of the following would be a PRIMARY consideration?

A.

Clearances will still be adequate with the added equipment.

B.

That all of the poles on the path are at least Class 3.

C.

Sufficient space exists to install additional guying if required.

D.

Utility coordination with public utilities verifies minimum inductive interference.

Question # 74

When should a program manager approve the closure of a component project?

A.

When acceptance criteria of the project are met

B.

When the project has delivered the protect benefits

C.

When program deliverables are complete

D.

When project deliverables are complete

Question # 75

Which of the following team members is responsible for ensuring compliance with me contract documents (CD)?

A.

Owner

B.

lCT Distribution Designer

C.

Architect

D.

Construction Manager (CM)

Question # 76

A global financial system is being delivered by the program learn to allow access from anywhere in the world Following a new cross-border regulation applying to privacy of local banking data accessed from abroad, the CEO of the bank requests that an external audit be conducted lo validate compliance with this new regulation. This event, which was not anticipated al this phase of the program, will generate additional work tor the program learn. This effort Is not included in the current program roadmap and benefits delivery plan

What immediate actions should the program manager take?

A.

Negotiate with the CEO in an attempt to avoid the audit.

B.

De-scope the capabilities of the system to not allow access from abroad

C.

Accept the risk of the audit and continue the program as planned

D.

Assess the impact of the audit and potential remediation on the program

Question # 77

The customer of a three-year program does not want to receive any intermediate details on the program. The program appears to be in trouble and the customer is concerned about a new system ' s cost. The program manager has provided monthly performance reports throughout the program ' s lite cycle.

Which of the following would the customer be interested in reviewing?

A.

Estimate to complete

B.

Estimate at completion

C.

Original cost baseline

D.

Cost performance index

Question # 78

A program manager needs to establish direction and identity the essential aspects of a program. In addition, they must ensure that the context and framework of the program are properly defined assessed and documented

Which document will be created to support this activity?

A.

Program resource management plan

B.

Program management plan

C.

Program master schedule

D.

Program scope statement

Question # 79

During program execution, a program manager receives feedback from an executive sponsor (hat some program stakeholders may not understand the intended benefits of the program. Which will provide the greatest value to clarify stakeholder perceptions?

A.

Performing a stakeholder analysis

B.

Updating the stakeholder communications requirements

C.

Redistributing the benefits management plan

D.

Redistributing the program charter

Question # 80

The program manager must define the program and understand the organization ' s target market and customer needs. What should the program manager do first?

A.

Brainstorm with the program team to decide on the definitions of the target market.

B.

Meet with peers to identify the company ' s competitors in the target market

C.

Meet with the project managers to identify the target market

D.

Work with the program sponsor to assess the needs of the target market