You'll find that our Prince2-Foundation exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these Prince2-Foundation sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any PRINCE2 7 Foundation written Exam practice test comfortably within the allotted time.

Question # 81

According to the ‘exception management’ technique, when should the team manager raise an issue?

A.

When the team manager predicts that a product will cause a stage to exceed its time tolerance

B.

When the team manager identifies that a product is going to be delivered late

C.

when the team manager predicts that a product will cause a work package to exceed its time tolerance

D.

when the team manager identifies that the work package has already exceeded its time tolerance

Question # 82

Identify the missing word(s) in the following sentence.

The 'controlling a stage' process is used to manage and control each [ ? ] of a project.

A.

delivery step

B.

benefit

C.

delivery stage

D.

team plan

Question # 83

Which is a purpose of the 'initiating a project' process?

A.

To ensure the project has a sound basis before asking the project board to authorize the project

B.

To authorize the stage plan for the next management stage of the project

C.

To establish a contract between the project management team and the commissioning organization

D.

To ensure that prerequisites are in place before starting the project

Question # 84

Which management level should approve a course of action if project-level tolerance is exceeded?

A.

Corporate, programme management or the customer

B.

Project board

C.

Project manager

D.

Team manager

Question # 85

Identify the missing words in the following sentence.

PRINCE2 requires that the business case is formally verified by [?] at stage boundaries.

A.

corporate, programme management or the customer

B.

the project board

C.

the project manager

D.

the change authority

Question # 86

Which does the Executive need to ensure is in place before the project is initiated?

A.

All Work Packages are authorized

B.

An understanding of how the project will contribute to corporate objectives

C.

The Project Plan has been approved

D.

The Project Initiation Documentation is complete

Question # 87

Which should be funded by a change budget?

A.

Increase in agreed scope

B.

Initiation stage

C.

Change Authority

D.

Handover activities

Question # 88

A product can NOT be supplied to meet all of the requirements in its baselined Product Description. What first action should be taken?

A.

Raise a request for change

B.

Raise an off-specification

C.

Write an Exception Report

D.

Amend the Work Package

Question # 89

If the Project Board instructs the Project Manager to implement a request for change, which document would contain details of that change?

A.

Checkpoint Report

B.

Highlight Report

C.

Issue Report

D.

Product Status Account

Question # 90

Why is it crucial that the Project Product Description clearly defines acceptance methods?

A.

Enables Project Assurance to authorize quality activities

B.

Defines how all project products will be reviewed and approved

C.

Defines how it will be proven that the completed project product meets the customer's expectations

D.

Provides confirmation that all project products have met their quality criteria