Spring Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: buysanta

Exact2Pass Menu

BICSI Registered Communications Distribution Designer – RCDDv14.1

Last Update 3 hours ago Total Questions : 320

The BICSI Registered Communications Distribution Designer – RCDDv14.1 content is now fully updated, with all current exam questions added 3 hours ago. Deciding to include RCDDv14.1 practice exam questions in your study plan goes far beyond basic test preparation.

You'll find that our RCDDv14.1 exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these RCDDv14.1 sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any BICSI Registered Communications Distribution Designer – RCDDv14.1 practice test comfortably within the allotted time.

Question # 41

What is the MINIMUM fire rating for telecommunications spaces walls and wall linings, if not specified otherwise by local Authority Having Jurisdiction (AHJ)?

A.

One hour

B.

Two hours

C.

Three hours

D.

No minimum requirement

Question # 42

A program manager initiates a developmental program. Significant resources and funding are required (or early activities until the program cost and budget estimates are complete

What should the program manager do to understand the financial environment?

A.

Map costs to the expected benefits realization

B.

Establish intermediate budget based on historical information

C.

Establish program financial framework

D.

Obtain intermediate funding from the executive sponsor

Question # 43

The program director of a four-year program, estimated to require 600.000 person-days effort, notices that team morale has decreased over the last three months. The program is at a critical stage with 70% completion through the last phase. A number of defects are found that result in teams working additional hours. The program director requests that the program management office (PMO) gather metrics to monitor the situation

Which of the following metrics should the PMO capture on a monthly basis?

A.

Billable hours charged to the program, non-billable hours charged to the program, quantity of defects per full-time equivalent (FTE)

B.

Absenteeism rate staff turnover quantity of defects, total hours worked average number of FTEs

C.

Amount of hours spent on rework of software coding retesting, and on non-rework activities

D.

Absenteeism rate staff turnover and leave liability

Question # 44

A program manager is concerned because several change requests in a component project are causing delays to the program ' s work package milestones. There are insufficient skilled resources within the component project to complete both the change requests and the milestone tasks.

What should the program manager do next to address this risk?

A.

Prioritize which resources are critical to the project based on an impact analysis of the critical change requests and update the program roadmap.

B.

Prioritize which change requests are critical to the project based on an impact analysis, resource only critical change requests until overdue milestones are achieved, and update the risk register

C.

Mandate that no component project change requests will be processed until overdue milestones have been completed and update the risk register to reflect this

D.

Add the lack of skilled resources to facilitate the large number of change requests to the issue log

Question # 45

A key stakeholder ' s requirement contradicts the organization ' s strategic objectives. The program manager meets with the stakeholder but is unable to reach a compromise on the requirement

What should the program manager do first?

A.

Meet with the program management office to update the benefits management plan

B.

Meet with the organization ' s strategic planning committee to obtain clarification

C.

Meet with the program sponsor to address the issue

D.

Meet with the customer to determine if the stakeholder ' s requirement is valid

Question # 46

A program is in its execution phase when a component project manager suggests a potential change that could increase the financial benefit of the program. The program manager is hesitant to submit a change request, as it would extend the program schedule and require a scope change.

To whom should the change request be presented?

A.

The program governance board

B.

The program customer

C.

The program management office (PMO)

D.

The protect governance board

Question # 47

Which two of the following items should be considered for inclusion in a comprehensive working outline of a SoW? (Select two options.)

A.

Schedule

B.

Contract administration

C.

Legal matters

D.

Technical considerations

E.

Financial matters

Question # 48

What is the MAIN concern with a poke-thru installation?

A.

The compatibility with the telecommunications outlet/connector

B.

The structural integrity of the floor assembly

C.

The fact that it is beneath the floor

D.

The diameter of the poke-thru device

Question # 49

Which of the following serves as a guiding principle for a program manager when preparing a program work breakdown structure?

A.

Decompose the program work based upon available resources

B.

Decompose the program to the work package level

C.

Decompose the program lo the architecture baseline level

D.

Decompose the program at a level sufficient to achieve control

Question # 50

Which of the following is a consideration for lighting telecommunication spaces?

A.

To ensure worker safety within TEs. Light level requirements are higher tor these than other spaces

B.

The light fixtures within telecommunications spaces shall be fluorescent type fixtures.

C.

The electrical power for lighting shall be connected to the same electrical panel as the telecommunications equipment.

D.

The lighting layout shall be coordinated with the equipment and pathway locations

Go to page: