You'll find that our Prince2-Foundation exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these Prince2-Foundation sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any PRINCE2 7 Foundation written Exam practice test comfortably within the allotted time.

Question # 51

Identify the missing words in the following sentence.

The 'directing a project' process starts when [ ? ] and is triggered by the request to initiate a project.

A.

the 'starting up a project' process is completed

B.

the project mandate has been approved by the project board

C.

the project board has agreed the project strategies

D.

corporate, programme management or the customer have authorized a project

Question # 52

Which theme estimates the cost of delivering the project?

A.

Business case

B.

Change

C.

Plans

D.

PROGEESS

Question # 53

Which product identifies how often stakeholders require information?

A.

Communication management approach

B.

Quality management approach

C.

Change control approach

D.

Risk management approach

Question # 54

Who represents the three project interests on a project?

A.

Project manager

B.

Project support

C.

External project stakeholders

D.

Project board

Question # 55

What theme provides all management levels within the project management team with mechanisms for monitoring and control?

A.

Progress

B.

Change

C.

Organization

D.

Quality

Question # 56

What is the first task of product-based planning?

A.

Produce the Initiation Stage Plan

B.

Write the Project Product Description

C.

Identify dependencies

D.

Create the product breakdown structure

Question # 57

Which is an objective of the Closing a Project process?

A.

Review and approve the plan for project closure

B.

Review the performance of the project against its baseline

C.

Perform any post-project reviews

D.

Create a Benefits Review Plan

Question # 58

Which statement defines a risk?

A.

A certain event occurring in the future that will have a negative impact on the project's objectives

B.

An event that has already occurred that the Project Manager must deal with immediately

C.

An uncertain event, or set of events that, should it or they occur, will have an effect on the achievement of objectives

D.

An uncertain event, or set of events that, should it or they occur, will be automatically escalated to the Project Board for a response

Question # 59

Which should be funded from a change budget?

A.

The Starting up a Project process

B.

A fallback plan

C.

An agreed change to the scope of a project

D.

A change to a plan, within allocated tolerances, due to poor estimating

Question # 60

Which PRINCE2 principle is supported by the setting of tolerances for the three levels of plan?

A.

Manage by stages

B.

Manage by exception

C.

Continued business justification

D.

Learn from experience