You'll find that our Prince2-Foundation exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these Prince2-Foundation sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any PRINCE2 7 Foundation written Exam practice test comfortably within the allotted time.

Question # 91

In which product does a Project Manager define the time and cost tolerances for the work to be done by a Team Manager?

A.

Product Description

B.

Team Plan

C.

Work Package

D.

Stage Plan

Question # 92

What is the definition of a project outcome?

A.

A measurable improvement that is perceived as an advantage by one or more stakeholders

B.

The reason for the project

C.

The result of the change derived from using the project's outputs

D.

The project's specialist products.

Question # 93

Which product identifies the management stages and timescales of a project?

A.

Project Brief

B.

Project Product Description

C.

Project Plan

D.

Initiation Stage Plan

Question # 94

Which statement applies to Stage Plans?

A.

Always have the same duration as the Project Plan

B.

Are produced at the same time as the Project Initiation Documentation

C.

Assist the Project Manager in the day-to-day running and control of the project

D.

Provide a baseline against which the Project Board monitor overall progress

Question # 95

How many management stages should a PRINCE2 project consist of?

A.

Start up stage, initiation stage and at least one other management stage to cover the remainder of the project

B.

Start up stage, at least one other management stage to cover the remainder of the project and a closing stage

C.

Initiation stage and at least one other management stage to cover the remainder of the project

D.

Start up stage, initiation stage and a closing stage

Question # 96

Which is NOT a purpose of a Benefits Review Plan?

A.

Define the period over which the cost-benefit analysis will be based

B.

Describe how to measure the performance of the project's products in operational use

C.

Define the scope, timing and ownership of the benefit reviews required

D.

Describe how to measure and confirm any benefits that are to be realised after the project is closed

Question # 97

Identify the missing word(s) in the following sentence. PRINCE2 recommends three levels of [ ? ] to reflect the needs of the different levels of management involved in a project.

A.

Management strategies

B.

Plan

C.

Stakeholder interests

D.

Time-driven controls

Question # 98

Which of the following statements about the Closing a Project process are true?

1. The Closing a Project process provides a fixed point for the receipt of completed Work Packages for the work performed in the final stage.

2. The Closing a Project process provides a fixed point to review if the objectives set out in the original Project Initiation Documentation have been achieved.

A.

Only 1 is true

B.

Only 2 is true

C.

Both 1 and 2 are true

D.

Neither 1 or 2 are true

Question # 99

Whose approval is needed to replace a Stage Plan with an Exception Plan?

A.

Corporate or programme management

B.

Project Board

C.

Project Manager

D.

Team Manager

Question # 100

Which role is responsible for creating Checkpoint Reports?

A.

Senior Supplier

B.

Team Manager

C.

Change Authority

D.

Project Support